CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: January 18, 2021
AGENDA ITEM:Public Hearing on proposed plans, specifications, form of contract and
estimate of cost [SE Ashworth Road Corridor Improvements Project, SE
Parkview Crossing Drive to SE Glacier Trail]
FORMAT:Public Hearing
SYNOPSIS INCLUDING PRO & CON: The SE Ashworth Road Corridor Improvements
Street project includes all materials, labor and equipment necessary for installation of
approximately: 50,000 CY of Grading, 27,000 SY of Modified Subbase, 21,000 SY of 10" PCC
Pavement, 2,100 SY of PCC Trail/Sidewalk, 800 SY of PCC Driveway, 3,500 SY of Temporary
Pavement, 1,200 LF of Water Main, 4,000 LF of Storm Sewer, 700 LF of Sanitary Sewer, 34 EA
Intakes or Manholes, 1,600 LF of Joint Utility Trench, Traffic Signalizal Modification, Lighting,
surface restoration and miscellaneous related work and appurtenances. This project is included in
the proposed FY 2022 Capital Improvements Plan to be considered for approved by City Council
in March 2021 with a total project budget of $6,680,000.00. This project has a completion date
of September 30, 2022.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Hold Public Hearing.
ATTACHMENTS: I. Notice of Public Hearing
PREPARED BY:Beth Richardson
REVIEWED BY:Rudy Koester RK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
G1
NOTICE OF PUBLIC HEARING
NPH - 1
SE ASHWORTH ROAD CORRIDOR IMPROVEMENTS
SE PARKVIEWCROSSING DRIVE TO SE GLACIER TRAIL
WAUKEE, IOWA
FOTH PROJECT NO. 19W019.01
The City Council of Waukee, Iowa, will hold a public hearing on the proposed Plans,
Specifications, Form of Contract, and Estimate of Costs for the construction of the above
referenced public improvements at 5:30 p.m. on Monday, January 18, 2021. At said hearing, any
interested person may appear and file objections thereto or to the cost of the improvements.
Due to public health concerns and guidance, in accordance with Iowa Code Sections 21.4(1)(b)
and 21.8, this meeting of the Waukee City Council will be conducted electronically as holding
the meeting in person is impossible or impractical. However, the public is encouraged to access
the meeting electronically in the manner specified below.
The meeting shall be conducted via Zoom at the following link or phone numbers:
https://zoom.us/j/352651371
Meeting ID: 352-651-371
Or by phone:
+1 646-558-8656 or
+1 312-626-6799 or
+1 301-715-8592
All persons wishing to observe or participate in this meeting may do so via Zoom or telephone.
Please contact the City Clerk’s office at 978-7904 or bschuett@waukee.org if you have questions
or electronic accessibility issues.
This project includes the furnishing of all labor, equipment, and materials for the construction of
the SE Ashworth Road Corridor Improvements from SE Parkviewcrossing Drive to SE Glacier
Trail in Waukee, generally described as follows:
Construct the SE Ashworth Road Corridor Improvements including all materials, labor
and equipment necessary for installation of approximately: 50,000 CY of Grading,
27,000 SY of Modified Subbase, 21,000 SY of 10" PCC Pavement, 2,100 SY of PCC
Trail/Sidewalk, 800 SY of PCC Driveway, 3,500 SY of Temporary Pavement, 1,200
LF of Water Main, 4,000 LF of Storm Sewer, 700 LF of Sanitary Sewer, 34 EA
Intakes or Manholes, 1,600 LF of Joint Utility Trench, Traffic Signalizal
Modification, Lighting, surface restoration and miscellaneous related work and
appurtenances.
______________________________
Courtney Clark, Mayor
ATTEST:
NOTICE OF PUBLIC HEARING
NPH -2
Rebecca D. Schuett, City Clerk
Publish: December 31, 2020