HomeMy WebLinkAbout2025-06-02 I01F_03 Painted Woods West Park_Change Order 2AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: June 2, 2025
AGENDA ITEM:Consideration of approval of Change Order No. 2 to Concrete Connection,
LLC., for Painted Woods West Park Project increasing the contract in the
amount of $13,008.00.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 to Concrete Connection, LLC is for
change in dirt quantity from 3,384 CY to 4,990 CY leaving an excess of 1,626
CY. Concrete Connection will dispose of this dirt at the $8.00/CY contract
price for onsite earthwork.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Letter of Recommendation
II. Change Order No. 2
PREPARED BY: Laurie Baker
REVIEWED BY: Matt Jermier
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1F3
gēnus [ landscape architects ]
520 42ND STREET
SUITE 400
DES MOINES, IA 50312
T 515 284 1010
WWW.GENUS-LA.COM
May 27, 2025
Mr. Matt Jermier
Parks and Recreation Director, Waukee
805 University Avenue
Waukee, IA 50263
RE: PAINTED WOODS WEST PARK – CHANGE ORDER #2
Genus Project No. 24007
Dear Mr. Jermier:
Please find Change Order #2 attached in the amount of $13,008 for the
above-referenced project. This work is associated with:
1) Removal of excess 1,626 cubic yards of soil from the project site.
Genus recommends that the City of Waukee approve Change Order #2
to Concrete Connection. Please reach out if you have questions or
need additional information.
Sincerely,
Scot Schuckert, ASLA
Field Operations Coordinator
CC: Will Becker, Concrete Connection
Dave Bartholomew, Concrete Connection
Laurie Baker, City of Waukee
Josh VandeKamp, City of Waukee
Dalton Stifel, City of Waukee
Brett Douglas, Genus
Concrete Connection, LLC
5170 NW Beaver Drive
Johnston, Iowa 50131
Phone: 319/830-2207
Email: wil l @yourconcreteconnection.com
Change Order 2 – 5/22/2025
To:Genus
Attn:Scot Schuckert
Genus
520 42nd St.
Des Moines, IA 50312
Phone: (515) 284-1010
Email: sschuckert@genus-la.com
Project:Painted Woods West Park
Proposed Change in Scope of Work:
Change in dirt quantity from 3,384 CY to 4,990 CY leaving an excess of 1,626 CY. Concrete Connection
will dispose of this dirt at the $8.00/CY contract price for onsite earthwork.
Additional Charges:
1,626 CY onsite earthwork ADD $13,008.00
Total Change Order #2 ADD $13,008.00
Previous Change Orders $58,540.00
Original Contract Amount $1,674,999.00
Contract Amount to Date $1,746,547.00
If you have any questions please call me at 319/830-2207.
Regards,
Will Becker
Concrete Connection LLC