CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: May 18, 2026
AGENDA ITEM:Consideration of approval of a motion approving Payment Estimate
No. 5 to Holzworth Concrete for NW 6th Street Culvert Over Little
Walnut Creek in the amount of $4,304.82
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Holzworth Concrete requested Payment Estimate
No. 5 is for the work completed on the NW 6th Street Culvert Over Little Walnut Creek in
the amount of $4,304.82. Foth has reviewed the payment estimate and recommends payment.
The partial payment is for the pay period April 1, 2026 to May 1, 2026. This pay estimate
is for temporary traffic control, conventional seeding type 4, hydraulic mulching, stormwater
pollution prevention plan SWPPP, and silt fence installation.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $4,304.82
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Payment Estimate No.5
ATTACHMENTS: I. Letter of Recommendation
II.Payment Estimate No. 5
PREPARED BY:Lisa Bauman
REVIEWED BY:Sara Kappos
I1I6
106 SW 7th Street, Suite 200 Des Moines, IA 50309 Phone: (515) 254-1393
May 12, 2026
Sara Kappos, P.E.
Assistant Director of Public Works
805 University Avenue
Waukee, IA 50263
RE: Pay Request #5
NW 6th Street Culvert Over Little Walnut Creek
Dear Ms. Kappos:
Attached please find a detailed Pay Request for City Council approval on May 18, 2026.
Submitted Quantity
Item No. Description Unit Quantity
8.1 TEMPORARY TRAFFIC CONTROL LS 0.25
9.1 CONVENTIONAL SEEDING, TYPE 4 (URBAN
TEMPORARY MIX)
AC 0.80
9.2 HYDRAULIC MULCHING AC 0.80
9.3 STORMWATER POLLUTION PREVENTION PLAN
(SWPPP) MANAGEMENT
LS 0.22
9.5 SILT FENCE, INSTALLATION LF 397.00
We have reviewed the submitted quantities, and they appear to be in order with what has been constructed
in the field. If City Staff concurs with this payment, we recommend the City of Waukee pay Holzworth
Concrete of West Des Moines, Iowa the amount of $4,304.82 for the work completed to date.
Please let me know if you have any questions or need additional information.
Sincerely,
Foth Infrastructure and Environment, LLC
Alicia Worden
Lead Construction Engineer
Encl: Pay Request #5 dated 05/01/2026
Department of Public Works
805 University Avenue
Waukee, Iowa 50263
Phone (515) 978-7920
Project
Number 0022W003.01
Contractor:
$630,797.60
4/1/2026 to 5/1/2026
Item Item Est.Unit Extended Quantity Value
No.Code Qty.Price Price Completed Completed
DIVISION 1 - GENERAL
1.1 (NOT USED)$0.00 $0.00
DIVISION 2 - EARTHWORK, SUBGRADE AND SUBBASE
2.1 2010-B-1000 CLEARING AND GRUBBING ACRE 1.6 $5,000.00 $8,000.00 1.60 $8,000.00
2.2 2010-D-1000 TOPSOIL, ON SITE CY 1149.0 $7.90 $9,077.10 1149.00 $9,077.10
2.3 2010-D-3000 TOPSOIL, WASTE CY 1272.0 $2.00 $2,544.00 1272.00 $2,544.00
2.4 2010-E-1010 EXCAVATION, CLASS 10, ROADWAY AND BORROW CY 16581.0 $3.00 $49,743.00 16581.00 $49,743.00
2.5 2010-E-1110 EMBANKMENT-IN-PLACE, STOCKPILE CY 15228.0 $6.25 $95,175.00 15228.00 $95,175.00
CO 2.6 SPECIAL SPECIAL GRADING AT PUBLIC SAFETY SITE CY 14700.0 $1.00 $14,700.00 14700.00 $14,700.00
DIVISION 3 - TRENCH AND TRENCHLESS CONSTRUCTION
3.1 (NOT USED)$0.00 $0.00
DIVISION 4 - SEWERS AND DRAINS
4.1 SPECIAL FIELD TILE REPAIR AND FITTINGS, PVC,
UNSPECIFIED DIAMETER LF 100.0 $56.75 $5,675.00 0.00 $0.00
DIVISION 5 - WATER MAIN AND APPURTENANCES
5.1 5010-B-1000 STEEL CASING PIPE, TRENCHED, 16 IN.LF 84.0 $160.00 $13,440.00 80.00 $12,800.00
DIVISION 6 - STRUCTURES FOR SANITARY AND STORM SEWER
6.1 (NOT USED)$0.00 $0.00
DIVISION 7 - STREETS & RELATED WORK
7.1 (NOT USED)$0.00 $0.00
DIVISION 8 - TRAFFIC SIGNALS AND TRAFFIC CONTROL
8.1 8030-A-1000 TEMPORARY TRAFFIC CONTROL LS 1.0 $2,000.00 $2,000.00 1.00 $2,000.00
DIVISION 9 - SITEWORK AND LANDSCAPING
9.1 9010-B-1400 CONVENTIONAL SEEDING, TYPE 4 (URBAN
TEMPORARY MIX)ACRE 2 $750.00 $1,500.00 1.74 $1,305.00
9.2 9010-B-1000 HYDRAULIC MULCHING ACRE 2.5 $2,250.00 $5,625.00 0.80 $1,800.00
9.3 9040-A-2000 STORMWATER POLLUTION PREVENTION PLAN
(SWPPP) MANAGEMENT LS 1 $2,750.00 $2,750.00 0.95 $2,612.50
9.4 9040-J-1000 RIP RAP, CLASS E TON 294 $78.50 $23,079.00 293.89 $23,070.37
9.5 9040-N-1000 SILT FENCE, INSTALLATION LF 1214 $2.35 $2,852.90 1594.00 $3,745.90
9.6 9040-N-2000 SILT FENCE, REMOVAL OF SEDIMENT LF 1214 $0.10 $121.40 0.00 $0.00
9.7 9040-N-3000 SILT FENCE, REMOVAL OF DEVICE LF 1214 $0.10 $121.40 0.00 $0.00
Date 5/12/2026
5
Pay Period
5/29/2026
NW 6th Street Culvert
Over Little Walnut CreekProject Title
5
Estimated
Completion Date
8/19/2025
Orig. Contract
Amount & Date 8/19/2025
Notice to Proceed
Date
Pay Request
Number
Holzworth Concrete
1819 Buffalo Road
West Des Moines, Iowa 50265
Purchase Order
Number
BID ITEMS
Description Unit
Contract ID
PAY REQUEST
c:\pw_workdir\pw_ie\fvd_amw2\d1000870\PR5_2026_0501_6th Street Culvert.xlsm
PR5_2026_0501_6th Street Culvert.xlsm
Page 1 of 3
9.8 9040-O-1000 STABILIZED CONSTRUCTION EXIT SY 167 $17.00 $2,839.00 0.00 $0.00
9.9 9040-T-1000 INLET PROTECTION DEVICE, INSTALLATION EA 2 $185.00 $370.00 2.00 $370.00
9.10 9040-T-2000 INLET PROTECTION DEVICE, MAINTENANCE AND
REMOVAL EA 2 $10.00 $20.00 2.00 $20.00
9.11 9060-F-1000 TEMPORARY CONSTRUCTION FENCE LF 950 $3.70 $3,515.00 0.00 $0.00
DIVISION 10 - DEMOLITION
10.1 (NOT USED)$0.00 $0.00
DIVISION 11 - MISCELLANEOUS
11.1 11020-A-1000 MOBILIZATION LS 1.0 $34,000.00 $34,000.00 1.00 $34,000.00
11.2 11050-A-1000 CONCRETE WASHOUT LS 1.0 $1,000.00 $1,000.00 1.00 $1,000.00
DIVISION 12 - STRUCTURES
12.1 2107-0425020 COMPACTING BACKFILL ADJACENT TO BRIDGES,
CULVERTS, OR STRUCTURES CY 120.0 $42.00 $5,040.00 120.00 $5,040.00
12.2 2402-0425040 FLOODED BACKFILL CY 156.0 $50.00 $7,800.00 156.00 $7,800.00
12.3 2402-2720000 EXCAVATION, CLASS 20 CY 1370.0 $4.20 $5,754.00 1370.00 $5,754.00
12.4 2402-3825025 GRANULAR MATERIAL FOR BLANKET CY 172.0 $76.00 $13,072.00 172.00 $13,072.00
12.5 2403-0100020 STRUCTURAL CONCRETE (RCB CULVERT)CY 386.2 $600.00 $231,720.00 386.20 $231,720.00
12.6 2404-7775000 REINFORCING STEEL LB 61335.0 $1.00 $61,335.00 61335.00 $61,335.00
12.7 2414-6460000 ORNAMENTAL METAL RAILING LF 171.2 $249.00 $42,628.80 171.20 $42,628.80
CO 12.8 SPECIAL DEBRIS REMOVAL LS 1.0 $18,900.00 $18,900.00 1.00 $18,900.00
# of Units Unit Price Extended Cost
$0.00
3.0%
MATERIALS STORED SUMMARY
Description
Approved Change Order 1
TOTAL
PAY REQUEST SUMMARY
$630,797.60
Total Approved
$648,212.67Contract Price
$18,900.00
TOTAL $664,397.60 $648,212.67
$19,446.38
$0.00
Approved Change Order 2
Total Earned Less Retainage
Retainage
$648,212.67
Materials Stored $0.00
Revised Contract Price
$14,700.00
$628,766.29
$664,397.60
Approved Change Order 3
Total Completed
c:\pw_workdir\pw_ie\fvd_amw2\d1000870\PR5_2026_0501_6th Street Culvert.xlsm
PR5_2026_0501_6th Street Culvert.xlsm
Page 2 of 3
The amount $4,304.82
Pay Request 4
Total Previously Approved (list each)
Pay Request 10
Pay Request 5
94.0%
$624,461.47Total Previously Approved
Percent of Contract Period Utilized (In Calendar Days, Based on Notice to Proceed Date & Contract Completion Date)
Pay Request 7
Amount Due This Request
Pay Request 8
is recommended for approval for payment in
accordance with the terms of the Contract.
Pay Request 9
Pay Request 2
Pay Request 1 $266,819.59
Pay Request 6
$222,516.42
$15,044.31
97.6%
$120,081.15
Percent Complete
$4,304.82
Pay Request 3