CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: July 21, 2025
AGENDA ITEM:Consideration of approval of a motion approving Change Order No. 3 to
Elder Corporation for the University Avenue Area Improvements –
Phase 1 Project in the amount of $68,221.32.
FORMAT:Consent
SYNOPSIS INCLUDING PRO & CON: Change Order No.3 is for modified subbase for
underpass backfill, modified subbase for driveway pavement, and underpass over excavation and
rock backfill due to poor soil conditions.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $68,221.32
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Change Order No. 3
ATTACHMENTS: I. Change Order No. 3
II. Letter of Recommendation
PREPARED BY:Lisa Bauman
REVIEWED BY:Sara Kappos SKK
I1F5
S-H Project No.: 4203290
July 15, 2025
Rudy Koester, Public Works Director
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: Change Order #3 – Review and Recommendation to Approve
University Avenue Area Improvements - Phase 1
Dear Mr. Koester:
Please find attached Change Order #3 for the University Avenue Area Improvements - Phase 1 project.
The change order includes the following items:
• Modified Subbase Underpass Backfill
• Modified Subbase for Driveway Pavement
• Underpass Overexcavation and Rock Backfill
Granular backfill for the pedestrian underpasses between the top of tunnel footings and bottom of
shared use path pavement is being removed from the project and replaced with the addition of modified
subbase material to provide a more uniform working surface for construction of the shared use path
pavement.
Modified subbase material measured by ton is added to be used as needed for repair of ruts in
standard-depth modified subbase (measured by square yard) placed on Univers ity Avenue and used as
temporary truck access to Waukee Public Works Building prior to PCC paving.
Overexcavation is added at the base of the 10th Street pedestrian underpass to remove unsuitable soil
material encountered during excavation, as identified by the geotechnical engineer. The overexcavated
area is to be backfilled with 3-inch clean rock material to establish the necessary subbase suitable for
construction of the pedestrian underpass structure.
We have reviewed the change order items and unit prices, and both are in line with anticipated
amounts. If City staff concurs with this change, we recommend the City of Waukee approve this change
order in the amount of $68,221.32 to the construction contract for the University Avenue Area
Improvements - Phase 1 with Elder Corporation of Des Moines, IA.
Sincerely,
SHIVE-HATTERY, INC.
Blake T. Peterson, PE
Civil Engineer
Enc. Change Order #3
CITY OF WAUKEE
230 W HICKMAN ROAD
WAUKEE, IOWA 50263
Contractor:
5088 E. University Avenue
Des Moines, IA 50327 $10,068,807.00 1/20/2025
130 TON $ 22.75 -846.00 $ (19,246.50)
CO-3.1 TON $ 33.15 948.00 $ 31,426.20
CO-3.2 TON $ 29.05 60.00 $ 1,743.00
CO-3.3 TON $ 85.75 633.22 $ 54,298.62
$ 68,221.32
$10,068,807.00
$11,298.05
$10,080,105.05
$68,221.32
$10,148,326.37
0.79%
0 Days
0 Days
November 21, 2025
May 31, 2026
Date:
Approved By:
City of Waukee
Signature:
Name:
Title:
Date:
Recommended By:
Shive-Hattery Inc.
Signature:
Name:
Title: Title:
Date:
University Avenue Area Improvements - Phase 1
4203290
Net Change by previously authorized Change Orders
The Contract Sum prior to This Change Order was
The Contract Sum will be increased by this Change Order in the amount of
The new Contract Sum including this Change Order will be
Description
UNDERPASS OVEREXCAVATION & ROCK BACKFILL
THE CONTRACT IS CHANGED AS FOLLOWS:
Items 130 and CO-3.1: Granular backfill for the pedestrian underpasses between the top of footing and bottom of shared use path pavement is being removed from the project and
replaced with modified subbase material to provide a more uniform working surface for construction of the shared use path pavement.
Item CO-3.2: Modified subbase material measured by ton is added to be used as needed for repair of ruts in standard-depth modified subbase placed on University Avenue and
used as temporary truck access to Waukee Public Works Building prior to PCC paving.
Item CO-3.3: Overexcavation is added at the base of the 10th Street pedestrian underpass to remove unsuitable soil material encountered during excavation. Overexcavated area is
to be backfilled with 3" clean rock material to establish the necessary subbase suitable for construction of the pedestrian underpass structure.
Item Value Adjustment
CHANGE ORDER SUMMARY
Quantity AdjustmentUnit Price
Contractor:
Elder Corporation
Elder Corporation
Signature:
Name:
The Landscaping/Site Restoration/Final Completion Contract Time will be changed by
MODIFIED SUBBASE UNDERPASS BACKFILL
The Grading/Structure/Utility/Paving Contract Time will be changed by
The date of Grading/Structure/Utility/Paving Completion as of the date of this Change Order therefore is
GRANULAR BACKFILL
CHANGE ORDER
Aggregate Change Order as a percent of Original Contract
The date of Landscaping/Site Restoration/Final Completion as of the date of this Change Order therefore is
NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER
Project Title
S-H Project File Number
Orig. Contract Amount & Date
Change Order Number
Date
3
TOTAL
The Original Contract Sum was
Unit
July 15, 2025
MODIFIED SUBBASE
P:\Projects\DM\4203290\Construction\_University Avenue Phase 1\CASupport\Change Orders\03\ChangeOrder03_UniversityAvenuePhase1.xlsx
1 of 1
Nick Tometich
Project Manager
Blake Peterson, PE
Project Engineer
Brad Deets
City Administrator
Date: 2025.07.16
14:00:12-05'00'
07/16/2025