HomeMy WebLinkAbout2016-03-07-Resolutions 16-081_NE Douglas Pkwy Extension - Engineering Agr Amendment 1THE CITY OF WAUKEE,IOWA
RESOLUTION 16-081
APPROVING AMENDMENT NO.I TO AN AGREEMKNT FOR ENGINEERING
SERVICES WITH FOTH INFRASTRUCTURE AND ENVIRONMENT,LLC [NE
DOUGLAS PARKWAY EXTENSION PROJECT FROM NE ALICE'S ROAD WEST]
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE,IOWA
WHEREAS,the City of Waukee,Dallas County,State of Iowa,is a duly organized Municipal
Organization;AND,
WHEREAS,on June 15,2015,the Waukee City Council approved an Agreement for
Engineering Services with Foth Infrastructure and Environment,LLC,related to the NE Douglas
Parkway Extension Project from NE Alice's Road west (Resolution JJ15-200);AND,
WHEREAS,the City proposes an Amendment to the Engineering Services Agreement for
wetland mitigation,temporary traffic signal design,design related to the intersection of NE
Douglas Parkway and NE Alice's Road as well as additional project coordination;AND,
WHEREAS,the engineering services amendment,attached hereto as Exhibit A,has been
reviewed and approved by the Waukee City Attorney.
NOW THEREFORE BE IT RESOLVED by the City Council of the City of Waukee that the
Amendment No,1 to an Agreement for Engineering Services with Foth Infrastructure and
Environment,LLC [NE Douglas Parkway Extension Project from NE Alice's Road west]is
hereby approved.
Passed by the City Council of the City of Waukee,Iowa,and approved the 7'"day of March,
2016.
Rick Peters,Mayor Pro Tem
Attest:
Rebecca D.Schuett,City Clerk
ROLL CALL VOTE
Shane Blanchard
Brian Harrison
Shelly Hughes
Larry R.Lyon
Rick Peterson
AYE
X
X
X
NAY ABSENT ABSTAIN
X
X
Fath infrastructure end Environment,LLC
Prolecl Number 14W024.01
Douglas Parkway Exienmon
Abces Road West h320-ft
Waukee,iowa
ENGINEERING SERVICES AMENDMENT NO.1
PROJECT NO.
THIS AIVIENDMENT,made and entered into this IK day of y ~ff 6 2016byandbetween,
the CITY OF WAUKEE,IOWA,hereinafter referred to as the "City",and FOTH INFRASTRUCTURE AND
ENVIRONMENT,LLC.,hereinafter referred to as the "Engineer",for professional services in connection with the
cence tualdesi n rebmina surya andma in fuctionaldesi n.ro'ectcoordination relimina desi n final lans
and s ecifications for the ro used construction of NE Dou las Parkwa from NE Alices Road west 1 320-ft hereby
amends the original Agreement dated June,2015 as follows;
The City and Engineer agree to amend the original Agreement to include additional services associated with:
~NE Douglas Parkway Mitigation Plan and 404 Permit
~Temporary Traffic Signal Design
~Design of the NE Alices Road Widening and Intersection Improvements at NE Douglas Parkway
~Additional Project Coordination with City of Clive
~Additional Project Coordination with Adjacent Landowner's Engineering Consultant
TASK A —NE Douglas Parkway Mitigation Plan and Section 404 Permit:
Wetland delineation surveys were completed in 2015 along on the corridor.The Engineer will prepare and submit a
Section 404 Permit Application containing the applicable data,wetland jurisdictional rationale,and proposed project
information to the USACE,lowe Department of Natural Resources (iDNR)Flood Plain Section,and IDNR Sovereign
Lands Section necessary to receive environmental approval.The City shall understand that the Engineer cannot
guarantee that the USACE or other relevant governmental agencies will ultimately approve the prepared application,
since such authorization is beyond their control.
Task A1 Coordination with other Re ulato A encies
The Engineer will prepare and submit a Section 404 Permit Application containing the applicable data,wetland
jurisdictional rationale,and proposed project information to the USAGE,lowe Department of Natural Resources
(IDNR)Flood Plain Section,and IDNR Sovereign Lands Section.We will also prepare a Mitigation Plan for the
project to meet Section 404 permitting requirements.The Engineer will contact the IDNR regarding potential
threatened and endangered species that may be affected by the project.The Mitigation Plan will summarize
each wetland and WUS area that will be impacted by the project based on the findings in our Weiland
Delineation Report dated July 15,2015 and the proposed site layout plan for the project.
Task A 2 Coordination with Voas Miti ation Bank
The Engineer will coordinate with the Voas Wetland Mitigation Bank regarding the purchase of credits for
emergent and wet meadow wetland impacts.Please note that the Voas Wetland Mitigation Bank does not offe
credits for forested or shrub/scrub wetland impacts or for stream mitigation.The USAGE may require onsite
mitigation of forested wetlands,trees plantings,and/or stream mitigation measures to offset potential impacts
from the proposed project.
Task A.3 Miti ation Plan
During the preparation of the Mitigation Plan,the Engineer will coordinate with the USAGE to assess what
mitigation measures will be required based on the proposed impacts.The Mitigation Plan will include a
discussion of the proposed impacts and a summary of the credits that will be purchased from the Voas Wetland
Mitigation Bank
Page 1
Foth Infrastructure and Environment,LLC
Project Number 14W024.01
Douglas Parkway Extension
Alices Road West 1,320-ft
Waukee,lowe
Fees assume that the City of Waukee will investigate and provide the required financial assurances that may be
required by the USAGE for the project,including construction bonds and escrow accounts.Because the City of
Waukee is a pubkc entity,the USAGE may accept a Letter of Commitment in lieu traditional financial
assurances.
The City should understand that a miligation plan is a conceptual design to outline the details of mitigation
activities proposed for the site for regulatory approval.It should not be relied upon for construction If WUS
mitigation or tree/shrub planting is required by the USAGE,we recommend that delailed engineering plans and
specifications be developed upon USACE approval of the mttigation plan and prior to construction.City shall
understand that the Engineer cannot guarantee that the USACE or other relevant governmental agencies will
ultimately approve the prepared application,since such authorization is beyond their control.
The Engineer will also prepare an approximate engineering cost estimate for the construction of the mitigation
area.
Task A.4 Additional Services be ond base Services
Fees assume that wetland mitigation will occur at the Voas Wetland Mitigation Bank and that stream mitigation
will not be a requirement of the USAGE;additional fees may be incurred if mitigation occurs at an alternate
location.Banking fees are not included in the scope of this proposal.Fees do not include Alternative Analysis,
WUS Mitigation Plan or hydrologic modeling that may be needed for the design of WUS mitigation.Fees also
do not include Cultural Resource or Threatened and Endangered Species surveys.Fees for addressing
USAGE or other agencies comments during the permitting process will be invoiced on a time and material basis
based on the Engineer's current fee schedule.Additional fees for construction observation,annual monitoring,
or deed restriction preparation may be incurred if tree/shrub planting or WUS mitigation is required.
This proposal does not include fees for Wetland Delineation,Phase I Cultural Resource Survey and topographic
survey services that may be required if an off-site mitigation area is selected.Fees for those surveys have not
been included in this proposal,but will be provided when the mitigation site is identified.This proposal does not
include property negotiations or legal fees necessary for the purchase or easement of the land selected for off-
stte mitigation.
Task A Subtotal —$5,000.00
TASK B —Temporary Traffic Signalization at NE Douglas Parkway and NE Alices Road
The Engineer will complete a Traffic Signal Warrant Analysis at the intersection of NE Douglas Parkway and NE Alices
Road to determine traffic signal requirements then develop temporary traffic signal plans at the intersection of NE
Douglas Parkway and NE Alices Road using available design standards of the City and the Manual on Uniform Traffic
Control Devices (MUTCD).Signal Layout,signal timing,coordination plans will be developed.
Task 8 Subtotal -$8,000.00
TASK 0 —Design of the NE Alices Road Widening and Intersection Improvements at NE Douglas Parkway
The current NE Douglas Parkway and NE Alices Road is a 3-Ieg intersection that does not accommodate any dedicated
turning movements from NE Alices Road onto NE Douglas Parkway.The proposed design calls for construction of the
fourth leg and providing dedicated left turn movements in all directions and dedicated right turn lanes in the northbound,
southbound,and eastbound directions.To accommodate these movement,NE Alices Road will be widen along the west
pavement edge from approximately 500-ft south of NE Douglas Parkway to 650-ft north of NE Douglas Parkway.Tasks
to be completed include:
Page 2
Foth Infrastructure end Environment,LLC
Project Number 14W024.01
Douglas Parkway Extension
Atices Road West 1,320-lt
Wsukee,lowe
Task C1 Additional To o ra hie Surve
The Engineer shall perform additional topographic survey required for the development of the NE Alices Rd
widening,Horizontal and vertical accuracies shall be adequate to produce a map that is compatible with
the topographic data for mcorporation inio the existing mapping.Task includes roadway cross-sectioning at
appropriate intervals indicating the location and elevation of key section breaks,including approximate
roadway centerline,edge of pavement and/or gutter 8 top-of-curb,sidewalks and driveways.This
informatron will be used to develop the existing roadway DTM for the Project site.
Task C 2 Final Plans
The Engineer will perform final design services in the preparation of design plans and specifications depicting
the proposed grading,drainage,paving,signing,utility relocation,and other features of the project.The
preliminary plans will include but not be limited to the following tasks:
Task C 2 1 Final Plan and Profiles E Sheets
This task consists of the development of preliminary plan and profile sheets that will show the existing
topography along with the proposed improvements based on the survey or the office relocation
centerline.Proposed Right-of-Way and Construction Easement limits based on the catch point lines
will be shown.Included will be the necessary CADD work to show the preliminary design features for
the proposed improvements.The scale of these sheets will be 1"=303
Task C 2 2 Final Traffic Control and Sta in J Sheets
This task consists of developing a suitable plan for construction scheduling and staging of the Project
and for traffic control measures to be implemented during construction.
Task C 2 3 Final Markin s and Traffic Si nin J Sheets
This task consists of the development of pavement marking and traffic signing plans to be placed into
service following construction.The traffic control devices,procedures,and layouts shall be as per the
Manual on Uniform Traffic Control Devices (MUTCD).
Task C 2.4 Final Intersection Geometries L Sheets
This task consists of developing and refining the geometric layouts and provides additional horizontal
and vertical survey information needed to construct the intersections.The scale of these plan sheets
will be 1"=203
Task C 2 5 Final S ecial Construction Details U Sheets
This task consists of preliminary design and drafting associated with special project details.Special
construction details include:
~Special Grading at the northwest corner of NE Douglas Parkway and NE Alices Road.
Task C.2 6 Detailed Cross Sections X Sheets
This task consists of the design and drafting associated with the assembly of detailed cross sections
(50'increments)along NE Alices Road to illustrate typical conditions,drainage designs,and non-
typical conditions as needed for guidance during design,review,and quantity estimating purposes.
Task C Subtotal -$40,000.00
TASK D —Project Coordination with the City of Ciive
The Engineer will complete the following project coordination as part of the project.
Task D.1 Pediodic Meetin s with Cit Staff
Informational update presentations will be provided to the City Staff on an as needed basis during the
Final Design process and Construction.The presentations will provide anintroduction/overview of the
project and project goals and objectives.It will also provide an update on design development
concepts and schedule.For estimating purposes,it is assumed that the Consultant will attend one (1)
meeting every other month for 8 months.
Page 3
Fotti Infrastructure and Environment,LLC
Project Number 14W 024 01
Douglas Parkway Extension
Alices Road West L320-It
Waukee,iowa
Task D.2 Exhibit Pre aration
Exhibits for the project meetings will consist of aerial mosaics for the project with the major project features
mdicated on the aerial photograph.Include coloring,lettering,and other techniques to delineate the
proposed design concepts and right of-way needs,including typical sections of the roadway.The figure will
indicate possible wetlands,wetland mitigation site,right-of-way needs,property lines,property ownership,
access control lines,grading limits,and new roadway improvements.
Task D Subtotal -$4,000.00
TASK E —Project Coordination with Adjacent Landowner's Engineering Consultant
The Engineer will conduct meetings to address specific conflicts and concerns.It is anticipated that there will
be ~two 2 meeting(sj with representatives of the adjacent Landowner.The first will be to advise of the nature
and extent of the improvements and any potential conflicts with existing or proposed utility systems,and the
second will be preliminary/final design review and coordination meetings.
Task E Subtotal -$8,000.00
In consideration for these services,the City agrees to adjust the Contract Schedule for services performed by the
Engineer under this Contract Amendment of the original project.
Basic Services of the Engineer
G.Project Letting
H.Construction Administration
March 2016
March 2016 —September 2016
jn consideration for these services,the City agrees to adjust the compensation for services performed by the Engineer.
These fees are based on the standard hourly rates of the Engineer's personnel actually engaged in the performance of
the services,plus direct out-of-pocket costs for expenses incurred by personnel who are actually engaged in the work
and other direct costs,The total Hourly Not-to-Exceed fees for the professional engineering services as described in this
amendment are as follows:
I.Basic Services of the Engineer
Task A
Task B
Task C
Task D
Task E
Total
$5,000.00$8,000.00
$40,000.00$4,000.00
8 000.00
$65,000.00
THIS AMENDMENT is subject to all provisions of the original Agreement.
THIS AMENDMENT,together with the original Agreement represents the entire and integrated AGREEMENT
between the City and Engineer.
THIS AMENDMENT executed the day and year written above.
FOTH INFRASTRUCTURE AND ENVIRONMENT,LLC.CITY OF WAUKEE,IOWA
By:By:
Patrick P.Kueter Client Director
X ioualsu014114w024 0111000sudgenAg .201 0 0212 Waukee oougiaa PkuurAmeod no 1 doo
Page 4