CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: June 15, 2026
AGENDA ITEM:Consideration of approval of Change Order No. 1 to Elder Corporation
for the 10th Street Extension Project, decreasing the contract in the
amount of $23,976.50.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 1 is for revision to the contract to
adjust sanitary sewer alignment and avoid routing beneath the future forebay and lake. The layout
was refined after bidding, resulting in an adjusted quantity of pipe and structures. It also modifies
pipe classes for the 60-inch and 72-inch storm sewer, as proposed installation depths exceeded
SUDAS limits for Class III pipe, requiring the substitution to Class IV pipe material.
Additionally, this change order adds erosion stone for rock check dams to provide temporary
erosion control based on field conditions.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order decreases the contract price in the amount of $23,976.50.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 1
II. Letter of Recommendation
PREPARED BY:Lisa Bauman
REVIEWED BY:Sara Kappos
I1H4
S-H Project No.: 4203290
June 10, 2026
Rudy Koester, Public Works Director
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: Change Order #1 – Review and Recommendation to Approve
10th Street Extension
Dear Mr. Koester:
Please find attached Change Order #1 for the 10th Street Extension project. The change order includes
the following items:
• Reduction of 24” Sanitary Sewer Pipe.
• Reduction of Class III 60-inch Storm Pipe
• Reduction of Class III 72-inch Storm Pipe
• Addition of 60” Sanitary Manhole.
• Reduction of 72” Sanitary Manhole
• Additional Clearing, Grubbing & Survey for Sanitary Sewer Alignment Change
• Addition of Class IV 60-inch Storm Pipe
• Addition of Class IV 72-inch Storm Pipe
• Addition of Erosion Stone
This change order revises the contract to adjust sewer alignment and avoid routing beneath the future
forebay and lake. The layout was refined after bidding, resulting in an adjusted quantity of pipe and
structures. It also modifies pipe classes for the 60-inch and 72-inch storm sewer, as proposed
installation depths exceeded SUDAS limits for Class III pipe, requiring the substitution to Class IV pipe
material. Additionally, this change order adds erosion stone for rock check dams to provide temporary
erosion control based on field conditions.
We have reviewed the change order items and unit prices, and both are in line with anticipated
amounts. If City staff concurs with this change, we recommend the City of Waukee approve this change
order deduct in the amount of $23,976.50 to the construction contract for the 10th Street Extension
project with Elder Corporation of Des Moines, IA.
Sincerely,
SHIVE-HATTERY, INC.
Patrick M. Watts, PE
Civil Engineer
Enc. Change Order #1
CITY OF WAUKEE
230 W HICKMAN ROAD
WAUKEE, IOWA 50263
Contractor:
5088 E University Avenue
Des Moines, IA $23,240,000.00 4/6/2026
18A LF $ 620.00 (118.00) $ (73,160.00)
32A LF $ 400.00 (599.00) $ (239,600.00)
33A LF $ 490.00 (586.00) $ (287,140.00)
70A EA $ 11,000.00 1.00 $ 11,000.00
71A EA $ 11,000.00 (1.00) $ (11,000.00)
CO-1.1 LS $ 3,700.00 1.00 $ 3,700.00
CO-1.2 LF $ 431.00 599.00 $ 258,169.00
CO-1.3 LF $ 532.00 586.00 $ 311,752.00
CO-1.4 TON $ 76.75 30.00 $ 2,302.50
$ (23,976.50)
$23,240,000.00
$0.00
$23,240,000.00
($23,976.50)
$23,216,023.50
-0.10%
0 Days
0 Days
August 13, 2027
September 30, 2027
Title: Project Manager
Date:
The new Contract Sum including this Change Order will be
Date:
Approved By:
City of Waukee
Signature:
Name: Brad Deets
Title: City Administrator
Date:
Recommended By:
Shive-Hattery Inc.
Signature:
Name: Patrick Watts
Title: Civil Engineer
Contractor:
2240021750
Net Change by previously authorized Change Orders
The Contract Sum prior to This Change Order was
The Contract Sum will be increased by this Change Order in the amount of
Description
THE CONTRACT IS CHANGED AS FOLLOWS:
Item 18A - "SANITARY SEWER G-MAIN, TRENCHED, 24 IN."; Decrease in the 24-inch sanitary sewer gravity main quantity. At the time of bidding, the future forebay and future lake layout was preliminary. However, prior to
installation, the design was refined and the sanitary sewer alignment was adjusted to avoid routing beneath the future forebay and lake, resulting in a reduced quantity.
Item 32A - "STORM SEWER, TRENCHED, RCP CLASS III, 60 IN."; Removal of the 60-inch Class III storm pipe. During submittal review, it was determined that the proposed installation depth exceeded the allowable limits for Class III
pipe per SUDAS requirements, necessitating the removal 60 inch Class III pipe.
Item 33A - "STORM SEWER, TRENCHED, RCP CLASS III, 72 IN."; Removal of the 72-inch Class III storm pipe. During submittal review, it was determined that the proposed installation depth exceeded the allowable limits for Class III
pipe per SUDAS requirements, necessitating the removal 72 inch Class III pipe.
Item 70A - "MANHOLE, SW-301,60 IN."; Increase in the number of 60-inch SW-301 manholes. Following refinement of the sanitary sewer alignment, improved pipe entry and exit angles were achieved at MH-2.12, allowing for the use
of a smaller manhole and resulting in the increase of one manhole from the original design.
Item 71A - "MANHOLE, SW-301, 72 IN."; Decrease in the number of 72-inch SW-301 manholes. Following refinement of the sanitary sewer alignment, improved pipe entry and exit angles were achieved at MH-2.12, allowing for the
use of a smaller manhole and resulting in the reduction of one manhole from the original design.
CO-1.1 - "ADDITIONAL SANITARY SEWER CLEARING, GRUBBING & SURVEY"; Addition of clearing, grubbing, and survey work resulting from the revised sanitary sewer alignment. The alignment adjustment required expansion of
construction limits to accommodate the revised layout, necessitating additional clearing, grubbing, and survey beyond the original scope.
CO-1.2 - "STORM SEWER, TRENCHED, RCP CLASS IV, 60 IN."; Addition of the 60-inch Class IV storm pipe. During submittal review, it was determined that the proposed installation depth exceeded the allowable limits for Class III
pipe per SUDAS requirements, necessitating the addition of Class IV 60-inch pipe.
CO-1.3 - "STORM SEWER, TRENCHED, RCP CLASS IV, 72 IN."; Addition of the 72-inch Class IV storm pipe. During submittal review, it was determined that the proposed installation depth exceeded the allowable limits for Class III
pipe per SUDAS requirements, necessitating the addition of Class IV 72-inch pipe.
CO-1.4 - "EROSION STONE"; Addition of erosion stone for construction of check dams. Erosion stone was added to the project to provide temporary erosion control measures in accordance with project needs and field conditions.
Item Value Adjustment
CHANGE ORDER SUMMARY
Quantity AdjustmentUnit Price
ADDITIONAL SANITARY SEWER CLEARING, GRUBBING &
SURVEY
Vanderpool Construction
Elder Corporation
Signature:
Name: Nick Tometich
The Landscaping/Site Restoration/Final Completion Contract Time will be changed by
STORM SEWER, TRENCHED, RCP CLASS III, 60 IN.
STORM SEWER, TRENCHED, RCP CLASS III, 72 IN.
The Grading/Structure/Utility/Paving Contract Time will be changed by
The date of Grading/Structure/Utility/Paving Completion as of the date of this Change Order therefore is
STORM SEWER, TRENCHED, RCP CLASS IV, 60 IN.
STORM SEWER, TRENCHED, RCP CLASS IV, 72 IN.
EROSION STONE
SANITARY SEWER G-MAIN, TRENCHED, 24 IN.
MANHOLE, SW-301, 72 IN.
MANHOLE, SW-301, 60 IN.
CHANGE ORDER
Aggregate Change Order as a percent of Original Contract
The date of Landscaping/Site Restoration/Final Completion as of the date of this Change Order therefore is
NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER
Project Title
S-H Project File Number
Orig. Contract Amount & Date
Change Order Number
Date
1
The Original Contract Sum was
Unit
June 10, 2026
10th Street Extension
1 of 1
06/11/2026 06/11/2026