CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: November 3, 2025
AGENDA ITEM:Consideration of approval of a motion approving Payment Estimate
No. 10 (Final) to Absolute Group for the Prairie Rose Trail Project in
the amount of $6,312.41.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Absolute Group requested Payment Estimate No. 10
(Final) for the work completed on the Prairie Rose Trail project in the amount of $6,312.41.
Snyder & Associates, Inc. has reviewed the payment estimate and recommends payment.
The partial payment is for the pay period August 1, 2025 to October 29, 2025. Work includes site
restoration, punchlist items and adjustment of plan quantities to match as-built conditions by
Change Order No. 5.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $6,312.41
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Payment Estimate No. 10 (Final)
ATTACHMENTS: I. Letter of Recommendation
II.Payment Estimate No. 10 (Final)
PREPARED BY:Lisa Bauman
REVIEWED BY:Sara Kappos SKK
I1G3
2727 SW SNYDER BOULEVARD | P.O. BOX 1159 | ANKENY, IA 50023-0974
autofill
v:\projects\2023\123.0957.01\construction\pay_2025-10-30_letterpayapp10.docm
October 29, 2025
Ms. Sara Kappos, P.E.
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: PARTIAL PAYMENT APPLICATION NO. 10 (FINAL)
PRAIRIE ROSE TRAIL
Dear Sara:
Enclosed is partial payment application 10 for the Prairie Rose Trail project. The application
includes work completed August 1, 2025 through October 29, 2025. Work includes site
restoration, punchlist items, and adjustment of plan quantities to match as-built conditions by
Change Order 05.
We recommend payment of $6,312.41 to the prime contractor, Absolute Group of Granger,
Iowa. Please place this payment application on the next available city council meeting agenda for
approval.
Sincerely,
SNYDER & ASSOCIATES, INC.
Rob Haaland, P.E., PTOE
Project Manager