HomeMy WebLinkAbout2017-11-20-Resolutions 17-528_Alice's Rd Gas Main Relocation - Award ContractsRESOLUTION 17-528 RESOLUTION MAKING AWARD OF CONTRACTS WHEREAS,Bid Package A and Bid Package B are identical except for the delivery dates;and WHEREAS,Bid Package A has a required delivery date of February I,2018; WHEREAS,Bid Package B has a required delivery date of March I,2018;and WHEREAS,both Bid Package A and Bid Package B were for the gas main pipe and associated materials;and WHEREAS,Bid Package C is for the electrical material components related to the gas main project;and WHEREAS,Consolidated Pipe &Supply Co.of Valleypark,Missouri submitted the apparent low bid for Bid Package A and Bid Package B;and WHEREAS,Consolidated Pipe &Supply Co.included G10 gaskets in its bid instead of the specified Phenolic gaskets;and WHEREAS,the Project Engineer has determined that the G10 gaskets are equivalent to the specified Phenolic gaskets and,accordingly,are approved equals;and WHEREAS,the Project Engineer has recommended the City award a contract for Bid Package A,accepting G10 gaskets as approved equals,to Consolidated Pipe & Supply Co.;and WHEREAS,Border State Industries,Inc.of Grand Haven,Michigan submitted the only bid for Bid Package C;and WHEREAS,Border State Industries did not include a bid for item No.3.16 for four compression lugs for use with ¹12 AWG cable;and WHEREAS,the total value for bid item No.3.16 is estimated to be less than $10.00;and WHEREAS,Border State Industries'bid did not include the specified decals for bid item No.3.4 for the test stations;and WHERAS,the Project Engineer states that the specified decals for bid item No. 3.4 are minor;and WHEREAS,the Project Engineer has recommended the City award a contract for Bid Package C to Border State Industries,Inc.that eliminates the specified decals for bid item No.3.4 for the test stations and the four compression lugs specified as item No. 3.16;and WHEREAS,the City Council has the authority to waive informalities and technicalities in any bid and to accept the bid which it deems to be in the best interests of the City: NOW,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WAUKEE,STATE OF IOWA: Section 1.That the following bids for the Supply of Materials for the Alice's Road Gas Main Relocation Project,described in the plans and specifications heretofore adopted by this Council on November 20,2017 and as modified as described herein,be and are hereby accepted, the same being the lowest responsive,responsible bids received for such work,as follows: Contractor:Consolidated Pipe &Su ly Co.of Valle ark,MO Amount of bid:$117,749.28 Portion of project:All Costs for Bid Package Alternate A Contractor:Border States Industries,Inc.,of GrandHaven,MI Amount of bid:$29,925.44 Portion of project:All Costs for Bid Package Alternate C Section 2.That the Mayor and Clerk are hereby directed to execute conuacts with the contractors for the Supply of Materials for the Alice's Road Gas Main Relocation Project,such contracts not to be binding on the City until approved by this Council. PASSED AND APPROVED this 20th day of November,2017. M ATTEST: City Clerk ROLL CALL VOTE Anna Bergman R.Charles Bottenberg Brian Harrison Shelly Hughes Larry R.Lyon AYE X X X X NAY ABSENT ABSTAIN