HomeMy WebLinkAbout2024-10-21 Resolution 2024-456_Accept Public Improvements, West Area Trunk Sewer Extension Phase 2RESOLUTION 2024-456
RESOLUTION ACCEPTING THE WEST AREA TRUNK
SEWER EXTENSION - PHASE 2
WHEREAS, on the 18`h day of July, 2022, the Mayor and Clerk of the City of Waukee,
Iowa, entered into a construction contract with Rognes Corporation of Ankeny, IA, for the
construction of certain public improvements generally described as the West Area Trunk Sewer
Extension - Phase 2; and
WHEREAS, the contractor has fully completed the construction of the public
improvements in accordance with the terms and conditions of the contract and plans and
specifications, as shown by the certificate of the Engineer filed with the Clerk on October 15, 2024:
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
WAUKEE, STATE OF IOWA:
Section 1. That the report of the Engineer be and the same is hereby approved and adopted,
and the public improvements are hereby approved and accepted as having been fully completed in
accordance with the plans, specifications and form of contract and the total final construction cost
thereof is hereby determined to be $4,382,837.70, as shown in the report of the Engineer.
PASSED AND APPROVED this 21" day of October, 202#-
ATTEST:
City Clerk
RESULTS OF VOTE:
AYE
R. Charles Bottenberg
X
Chris Crone
X
Rob Grove
X
Anna Bergman Pierce
X
Ben Sinclair
X
Mayor
NAY ABSENT ABSTAIN