HomeMy WebLinkAbout2024-10-21 I06B West Area Trunk Sewer Extension Phase 2_Accept ImprovementsAGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: October 21, 2024
AGENDA ITEM:Consideration of approval of a resolution accepting public improvements
[West Area Trunk Sewer Extension Phase 2]
FORMAT:Resolution
SYNOPSIS INCLUDING PRO & CON:
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Veenstra & Kimm has reviewed the public
improvements for the West Area Trunk Sewer Extension Phase 2 project
and find it in substantial conformance with the project plans and
specifications.
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Resolution
PREPARED BY:Lisa Bauman
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I6B
RESOLUTION 2024-
RESOLUTION ACCEPTING THE WEST AREA TRUNK
SEWER EXTENSION - PHASE 2
WHEREAS, on the 18th day of July, 2022, the Mayor and Clerk of the City of Waukee,
Iowa, entered into a construction contract with Rognes Corporation of Ankeny, IA, for the
construction of certain public improvements generally described as the West Area Trunk Sewer
Extension - Phase 2; and
WHEREAS, the contractor has fully completed the construction of the public
improvements in accordance with the terms and conditions of the contract and plans and
specifications, as shown by the certificate of the Engineer filed with the Clerk on October 15, 2024:
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
WAUKEE, STATE OF IOWA:
Section 1.That the report of the Engineer be and the same is hereby approved and adopted,
and the public improvements are hereby approved and accepted as having been fully completed in
accordance with the plans, specifications and form of contract and the total final construction cost
thereof is hereby determined to be $4,382,837.70, as shown in the report of the Engineer.
PASSED AND APPROVED this 21st day of October, 2021.
Mayor
ATTEST:
City Clerk