HomeMy WebLinkAbout2024-12-16 I01F_02 Waukee Public Safety_Change Order 9_Ryan Contract\AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: December 16, 2024
AGENDA ITEM:Consideration of approval of Change Order No. 9 Construction
Management Services Agreement to Ryan Companies, US, Inc., for the
Waukee Public Safety Building Project, amended Schedule of Fees
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON:Change Order No. 8 relates to the cost of
professional fees for the construction Management Services contract with Ryan Companies which is
based upon a percentage of the cost of the total project. The change reflects an accounting update
based upon the approval of Change Order No. 8 for additional work associated with the project as well
as for costs related to fan rental charges and temporary power charges due to a service delay on
permanent power installation.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:The net result of this
Change Order increases the contract price in the amount of $39,689.00.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the Change Order.
ATTACHMENTS: I. Construction Management Change Order No. 9
PREPARED BY: Brad Deets, City Administrator
REVIEWED BY:
I1F2
Ryan Companies
111 E Grand Avenue, Suite 200
Des Moines, IA 50309
ph: 515-309-8500
ryancompanies.com
December 16, 2024
Brad Deets, City Administrator
City of Waukee
230 W. Hickman Road
Waukee, IA 50263
Re: Waukee Public Safety Building
Construction Management Proposal as per AIA C132 Agreement: CO No. 9
Dear Brad:
Thank you for the opportunity to work with you and your team on the Waukee Public Safety Building project.
We respectfully submit the following Change Order No. 9 to our agreement for Construction Management
Services dated December 18, 2023.
This change order reflects an accounting update on the construction management fee as a percentage of
the cost of work based on executed AIA Document C132-2019 dated December 18, 2023 (the “CMA
Agreement”). Attachment 3 Schedule of Fees to the CMA Agreement is updated to the Attachment 3
hereto.
The cost change associated with this CO No. 9 is $39,689.00. It includes 3.25% fee on Prime CO 8
cost of work, fan rental charges, and temporary power charges due to the MEC service delay.
Thanks again for the opportunity to be a part of this exciting project.
Sincerely,
RYAN COMPANIES US, INC.
Jill Boetger
Project Manager
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Ryan Companies
111 E Grand Avenue, Suite 200
Des Moines, IA 50309
ph: 515-309-8500
ryancompanies.com
Cc: Matt Van Loon, Ryan Co.
Ryan Pigneri, Ryan Co.
Beth Bertlshofer, Ryan Co.
Angie Pfannkuch, Sidekick Development
Agreed to this ___________ day of December, 2024.
City of Waukee, Iowa Ryan Companies US, Inc.
By:______________________ By:______________________
Its: City Administrator Its: Matt Hillis, VP of Construction
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Ryan Companies US, Inc Waukee Public Safety Facility
CMa Fee and Anticipated Staffing / General Conditions Costs 12.16.2024
CMa Fees
Proposed CMa and Change Order Fee 3.25%
Fee on Cost of Work (Prime Contracts)3.25% 28,868,515$ 938,227$ Based on 11.21.23 Bid Effort
Fee on Ryan Co. Management Time & GCs 3.25% 1,617,514$ 52,569$
Fee on Cost of Work (Prime Contracts) Prime CO
No. 1
3.25% 38,675$ 1,257$ Ryan Co. CO No. 2 (03.18.2024)
Fee on Cost of Work (Prime Contracts) Prime CO
No. 2
3.25% 15,620$ 508$ Ryan Co. CO No. 3 (05.06.2024)
Fee on Cost of Work (Prime Contracts) Prime CO
No. 3
3.25% 21,130$ 687$ Ryan Co. CO No. 4 (06.17.2024)
Fee on Cost of Work (Prime Contracts) Prime CO
No. 4
3.25% 2,895$ 94$ Ryan Co. CO No. 5 (07.15.2024)
Fee on Cost of Work (Prime Contracts) Prime CO
No. 5
3.25% 67,171$ 2,183$ Ryan Co. CO No. 6 (08.19.2024)
Fee on Cost of Work (Prime Contracts) Prime CO
No. 6
3.25% 9,831$ 320$ Ryan Co. CO No. 7 (09.16.2024)
Fee on Cost of Work (Prime Contracts) Prime CO
No. 7
3.25% 18,705$ 608$ Ryan Co. CO No. 8 (10.21.2024)
Fee on Cost of Work (Prime Contracts) Prime CO
No. 8
3.25% 23,749$ 772$ Ryan Co. CO No. 9 (12.16.2024)
Subtotal 997,224$
PRECONSTRUCTION SERVICES Unit Rate Unit Qty Cost Comments
Preconstruction Management 137$ hr 555 75,880$ Average (6) hrs week
July Budget 22,000$ ea 1 22,000$ Assumes (4) week effort
Schematic Design+/Design Document-33,000$ ea 1 33,000$ Assumes (6) week effort. VE Process.
Construction Documents
33,000$ ea 1 33,000$ Assumes (6) week effort. Bid Set/GMP.
Subtotal 163,880$
CONSTRUCTION SERVICES Unit Rate Unit Qty Cost Comments
Superintendent 117.00$ hr 3,293 385,281$ Onsite full time
Assistant Superintendent 96.00$ hr 2,080 199,680$ Onsite full time after structure
Project Manager 137.00$ hr 1,603 219,611$ Onsite as needed
Project Engineer 76.00$ hr 2,600 197,600$ Onsite full time
Subtotal 1,002,172$
Unit Rate Unit Qty Cost Comments
Project Manager
137.00$ hr 1,603 219,611$ Adjust Ryan PM II to full time. Onsite as
needed
VDC Manager 158.00$ hr 192 30,336$
Subtotal 249,947$
GENERAL CONDITIONS Unit Rate Unit Qty Cost Comments
Site Mobilization / Set-up / Staging / Trailer 2,200.00$ mo 20 44,000$
PM / Superintendent Cellular Phones 375.00$ mo 20 7,500$
Field Office Furniture / Printer / Copier / Supplies 450.00$ mo 20 9,000$
Field Office Computers / Monitors / Plan Stations 550.00$ mo 20 11,000$
Superintendent Fuel 500.00$ mo 20 10,000$
Jobsite Travel/Mileage 200.00$ mo 20 4,000$
Project Signage 450.00$ ls 1 450$
Water/Ice/Cups 275.00$ mo 20 5,500$
Portable Toilets 600.00$ mo 20 12,000$
Postage & Currier Service 60.00$ mo 20 1,200$
As-Built Documents (Mark-ups & Recording) 500.00$ ls 1 500$
Construction Debris /Recycling Dumpsters 475.00$ ea 95 45,125$
First Aid Services 50.00$ mo 20 1,000$
Safety Supplies 125.00$ mo 20 2,500$
Technology / Software Fees 0.20% % 1,319,827$ 2,640$
General Liability Insurance 1.15% % 1,319,827$ 15,178$
Subtotal 171,593$
Unit Rate Unit Qty Cost Comments
Site Mobilization / Set-up / Staging / Trailer 1,350.00$ mo 15 20,250$ Change from single to 24x60 trailer
PM / Superintendent Cellular Phones 125.00$ mo 15 1,875$ Jobsite Connectivity for Added Staff
Safety Inspector - 3rd Party / OSHA 275.00$ mo 15 4,125$
Technology / Software Fees 0.20% % 272,072$ 544$
General Liability Insurance 1.15% % 272,072$ 3,129$
Subtotal 29,923$
Unit Rate Unit Qty Cost Comments
Ryan Fan Rental 55.57$ day 11 611$ 4 fans
Temporary Generator & Fuel Extension 38,306.00$ ls 1 38,306$ Primary power activated 11/14/2024
Subtotal 38,917$
Anticipated Staffing and General Conditions Budget:2,653,656$
CHANGE ORDER NO. 9: FAN RENTAL & TEMP
GENERATOR
Budget Summary
CHANGE ORDER NO. 1: ADDITIONAL GENERAL
CONDITIONS
CHANGE ORDER NO. 1: ADDITIONAL CONSTRUCTION
SERVICES
ATTACHMENT 3: SCHEDULE OF FEES
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Waukee Public Safety - Change Request Summary 10/29/2024
Ryan Companies US, Inc.
Change Request Subcontractor Comments Cost Change
45.0 DDVI No response $0.00
45.1 Jordison Construction No response $0.00
45.2 Enterprise Precast No response $0.00
45.3 TSF Structures No response $0.00
45.4 Northwest Steel No response $0.00
45.5 Forman Ford No response $0.00
45.6 Academy Roofing No response $0.00
45.7 Ford Metro No response $0.00
45.8 Skold Door No response $0.00
45.9 Hilsabeck Schacht No response $0.00
45.10 Elite Fire Sprinkler No response $0.00
45.11 Kruck Plumbing and Heating No response $0.00
45.12 Van Maanen No response $0.00
45.13 TriCity Electric No response $0.00
45.14 Wenthold No response $0.00
45.15 Absolute No response $0.00
45.16 Jordison Construction No response $0.00
45.17 Alpha Landscapes No response $0.00
45.18 Ryan (4) High velocity fan rental, 11-days.$592.00
$592.00
Builders Risk (.23% Cost of Work (Estimated)) Excluded per City $0.00
CMa Fee on Cost of Work (3.25%)$19.24
CMa Project Manager Time $0.00
CMa Project Superintendent Time $0.00
$611.24
Change Request 045
Summary: Rental of high velocity fans to dry out the building pad due to excessive weather conditions.
Change Request 045 Subtotal
Change Request 045 Cost Change Total
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Cost location Inventory number Cost center Cost code Date arrived Workdays on site Current cost
IA-Waukee Public Safety
Facility - 6173000 FHV2 6173000 Aug 26, 2024 11:56:16 a 11 148
IA-Waukee Public Safety
Facility - 6173000 FHV3 6173000 Aug 26, 2024 11:56:16 a 11 148
IA-Waukee Public Safety
Facility - 6173000 FHV5 6173000 Aug 26, 2024 11:56:16 a 11 148
IA-Waukee Public Safety
Facility - 6173000 FHV4 6173000 Aug 26, 2024 11:56:16 a 11 148
IA-Waukee Public Safety
Facility - 6173000 AED2 6173000 014020-M Jun 27, 2024 10:39:12 a 23 100
Monthly Total 692.00$
006173000.11430.015350 = $192.00
006173000.11420.014020 = $100.00
FAN RENTAL = $592
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Waukee Public Safety - Change Request Summary 12/5/2024
Ryan Companies US, Inc.
Change Request Scope Comments Cost Change
37.1 Trailer Generator w/ Fuel Cell (56kw) September $4,265.02
37.2 Trailer Generator w/ Fuel Cell (56kw) October $4,265.02
37.3 Trailer Generator w/ Fuel Cell (56kw) November (Final)$4,441.57
37.4 Building Generator w/ Fuel Cell (20kw) August $2,036.03
37.5 Building Generator w/ Fuel Cell (20kw) September $1,636.03
37.6 Building Generator w/ Fuel Cell (20kw) October (10/2 to 10/4)$1,014.97
37.7 Building Generator w/ Fuel Cell (56kw) October $8,061.10
37.8 Building Fuel Cell November (Final)$1,003.66
37.9 Building Generator (56kw) November (Final)$6,364.48
37.10 Agriland Fuel September $1,546.25
37.11 Agriland Fuel October $985.54
37.12 Ryan Fuel October $256.00
37.13 Ryan Fuel November $1,225.00
$37,100.67
Builders Risk (.23% Cost of Work (Estimated)) Excluded per City $0.00
CMa Fee on Cost of Work (3.25%)$1,205.77
CMa Project Manager Time $0.00
CMa Project Superintendent Time $0.00
$38,306.44
Change Request 037
Summary: Generator and fuel extension due to primary service delay. MEC activated meter on 11/14/2024.
Change Request 037 Subtotal
Change Request 037 Cost Change Total
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
One‐Ryan ‐> Construction ‐> Documents ‐> zz_Yard
Job #Cost Code Total
1710 53010.000000 135.00
006002000 11420.015350 80.00
006087000 11420.015012 3296.00
006173000 11420.014020 100.00
006173000 11420.015140 256.00
006611200 11420.015012 1012.00
006662000 11420.015012 595.00
006725000 11420.015620 172.00
006725000 11420.015012 2601.00
006725200 11420.015012 1989.00
006777000 11420.015012 100.00
006777000 11420.015620 392.00
006777000 11420.014020 474.00
006801000 11420.015012 1740.00
006801200 11420.015012 280.00
007030000 11420.015012 440.00
007040000 11420.014020 1020.00
007040000 11420.015012 7059.00
007040200 11420.915140 344.00
007040200 11420.971901 15821.00
007104002 11420.015012 600.00
007117201 11420.512015 192.00
007117201 11420.015012 710.00
007139000 11420.014020 96.00
007139000 11420.015012 1505.00
007328000 11420.014020 386.00
007328000 11420.015012 2340.00
007328200 11420.015012 740.00
007332200 11420.015012 2655.00
007333200 11420.014020 36.00
007333200 11420.015012 1540.00
007382000 11420.540100 38.00
007382000 11420.014020 200.00
007400200 11420.015012 6442.50
007442000 11420.015012 1055.00
To find individual job backup, please follow the
below path in OneDrive‐Ryan (Sharepoint)
NXS# 101 ‐ 147178
Invoice # 102024DESYARD
October 2024 DES MOINES YARD
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
007468000 11420.015012 200.00
007478200 11420.015012 70.00
007483200 11420.015012 528.00
007498000 11420.015012 480.00
TOTAL DEBIT $57,719.50
1723.40040 CREDIT ($53,978.50)
1723.41111 CREDIT ($3,568.00)
1725.54010 CREDIT ($38.00)
1725.54280 CREDIT ($135.00)
($57,719.50)
Difference $0.00
TOTAL CREDIT
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
One-Ryan -> Construction -> Documents -> zz_Yard
Job # Cost Code Total
004638000 11420.014020 120.00
004638000 11430.015350 970.00
006002000 11420.015350 80.00
006087000 11420.015012 3296.00
006173000 11420.014020 100.00
006173000 11420.015140 1225.00
006469000 11420.015012 190.00
006615200 11420.015012 495.00
006662000 11420.015012 595.00
006686000 11420.014020 72.00
006686000 11430.015350 153.00
006725000 11420.015620 315.00
006725000 11420.015012 1168.00
006725200 11420.015012 2192.00
006777000 11420.015012 100.00
006777000 11420.015620 350.00
006801000 11420.015140 63.00
006801000 11420.015012 1800.00
006801200 11420.015012 1144.00
007030000 11420.015012 40.00
007040000 11420.014020 675.00
007040000 11420.015012 4735.00
007040200 11420.915140 266.00
007040200 11420.971901 30098.00
007104002 11420.015012 160.00
007139000 11420.015012 925.00
007328000 11420.014020 150.00
007328000 11420.015012 675.00
007328200 11420.015012 1198.00
007332200 11420.015012 2695.00
007333200 11420.015012 1120.00
007468000 11420.015012 200.00
007478200 11420.015012 184.00
007483200 11420.015012 400.00
007498000 11420.015012 480.00
To find individual job backup, please follow the
below path in OneDrive-Ryan (Sharepoint)
NXS# 101 - 147178
Invoice # 112024DESYARD
November 2024 DES MOINES YARD
Docusign Envelope ID: 6E8D2AEE-C3DE-46D4-A21C-AC9C16B922C8
TOTAL DEBIT $58,429.00
1723.40040 CREDIT ($55,193.00)
1723.41111 CREDIT ($3,236.00)
1725.54010 CREDIT $0.00
1725.54280 CREDIT $0.00
($58,429.00)
Difference $0.00
TOTAL CREDIT