HomeMy WebLinkAbout2024-11-04 I01H_04 Ute Ave-Ashworth Rd Intersection_Accept ImprovementsAGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: November 4, 2024
AGENDA ITEM:Consideration of approval of a resolution accepting Public Improvements
[Ute Avenue and Ashworth Road Intersection Improvements]
FORMAT:Resolution
SYNOPSIS INCLUDING PRO & CON:
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Snyder & Associates, Inc. has reviewed the public
improvements for the Ute Avenue and Ashworth Road Intersection Improvements and find it in
substantial compliance with the plans and specifications for the project.
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Resolution
II. Certificate of Completion
PREPARED BY: Lisa Bauman
REVIEWED BY: Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1H4
RESOLUTION 2024-
RESOLUTION ACCEPTING THE UTE AVENUE &
ASHWORTH ROAD INTERSECTION IMPROVEMENT
PROJECT
WHEREAS, on the 2nd day of August, 2021, the Mayor and Clerk of the City of Waukee,
Iowa, entered into a construction contract with Concrete Technologies, Inc., of Grimes, IA, for the
construction of certain public improvements generally described as the Ute Avenue & Ashworth
Road Intersection Improvement Project; and
WHEREAS, the contractor has fully completed the construction of the public
improvements in accordance with the terms and conditions of the contract and plans and
specifications, as shown by the certificate of the Engineer filed with the Clerk on October 31, 2024:
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
WAUKEE, STATE OF IOWA:
Section 1.That the report of the Engineer be and the same is hereby approved and adopted,
and the public improvements are hereby approved and accepted as having been fully completed in
accordance with the plans, specifications and form of contract and the total final construction cost
thereof is hereby determined to be $4,847,160.75, as shown in the report of the Engineer.
PASSED AND APPROVED this 4th day of November, 2024.
Mayor
ATTEST:
City Clerk
V:\Projects\2020\120.0783.01\Construction\Certificate_Completion.docx
CERTIFICATE OF COMPLETION
Ute Avenue and Ashworth Road Intersection Improvements
Waukee, Iowa
October 31, 2024
This is to certify that the constructed improvements on the Ute Avenue and
Ashworth Road Intersection Improvements project have been completed in
substantial compliance with the plans and specifications for the project. The final
contract amount is $4,847,160.75. I hereby recommend acceptance of the project.
Respectfully submitted,
_______________________ ________________________
Snyder & Associates, Inc. City of Waukee
Nathan Carhoff, P.E. Brad Deets, AICP
Project Manager City Administrator
Iowa License Number P19699