AGENDA ITEM:Consideration of approval of a resolution approving contract, bond [Lift
Station No. 3 Rehabilitation Phase 3, Wet Well Repairs Project]
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON:
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:$127,300.00
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the resolution approving contract and bond with Woodruff
Construction, Inc., in the amount of $127,300.00.
ATTACHMENTS: I. Proposed Resolution
II. Contract, Bond
PREPARED BY: Becky Schuett
REVIEWED BY:
J1M
RESOLUTION 2021-
RESOLUTION APPROVING CONSTRUCTION CONTRACT
AND BOND FOR THE LIFT STATION NO. 3
REHABILITATION PHASE 3, WET WELL REPAIRS
PROJECT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WAUKEE, STATE
OF IOWA:
That the construction contract and bond executed and insurance coverage for the
construction of certain public improvements described in general as the Lift Station No. 3
Rehabilitation Phase 3, Wet Well Repairs Project, and which have been signed by the Mayor and
Clerk on behalf of the City be and the same are hereby approved as follows:
Contractor: Woodruff Construction, Inc., of Ames, IA
Amount of bid: $127,300.00
Bond surety: Liberty Mutual Insurance Company
Date of bond: January 25, 2021
Portion of project: All construction work
PASSED AND APPROVED this 1st day of February, 2021.
Mayor
ATTEST:
City Clerk
RESULTS OF VOTE: AYE NAY ABSENT ABSTAIN
Anna Bergman
R. Charles Bottenberg
Chris Crone
Larry R. Lyon
Ben Sinclair