HomeMy WebLinkAbout2018-03-05-Resolutions 18-079_Little Walnut Creek Trunk Sewer Phase 4 - Approve Plans - SpecsRESOLUTION 18-079
RESOLUTION ADOPTING PLANS,SPECIFICATIONS,FORM
OF CONTRACT AND ESTIMATE OF COST FOR THE LITTLE
WALNUT CREEK TRUNK SEWER EXTENSION -PHASE 4
WHEREAS,on the 13'"day of February,2018,plans,specifications,form of contract
and estimate of cost were filed with the Clerk for the construction of certain public
improvements described in general as the Little Walnut Creek Trunk Sewer Extension -Phase 4;
and
WHEREAS,notice of hearing on plans,specifications,form of contract and estimate of
cost for the public improvements was published as required by law:
NOW,THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WAUKEE,STATE OF IOWA:
Section 1.That the plans,specifications,form of contract and estimate of cost are hereby
approved as the plans,specifications,form of contract and estimate of cost for the public
improvements,as described in the preamble of this Resolution.
PASSED AND APPROVED this 5th day of March,2018.
ayor P em
ATTEST
City Clerk
RESULTS OF VOTE:
Anna Bergman
R.Charles Bottenberg
Courtney Clarke
Shelly Hughes
Larry R.Lyon
AYE
X
X
X
X
X
NAY ABSENT ABSTAIN