HomeMy WebLinkAbout2019-02-04-Resolutions 19-048_NW Area Water Main Extension Phase 2 - Award ContractRESOLUTION 19-048
RESOLUTION MAKING AWARD OF CONSTRUCTION
CONTRACT FOR THE NORTHWEST AREA WATER MAIN
EXTENSION -PHASE 2
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WAUKEE,STATE
OF IOWA:
Section 1.That the following bid for the construction of certain public improvements
described in general as the Northwest Area Water Main Extension —Phase 2,described in the
plans and specifications heretofore adopted by this Council on January 21,2019,be and is
hereby accepted,the same being the lowest responsive,responsible bid received for such work,
as follows:
Contractor:Keller Excavating
Amount of bid:$1,286,586.00
of Boone,IA
Portion of project:All construction work
Section 2.That the Mayor and Clerk are hereby directed to execute the contract with the
contractor for the construction of the public improvements,such contract not to be binding on the
City until approved by this Council.
PASSED AND APPROVED this 4th day of February,2019.
or
ATTEST:
City Clerk
RESULTS OF VOTE:
Anna Bergman
R.Charles Bottenberg
Courtney Clarke
Shelly Hughes
Larry R.Lyon
AYE
X
X
X
X
X