HomeMy WebLinkAbout2021-05-17-I01Z Triumph Park_Pmt Est 7CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: May 17, 2021
AGENDA ITEM:Consideration of approval of Payment Estimate No. 7 to Larson Construction,
Co., Inc., for the Triumph Park Project in the amount of $605,508.11.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Payment Estimate No. 7 to Larson Construction, Co., Inc.,
is for general conditions, Building Foundations/SOG, masonry, structural steel
framing, metal roof/wall panels-soffit, electrical, earthwork, PCC Sidewalk,
construction of the retaining near the pond, and site utilities. The quantities
completed to date have been reviewed and agreed upon by the contractor, City
of Waukee Staff, and Confluence.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Letter of Recommendation
II. Payment Estimate No. 7
PREPARED BY: Matt Jermier
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
AGENDA ITEM: I1Z
thinkconfluence.com
May 3, 2021
Mr. Matt Jermier, Parks and Recreation Director
Parks and Recreation Department
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: Contractor Application for Payment #7 - Triumph Park
Dear Mr. Jermier:
Attached please find contractor Application for Payment #7 in the amount of $605,508.11 for approval and
signature by Waukee City Council. Quantities have been reviewed and agreed upon by the contractor, City staff,
and Confluence.
Confluence recommends approval and payment as indicated.
If there are any questions, please let me know.
Sincerely,
Confluence
Matthew O. Carlile, ASLA, LEED AP
Principal
Confluence
525 17th Street
Des Moines, Iowa 50309
Cc: Project File