HomeMy WebLinkAbout2021-05-03-J01U Library Stormwater Improvements_Change Order 6AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: May 3, 2021
AGENDA ITEM:Consideration of approval of Change Order No. 6 to Elder Corporation
for the Waukee Public Library Stormwater Improvements increasing the
contract amount by $28,169.00.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 6 is for interpretive signage and
landscape planting bed renovation. The majority of the change order is
for interpretive signage which will be installed in both the interior and
exterior of the building to highlight the stormwater BMPs installed on
the site. The interpretive signage was a part of the $100,000 IDALS WQI
grant funding the project received. The remaining change order is for
rehabilitating an existing planter bed adjacent to the building.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $28,169.00.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the change order.
ATTACHMENTS: I. Change Order No. 6
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Rudy Koester RK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1U
Project# 4185870
April 27, 2021
TO: Rudy Koester
City of Waukee
805 University Ave
Waukee IA, 50263
RE: Change Order #6
Waukee Public Library Stormwater Improvements
SH Project Number 4185870
Mr. Koester,
Please find attached Change Order #6 for the Waukee Public Library Stormwater Improvements. The
change order includes the following items:
· Interpretive Signage
· Landscape Planting Bed Renovation
The interpretive signage elements will assist in communication of the water quality needs, goals, and
functions of the newly-installed stormwater best management practices (BMPs) to library visitors.
Funding for interpretive signage for the project was applied for and awarded as part of the Iowa
Department of Agriculture and Land Stewardship Water Quality Initiative – Urban Conservation
Demonstration Project grant program.
Current plantings have become overgrown in the existing raised planting bed integral to the building
north of the main entrance. It has been determined that it will be advantageous to complete a
renovation of this planting bed now while a landscape contractor is onsite for the bioretention cell
plantings.
We have reviewed the change order items and unit prices, both are line with anticipated amounts. If
City staff concurs with this change, we recommend the City of Waukee approve this change order in the
amount of $28,169.00 to the construction contract for the Waukee Public Library Stormwater
Improvements with Elder Corporation of Pleasant Hill, IA.
Sincerely,
Shive-Hattery, Inc.
Nathan Hardisty, PE
Project Manager
Enc. Change Order #6
City of Waukee
230 W Hickman Road
Waukee, IA 50263 Distribution:
Owner __X__
Engineer __X__
Contractor __X__
Contractor:
5088 East University Ave
Pleasant Hill, IA 50327 $2,162,580.00 May 4, 2020
CO-6.1 LS $12,000.00 1 $12,000.00
CO-6.2 EA $5,000.00 1 $5,000.00
CO-6.3 EA $4,600.00 1 $4,600.00
CO-6.4 LS $5,700.00 1 $5,700.00
CO-6.88A CY $79.00 11 $869.00
$28,169.00
$2,162,580.00
$17,664.40
$2,180,244.40
$28,169.00
$2,208,413.40
2.12%
0 Days
June 15, 2021
CHANGE ORDER
Aggregate Change Order as a percent of Original Contract
The date of Final Completion as of the date of this Change Order therefore is
NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER
Project Title
S-H Project File Number
Orig. Contract Amount & Date
Change Order Number
Date
6
The Contract Time will be changed by
TOTAL
The Original Contract Sum was
Unit
April 27, 2021
Contractor:
Elder Corporation
Elder Corporation
Signature:
Name:
Interpretive Signage - Picture Window Graphic Decals
Interpretive Signage - Graphic Sign Panel
Interpretive Signage - Exterior BMP Marker Signs
Renovate Existing Planter
Filtration Soil
Title:
Date:
Waukee Public Library Stormwater
Improvements
4185870
Net Change by previously authorized Change Orders
The Contract Sum prior to This Change Order was
The Contract Sum will be increased by this Change Order in the amount of
The new Contract Sum including this Change Order will be
Description
THE CONTRACT IS CHANGED AS FOLLOWS:
Change Order Items CO-6.1, CO-6.2, and CO-6.3 are to add interpretive signage fabrication and installation to the project. Exterior Stormwater Best Management
Practice (BMP) marker signs, an interior graphic sign panel, and window graphic decals will be installed. A Water Quality Initiative - Urban Conservation
Demonstration Project grant from the Iowa Department of Agriculture and Land Stewardship was applied for and awarded to this project, and a portion of the
grant funding received is to be directed toward signage and interpretation. These interpretive elements being added to the project to assist in communication of
the water quality needs, goals, and function of the installed BMPs to library visitors.
Change Order Items CO-6.4 and CO-6.88A are to add renovation of an existing planting bed to the project. At the existing raised planter integral to the building
wall north of the main entrance, existing vegetation and soils will be removed and new filtration planting soil, plantings, and mulch will be installed.
Item Value Adjustment
CHANGE ORDER SUMMARY
Quantity AdjustmentUnit Price
Date:
Approved By:
City of Waukee
Signature:
Name:
Title:
Date:
Recommended By:
Shive-Hattery
Signature:
Name: Nathan T. Hardisty, PE
Title: Project Manager
\\sh.shive-hattery.com\data\Projects\DM\4185870\Construction\Library\CASupport\Change Orders\CO #6\Waukee Public Library Stormwater Improvements Change Order #6.xlsx