Loading...
HomeMy WebLinkAbout2025-08-04 I01E_03 T Ave Corridor, W Hickman Rd to NW Douglas Pkwy_Change Order 15AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: August 4, 2025 AGENDA ITEM:Consideration of approval of a motion approving Change Order No. 11 to All-Star Concrete, LLC, for the T Avenue Corridor Improvements Project, W Hickman Road to NW Douglas Parkway, increasing the contract in the amount of $36,123.80. FORMAT:Consent SYNOPSIS INCLUDING PRO & CON: Change Order No.11 is for correcting the redundant credit to the city in the change order for the sign change addition and Gridsmart deduction under the traffic signalization line item. The amounts were already accounted for with line item 8.20 and 8.21. Additional work was required near the properties east of T Avenue to handle stormwater flows. This included export of soil and additional stone to dewater the area and the addition of an area intake to take on surface flows. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order increases the contract price in the amount of $36,123.80. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve Change Order No.11 ATTACHMENTS: I. Change Order No.11 II. Letter of Recommendation PREPARED BY:Lisa Bauman REVIEWED BY:Sara Kappos I1E3 8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393 July 16, 2025 Sara Kappos, P.E. Assistant Public Works Director 805 University Avenue Waukee, IA 50263 RE: Change Order #11 T Avenue Corridor Improvements – W Hickman Road to NW Douglas Parkway Dear Mrs. Kappos: Attached please find a detailed Change Order for City Council approval on August 4, 2025. Change Description: Corrected the redundant credit to the city in the change order for the sign change addition and Gridsmart deduction under the traffic signalization line item. The amounts were already accounted for with line item 8.20 and 8.21. Also, additional work was required near the properties east of T Avenue to handle stormwater flows. This included export of soil and additional stone to dewater area plus an intake to take on surface flows. We have reviewed the quotes submitted from All - Star and it appears to be in order with current industry pricing. If the City Staff concurs with this pricing, we recommend the City of Waukee Increase the contract price in the amount of $36,123.80 to complete the additional work associated with Change Order #11. If you have any questions, please contact me. Sincerely, Foth Infrastructure & Environment, LLC Rob Kline, P.E. Lead Civil Engineer Encl: Change Order #11 dated 07/16/2025 CHANGE ORDER 11 Distribution: Owner - Finance ____ Owner - Public Works ____ Engineer ____ Contractor ____ Contractor:All-Star Concrete LLC. 4989 NW Johnston Dr. Johnston, Iowa 50131 $10,683,619.98 August 7, 2023 8.1 Division 1 8010-A-1000 LS $8,824.00 1.00 $8,824.00 2.14 Divison 1 Special TON $62.68 90.00 $5,641.20 2.15 Division 1 Special TON $123.07 130.00 $15,999.10 6.3 Division 1 Special LS $5,659.50 1.00 $5,659.50 $36,123.80 $10,683,619.98 $177,714.94 $10,861,334.92 $36,123.80 $10,897,458.72 0 Days Recommended By: All-Star Concrete LLC. Signature: Name: Bryan Sprigs Title: Project Manager Date: Owner:City of Waukee □ ≤$500 Department Director X_______________________________________Date___________________ □ $501 to $2,500 City Administrator X_______________________________________Date___________________ □ Date___________________ □ >$2,501 City Council approved or ratified at Council meeting on Date___________________ GABION STONE WITH FABRIC TRAFFIC SIGNALIZATION EXPORT 12" OF EXISTING SOIL Value AdjustmentItem No. Signature: The Contract Sum will be increased by this Change Order in the amount of Net Change by previously authorized Change Orders Foth Infrastructure & Environment, LLC The Contract Sum prior to This Change Order was Division Item Code Quantity AdjustmentUnit Price City of Waukee Description Unit SW-512 INTAKE with PIPE,GRATE,CONCRETE,GRADING and LABOR Prepared By: Date: The Contract Time will be increased by CHANGE ORDER SUMMARY NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER The Original Contract Sum was Title: Lead Civil Engineer Title: City Administrator Name: Rob Kline, P.E. The new Contract Sum including this Change Order will be Signature: Date: Name: Brad Deets Checked By: Department of Public Works 805 University Avenue Waukee, IA 50263 (515) 987-7920 Fax (515) 987-3979 THE CONTRACT IS CHANGED AS FOLLOWS: Corrected the redundant credit to the city in the change order for the sign change addition and Gridsmart deduction under the traffic signalization line item. The amounts were already accounted for with line item 8.20 and 8.21. Also, additional work was required near the properties east of T Avenue to handle stormwater flows. This included export of soil and additional stone to dewater area plus an intake to take on surface flows. T Avenue Corridor Improvements W Hickman Rd to NW Douglas Pkwy 11 22W007.00 Waukee Project File Number July 16, 2025 Foth Project File Number Orig. Contract Amount & Date Date Change Order Number Project Title C11-2025-0716-Waukee T Avenue.xlsx Change Order 1 Page 1 of 1