HomeMy WebLinkAbout2025-03-17 I01H_06 Ridge Pointe Parking Lot Reconstruction_Change Order 2AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: March 17, 2025 AGENDA ITEM:Consideration of approval of Change Order No. 2 to Manatt’s, Inc., for the Ridge Pointe Parking Lot Project decreasing the contract in the amount of $3,462.00. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 to Manatt’s, Inc. is for reduction of seeding items and inlet protection devices. Change Order No. 2 decreases the contract price by a total of $3,462.00 FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: Approve Payment RECOMMENDATION: Approve the resolution. ATTACHMENTS: I. Letter of Recommendation II. Change Order No. 2 PREPARED BY: Laurie Baker REVIEWED BY: Matt Jermier PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: I1H6 MARCH 11 , 2024 Matt Jermier Parks & Recreation Director City of Waukee 805 University Ave Waukee, IA 50263 mjermier@waukee.org 217 East 2nd Street + Suite 110 + Des Moines, IA 50309 515.243.9143 + ISGInc.com Architecture + Engineering + Environmental + Planning RE: RIDGE POINT PARKING LOT RECONSTRUCTION – CHANGE ORDER NO. 2 Matt, Enclosed in this document is a signed copy of Change Order No. 2 for the project mentioned above. This change order includes the reduction of Seeding items and Inlet Protection Devices. Change Order No. 2 decreases the contract price by a total of $3,462.00. Please sign the copy of Change Order No. 2 in the spaces provided. Return one signed copy to ISG Inc. and one signed copy to Mannat’s Inc. Sincerely, Nick Frederiksen Senior Project Manager Nick.Frederiksen@ISGInc.com 3/11/2025 Amount 12 HYDRAULIC SEEDING, SEEDING, FERTILIZING, AND MULCHING, TYPE 1 LS -1.0 $2,000.00 ($2,000.00) 13 HYDRAULIC SEEDING, SEEDING, FERTILIZING, AND MULCHING, TYPE 4 LS -1.0 $1,000.00 ($1,000.00) 15 INLET PROTECTION DEVICE EA -3.0 $225.00 ($675.00) B1 SOD SQ 1.5 $142.00 $213.00 TOTALS $213.00 ($3,675.00) NET CHANGE IN CONTRACT PRICE INCREASE (DECREASE) IN CONTRACT TIME, days Justification For Changes: Page 2 of 2 Increase Decrease EJCDC® C-941, Change Order. Prepared and published 2013 by the Engineers Joint Contract Documents Committee. ITEM NO. DESCRIPTION UNIT QUANTITY UNIT PRICE ($3,462.00) ITEM 12, HYDRAULIC SEEDING, SEEDING, FERTILIZING, AND MULCHING, TYPE 1 - QUANTITY REDUCED TO ZERO SINCE ALTERNATE B WAS AWARDED AND SOD WAS USED IN PLACE OF HYDRAULIC SEEDING. ITEM 13, HYDRAULIC SEEDING, SEEDING, FERTILIZING, AND MULCHING, TYPE 4 - QUANTITY REDUCED TO ZERO SINCE ALTERNATE B WAS AWARDED AND SOD WAS USED IN PLACE OF HYDRAULIC SEEDING. ITEM 15, INLET PROTECTION DEVICES - QUANTITY REMOVED AS THEY WERE NOT USED DURING CONSTRUCTION. ITEM B1, SOD - WAS INCREASED BY 1.5 SQAURE FOR ADDITIONAL RESTORATION WITH THE ADDITION OF SHARE USE PATH EXTENTS.