CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: November 18, 2024
AGENDA ITEM:Consideration of approval of Payment Estimate No. 3 to Busy Bee
Construction for the Transite Water Main Replacement – Phase 4 Project
in the amount of $202,884.89.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Busy Bee Construction requested Payment Estimate
No. 3 for the work completed on the Transite Water Main Replacement – Phase 4 Project in the
amount of $202,884.89. Veenstra & Kimm has reviewed the payment estimate and recommends
payment.
The partial payment is for the pay period October 4, 2024 to November 7, 2024. This pay
estimate is for water main and appurtenances installed.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $202,884.89
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Payment Estimate No. 3
ATTACHMENTS: I. Payment Estimate No. 3
II. Letter of Recommendation
PREPARED BY:Lisa Bauman
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1J5
November 13, 2024
Rudy Koester
Public Works Director
City of Waukee
805 University Avenue
Waukee, Iowa 50263
WAUKEE, IOWA
TRANSITE WATER MAIN REPLACEMENT – PHASE 4
PARTIAL PAYMENT ESTIMATE NO. 3
Enclosed are three copies of Partial Payment Estimate No. 3 for the period between October 4,
2024 and November 7, 2024 for the above-mentioned project. Partial Pay Estimate No. 3 is for
water main and appurtenances installed. We have checked the estimate and recommend
payment to Busy Bee Construction LLC in the total amount of $202,884.89.
Please sign Partial Payment Estimate No. 3 in the spaces provided. Return one signed copy to
our office and one signed copy to Busy Bee Construction LLC with payment. The remaining copy
is for the City of Waukee’s records.
If you have any questions or comments, please contact us at 515-225-8000.
VEENSTRA & KIMM, INC.
Jordan Kappos
JDK
275377
Enclosures
cc: Busy Bee Construction LLC – w/enclosure (email)
Sara Kappos, City of Waukee – w/enclosure (email)
Becky Schuett, City of Waukee – w/enclosure (email)
Lisa Bauman, City of Waukee – w/enclosure (email)
Rachel Bruns, City of Waukee – w/enclosure (email)
Tracy Lovetinsky, City of Waukee – w/enclosure (email)
QUANTITY VALUE
ESTIMATED AUTHORIZED COMPLETED COMPLETED
ITEM NO.DESCRIPTION UNIT (ORIG. CONT.)(INCL. C.O.'S)TO DATE UNIT PRICE TO DATE
1.1 Mobilization
LS 1.00 1.00 1.00 25,000.00$ $25,000.00
1.2 Traffic Control
LS 1.00 1.00 0.75 15,000.00$ $11,250.00
1.3 8" PVC Water Main Directional Bored in Place
LF 4,732.00 4,732.00 4,728.00 71.69$ $338,950.32
1.4 1" Water Service Connection
Each 99.00 99.00 0.00 564.23$ $0.00
1.5 1" Curb Stop and Box
Each 99.00 99.00 0.00 582.36$ $0.00
1.6 1" Water Service Pipe in Open Cut
LF 495.00 495.00 0.00 26.62$ $0.00
1.7 1" Water Service Pipe Directional Bored in Place
LF 2,483.00 2,483.00 0.00 26.62$ $0.00
1.8 8" Gate Valve
Each 9.00 9.00 10.00 2,973.50$ $29,735.00
1.9 Hydrant Assembly
Each 13.00 13.00 14.00 9,203.28$ $128,845.92
1.10 Tapping Valve Assembly, 12"x8" Tapping Sleeve and 8" Valve
Each 1.00 1.00 1.00 7,466.50$ $7,466.50
1.11 Connection to Existing System
Each 3.00 3.00 2.00 5,516.46$ $11,032.92
1.12 Sidewalk Removal
Each 18.00 18.00 0.00 30.00$ $0.00
1.13 PCC Sidewalk
SY 223.00 223.00 0.00 170.00$ $0.00
1.14 Detectable Warnings
SF 8.00 8.00 0.00 80.00$ $0.00
1.15 PCC Pavement
SY 16.00 16.00 0.00 170.00$ $0.00
1.16 Sodding
LS 1.00 1.00 0.00 40,000.00$ $0.00
$552,280.66
CO 1
CO 1.1 8" x 1' MJ Offset
EA 0.00 2.00 2.00 1,300.00$ $2,600.00
CO 1.2 6" Gate Valve
EA 0.00 1.00 1.00 1,971.00$ $1,971.00
CO 1.3 4" Gate Valve
EA 0.00 1.00 1.00 1,635.00$ $1,635.00
$6,206.00
$558,486.66
ESTIMATE OF CONSTRUCTION COMPLETED
PARTIAL PAYMENT NO. 3
$824,253.87
Date: November 13, 2024
Change Order No. 1 Value Completed
Total Value Completed - Bid Items
BID ITEMS
PROJECT TITLE: TRANSITE WATER MAIN REPLACEMENT - PHASE 4
Contractor: Busy Bee Construction LLC
Original Contract Amount:
Pay Period: October 4, 2024 to November 7, 2024
Base Bid Value Completed
275377 Page 1 of 2