HomeMy WebLinkAbout2025-12-15 I01F_14 NW 10th St Crack and Seat_Pmt Est 3-FinalAGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: December 15, 2025
AGENDA ITEM:Consideration of approval of a motion approving Payment Estimate
No. 3 (Final) to Grimes Asphalt and Paving Corporation for the NW 10th
Street Crack & Seat Project, NW Douglas Parkway to 260th Street, in the
amount of $10,450.00.
FORMAT:Consent
SYNOPSIS INCLUDING PRO & CON: Grimes Asphalt and Paving Corporation requested
Payment Estimate No. 3 (Final) for the work completed on the NW 10th Street Crack and Seat,
NW Douglas Parkway to 260th Street Project in the amount of $10,450.00. Foth Infrastructure has
reviewed the payment estimate and recommends payment.
The partial payment is for the pay period November 1, 2024 to September 22, 2025. All work on
the project has been completed, and this payment is for balancing bid items for as built quantities.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $10,450.00
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Payment Estimate No. 3
ATTACHMENTS: I. Payment Estimate No. 3
II. Letter of Recommendation
PREPARED BY:Lisa Bauman
REVIEWED BY:Sara Kappos SKK
I1F14
106 SW 7th Street Suite 200 Des Moines, IA 50309 Phone: (515) 254-1393
December 1, 2025
Sara Kappos, P.E.
Assistant Public Works Director
805 University Avenue
Waukee, IA 50263
RE: Final Change Order #3 & Pay Request #3
10th Street Crack and Seat – NW Douglas Parkway to 260th Street
Dear Mrs. Kappos:
Attached please find a detailed Pay Request and Change Order for City Council approval on
December 15, 2025.
Submitted Quantity
Item No. Description Division Unit Quantity
7.9 FULL DEPTH PATCHES, HMA, 8 IN. 1 SY 141.6
7.9 FULL DEPTH PATCHES, HMA, 8 IN. 2 SY 58.4
8.4 TRAFFIC SIGNS, R6-1R, 54" x 18" 1 EA 2.00
8.5 REMOVE AND REINSTALL TRAFFIC SIGNS 1 EA 1.00
8.6 REMOVE AND SALVAGE TRAFFIC SIGN
ASSEMBLY
1 EA 3.00
We have reviewed the submitted quantities, and they appear to be in order with what has been
constructed in the field. If City Staff concurs with this payment, we recommend the City of
Waukee pay Grimes Asphalt of Des Moines, Iowa the amount of $10,450.00 for the work
completed to date.
Change Description:
This change order includes the zero-out change order to adjust final quantities to the measured
as-built amounts.
We recommend the City of Waukee Increase the contract price in the amount of $11,000.00 to
complete the work associated with Change Order #3.
If you have any questions, please contact me.
Sincerely,
Foth Infrastructure & Environment, LLC
Rob Kline, P.E.
Lead Civil Engineer
Encl: Final Pay Request #3 & Change Order #3 dated 12/1/2025
Department of Public Works
805 University Avenue
Waukee, Iowa 50263
Phone (515) 987-4363
Contractor:
Division 1
Division 2
Item Item Div. 1 Div. 2 Unit Div. 1 Div. 2 Div. 1 Qty.Div. 2 Qty.Div. 1 Val.Div. 2 Val.Total Value
No.Code Qty.Qty.Price Cost Cost Completed Completed Completed Completed Completed
DIVISION 1 - GENERAL
1.1 NOT USED $0.00 $0.00 $0.00 $0.00 $0.00
DIVISION 2 - EARTHWORK, SUBGRADE AND SUBBASE
2.1 2010-D-1003 TOPSOIL, OFF-SITE CY 420.0 0.0 $50.00 $21,000.00 $0.00 420.00 0.00 $21,000.00 $0.00 $21,000.00
2.2 2010-G-1012 SUBGRADE PREPARATION, 12 IN.SY 0.0 280.0 $2.75 $0.00 $770.00 0.00 280.00 $0.00 $770.00 $770.00
2.3 Special CLASS 13 EXCAVATION CY 47.1000 16.9000 $64.00 $3,014.40 $1,081.60 47.1000 16.9000 $3,014.40 $1,081.60 $4,096.00
DIVISION 3 - TRENCH AND TRENCHLESS CONSTRUCTION
3.1 NOT USED $0.00 $0.00 $0.00 $0.00 $0.00
DIVISION 4 - SEWERS AND DRAINS
4.1 4040-A-1004 SUBDRAIN, PVC, 4 IN.LF 8781.0 11034.0 $5.77 $50,666.37 $63,666.18 8781.00 11034.00 $50,666.37 $63,666.18 $114,332.55
4.2 4040-D-1000 SUBDRAIN, OUTLET, CMP EA 22.0 33.0 $275.00 $6,050.00 $9,075.00 22.00 33.00 $6,050.00 $9,075.00 $15,125.00
DIVISION 5 - WATER MAIN AND APPURTENANCES
5.1 NOT USED $0.00 $0.00 $0.00 $0.00 $0.00
DIVISION 6 - STRUCTURES FOR SANITARY AND STORM SEWER
6.1 NOT USED $0.00 $0.00 $0.00 $0.00 $0.00
DIVISION 7 - STREETS & RELATED WORK
7.1 7010-E-1003 CURB AND GUTTER, 3 FT, 10 IN. LF 370.0 0.0 $32.00 $11,840.00 $0.00 370.00 0.00 $11,840.00 $0.00 $11,840.00
7.2 SPECIAL 12 IN. CIP PCC BLOCK BEHIND EXISTING CURB LF 256.0 0.0 $26.00 $6,656.00 $0.00 256.00 0.00 $6,656.00 $0.00 $6,656.00
7.3 7010-J-1004 GRANULAR SURFACING TON 2703.7 3022.1 $36.50 $98,683.96 $110,307.75 2703.67 3022.13 $98,683.96 $110,307.75 $208,991.70
7.4 7020-I-1000 ASPHALT PAVEMENT SAMPLES AND TESTING LS 0.5 0.5 $550.00 $275.00 $275.00 0.50 0.50 $275.00 $275.00 $550.00
7.5 7020-A-1000 HMA PAVEMENT, HIGH TRAFFIC, SURFACE COURSE, PG 58-28H, 1/2" MIXTON1248.3 1471.3 $93.00 $116,088.18 $136,827.18 1248.26 1471.26 $116,088.18 $136,827.18 $252,915.36
7.6 7020-A-1010 HMA PAVEMENT, STANDARD TRAFFIC, INTERMEDIATE COURSE, PG 58-28S, 1/2" MIXTON2735.5 3242.0 $86.00 $235,253.00 $278,812.00 2735.50 3242.00 $235,253.00 $278,812.00 $514,065.00
7.7 7020-A-1021 HMA OVERLAY, INTERLAYER BASE COURSE, PG 58-34E, 3/8" MIXTON 805.9 1000.4 $121.00 $97,513.90 $121,048.40 805.90 1000.40 $97,513.90 $121,048.40 $218,562.30
7.8 7030-H-3000 DRIVEWAY, GRANULAR, CLASS-A CRUSHED STONE, DRIVEWAY OR ROADWAY, 4 IN.TON 0.0 0.0 $36.50 $0.00 $0.00 0.00 0.00 $0.00 $0.00 $0.00
7.9 7040-A-1008 FULL DEPTH PATCHES, HMA, 8 IN.SY 141.6 58.4 $45.00 $6,372.00 $2,628.00 141.60 58.40 $6,372.00 $2,628.00 $9,000.00
7.10 7040-B-1006 SUBBASE OVER-EXCAVATION TON 0.0 0.0 $56.00 $0.00 $0.00 0.00 0.00 $0.00 $0.00 $0.00
7.11 7040-G-1000 MILLING SY 296.0 183.0 $11.00 $3,256.00 $2,013.00 296.00 183.00 $3,256.00 $2,013.00 $5,269.00
7.12 7040-H-1000 PAVEMENT REMOVAL SY 771.0 0.0 $16.50 $12,721.50 $0.00 771.00 0.00 $12,721.50 $0.00 $12,721.50
7.13 7092-A-1000 CRACK AND SEAT OF PCC PAVEMENT SY 10735.8 13305.3 $1.15 $12,346.17 $15,301.10 10735.80 13305.30 $12,346.17 $15,301.10 $27,647.27
7.14 7092-C-1000 FULL DEPTH SAW CUT LF 550.0 550.0 $3.50 $1,925.00 $1,925.00 550.00 550.00 $1,925.00 $1,925.00 $3,850.00
7.15 7092-H-1000 JOINT CONTROL FABRIC LF 500.0 500.0 $2.50 $1,250.00 $1,250.00 500.00 500.00 $1,250.00 $1,250.00 $2,500.00
7.16 SPECIAL HMA PAVEMENT, 1/2" INTERMEDIATE AND
SURFACE MIX, 6 IN.TON 385.0994 109.1606 $105.00 $40,435.44 $11,461.86 385.0994 109.1606 $40,435.44 $11,461.86 $51,897.30
DIVISION 8 - TRAFFIC SIGNALS AND TRAFFIC CONTROL
8.1 8020-C-1000 PAINTED PAVEMENT MARKINGS, DURABLE STA 123.0000 127.6000 $90.00 $11,070.00 $11,484.00 123.0000 127.6000 $11,070.00 $11,484.00 $22,554.00
8.2 8020-M-1000 GROOVES CUT FOR PAVEMENT MARKINGS STA 123.0000 127.6000 $36.00 $4,428.00 $4,593.60 123.0000 127.6000 $4,428.00 $4,593.60 $9,021.60
8.3 8030-A-1000 TEMPORARY TRAFFIC CONTROL LS 0.5 0.5 $17,600.00 $8,800.00 $8,800.00 0.50 0.50 $8,800.00 $8,800.00 $17,600.00
8.4 8040-A-1000 TRAFFIC SIGNS, R6-1R, 54" x 18"EA 2.0 0.0 $500.00 $1,000.00 $0.00 2.00 0.00 $1,000.00 $0.00 $1,000.00
8.5 8040-I-1000 REMOVE AND REINSTALL TRAFFIC SIGNS EA 1.0 0.0 $400.00 $400.00 $0.00 1.00 0.00 $400.00 $0.00 $400.00
8.6 8040-J-1000 REMOVE AND SALVAGE TRAFFIC SIGN ASSEMBLY EA 3.0 0.0 $200.00 $600.00 $0.00 3.00 0.00 $600.00 $0.00 $600.00
DIVISION 9 - SITEWORK AND LANDSCAPING
9.1 9010-A-1100 HYDRAULIC SEEDING, FERTILIZING & MULCHING, TYPE 6 (SALT-RESISTANT MIXTURE)AC 0.1 0.0 $14,500.00 $2,030.00 $0.00 0.14 0.00 $2,030.00 $0.00 $2,030.00
9.2 9040-T-1000 INLET PROTECTION DEVICE, DROP-IN TYPE EA 0.0 0.0 $175.00 $0.00 $0.00 0.00 0.00 $0.00 $0.00 $0.00
9.3 9040-T-2000 INLET PROTECTION DEVICE, MAINTENANCE EA 0.0 0.0 $25.00 $0.00 $0.00 0.00 0.00 $0.00 $0.00 $0.00
3
Project Title:NW 10th Street Crack and Seat
NW Douglas Parkway to 260th Street
Project
Number:0023W034.00Project File Number:
Grimes Asphalt and Paving Corporation
BID ITEMS
Description Unit
FINAL PAY REQUEST
Purchase Order Number:
Original Contract
Amount & Date $1,254,457.62 5/6/2024
Notice to Proceed
Date 5/20/2024
Estimated Completion
Date 8/9/2024
Pay Period
Pay Request Number
Date
Contract ID
11/1/2024 to 9/22/2025
3
12/1/2025
5550 NE 22nd Street
Des Moines, Iowa 50313
(515)266-5173
City of Waukee
Dallas County
c:\pw_workdir\pw_ie\fvd_amw2\d0862684\PA3_2025_1225_Waukee 10th Crack and Seat.xlsb
PA3_2025_1225_Waukee 10th Crack and Seat.xlsb
Page 1 of 2
DIVISION 10 - DEMOLITION
10.1 NOT USED $0.00 $0.00 $0.00 $0.00 $0.00
DIVISION 11 - MISCELLANEOUS
11.1 11020-A-1000 MOBILIZATION LS 0.5 0.5 $22,200.00 $11,100.00 $11,100.00 0.50 0.50 $11,100.00 $11,100.00 $22,200.00
11.2 11030-A-1000 MAINTENANCE OF POSTAL SERVICE LS 0.5 0.5 $500.00 $250.00 $250.00 0.50 0.50 $250.00 $250.00 $500.00
11.3 11030-B-1000 MAINTENANCE OF SOLID WASTE COLLECTION LS 0.5 0.5 $500.00 $250.00 $250.00 0.50 0.50 $250.00 $250.00 $500.00
DIVISION 12 - STRUCTURES
12.1 NOT USED $0.00 $0.00 $0.00 $0.00 $0.00
Div. 1 Div. 2
Div. 1 Div. 2 Ext. Cost Ext. Cost
$0.00 $0.00 $0.00
The amount
MATERIALS STORED SUMMARY
SUBTOTAL $765,274.91 $1,558,194.58
PAY REQUEST SUMMARY
$0.00
$1,480,284.85
$1,558,194.58
$77,909.73
Total Previously Approved (list each)
$1,558,194.58
Contract Price
Total Approved
$1,254,457.62
$239,985.96
$11,000.00
$1,558,194.58
Materials Stored
$1,333,266.45
Total Completed
100%
$10,450.00
691.4%
$1,469,834.85
Total Earned Less Retainage
Approved Change Order 1
Approved Change Order 2
Approved Change Order 3
Revised Contract Price
$52,751.00
Total Previously Approved
Amount Due This Request
Percent Complete
Percent of Contract Period Utilized (In Calendar Days, Based on Notice to Proceed Date & Contract Completion Date)
is recommended for approval for payment in accordance with the terms of
the Contract.$10,450.00
$792,919.66 $765,274.91 $792,919.66
Pay Request 1
Pay Request 2
Retainage 5.0%
SUBTOTAL
Description
# of Units
Total Units Total CostUnit Price
$136,568.40