AGENDA ITEM:Consideration of approval of Change Order No. 2 to Absolute Group for
the Prairie Rose Trail Project increasing the contract amount by
$35,106.30.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 is for grading to reshape the
west bank of the pond north of NW Douglas Parkway to eliminate steep drop off, unknown storm
drain repairs at the east and west bridge abutments, addition of a concrete pier to support the trail
tying into the box culvert under NW Douglas Parkway and installation of a rock trench to help
drainage at the south end of the box culvert under NW Douglas Parkway.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $35,106.30.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Change Order No. 2
ATTACHMENTS: I. Change Order No. 2
II. Letter of Recommendation
PREPARED BY:Lisa Bauman
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1E8
Absolute Group, Inc.
PO Box 430
1800 Burr Oak Blvd
Granger, IA 50109
Project:
To:
Description of Proposed Change:
Item Quantity Units Unit Price Amount
1 1 LS 11,000.00$ 11,000.00$
2 1 LS 1,500.00$ 1,500.00$
-$
-$
-$
Accepted:
By: By:
Date: Date:
12,500.00$ Total
2
City of Waukee Absolute Group, Inc.
Additional Days Requested:
Pond Grading - Dozer, Skid Loader, Excavator
Mobe
Description
Pricing to reshape the west bank of the pond located north of Douglas Ave. Excess material will be spread onsite shown in the
attachement. This price does not cover haul off of material. Figured 2.5 days with a grading crew consisting of 3 operators, dozer, skid
loader, and excavator.
Change Order Proposal
Prairie Rose Trail
City of Waukee Job Number: 03PM-24002
Date: 9/19/2024
Absolute Group, Inc.
PO Box 430
1800 Burr Oak Blvd
Granger, IA 50109
Project:
To:
Description of Proposed Change:
Item Quantity Units Unit Price Amount
1 1 LS 10,570.00$ 10,570.00$
Accepted:
By: By:
Date: Date:
10,570.00$ SubTotal
1
Markup
Total
1,057.00$
11,627.00$
City of Waukee Absolute Group, Inc.
Additional Days Requested:
60' Trail Bridge Revisions
Description
See attached description.
Change Order Proposal
Prairie Rose Trail
City of Waukee Job Number: 03PM-24002
Date: 9/13/2024
Absolute Group, Inc.
PO Box 430
1800 Burr Oak Blvd
Granger, IA 50109
Project:
To:
Description of Proposed Change:
Item Quantity Units Unit Price Amount
1 1 LS 3,163.00$ 3,163.00$
Accepted:
By: By:
Date: Date:
24" Clay Tile Repair
Description
Murphy Heavy Contracting discovered 24" clay tile while installing rip rap on the 60' Prairie Rose Trail bridge. The price below is to
relace the damaged section of 24" clay tile with 24" corrugated plastic tile.
Change Order Proposal
Prairie Rose Trail
City of Waukee Job Number: 03PM-24002
Date: 9/24/2024
City of Waukee Absolute Group, Inc.
Additional Days Requested:
3,163.00$ SubTotal
1
Markup
Total
316.30$
3,479.30$
Absolute Group, Inc.
PO Box 430
1800 Burr Oak Blvd
Granger, IA 50109
Project:
To:
Description of Proposed Change:
Item Quantity Units Unit Price Amount
1 12 EA 500.00$ 6,000.00$
2 75 LF 20.00$ 1,500.00$
Accepted:
By: By:
Date: Date:
12"x60" Concrete Pier
3'x1' Rock Trench
Description
Piers under trail approaches at Douglas box culvert. Rock trench along trail north of Douglas box culvert.
Change Order Proposal
Prairie Rose Trail
City of Waukee Job Number: 03PM-24002
Date: 9/10/2024
City of Waukee Absolute Group, Inc.
Additional Days Requested:1
Total 7,500.00$