HomeMy WebLinkAbout2018-08-06-Resolutions 18-313_Windfield-High School Trail Phase 1 - Accept ImprovementsRESOLUTION 18-313
RESOLUTION ACCEPTING THE WINDFIELD/HIGH SCHOOL TRAIL-
PHASEI
WHEREAS,on the 18 day of September,2017,the Mayor and Clerk of the City of
Waukee,Iowa,entered into a construction contract with Concrete Professionals of Altoona,IA,
for the construction of certain public improvements generally described as the Windfield(High
School Trail -Phase I;and
WHEREAS,the contractor has fully completed the construction of the public
improvements in accordance with the terms and conditions of the contract and plans and
specifications,as shown by the certificate of the Engineer filed with the Clerk on July 31,2018:
NOW,THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WAUKEE,IOWA:
Section 1.That the report of the Engineer be and the same is hereby approved and
adopted,and the public improvements are hereby approved and accepted as having been fully
completed in accordance with the plans,specifications and form of contract and the total final
construction cost thereof is hereby determined to be $139,779.01,as shown in the report of the
Engineer.
PASSED AND APPROVED this 6'"day of August,2018.
ayor
ATTEST
City Clerk
RESULTS OF VOTE:
Anna Bergman
R.Charles Bottenberg
Courtney Clarke
Shelly Hughes
Larry R.Lyon
AYE
X
X
X
X
NAY ABSENT ABSTAIN