AGENDA ITEM:Consideration of approval of Partial Payment Estimate No. 3 to Priority
Excavating, LLC for the Little Walnut Creek North Trunk Sewer Phase 1
and Water Main Extensions in the amount of $69,426.67.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Priority Excavating, LLC has requested Payment
Estimate No. 3 for the work completed on the Little Walnut Creek North Trunk Sewer Phase 1
and Water Main Extensions in the amount of $69,426.67. Veenstra & Kimm, Inc. has reviewed
the payment estimate and recommends payment.
The partial payment is for the pay period June 12, 2021 to July 2, 2021. This pay estimate is for
stored materials for the sanitary manholes that have been delivered to the site.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $69,426.67
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Partial Payment No. 3
ATTACHMENTS: I. Partial Payment No. 3
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1S
West Des Moines, IA • Coralville, IA • Dubuque, IA • Mason City, IA • Sioux City, IA
Cedar Rapids, IA • Rock Island, Il • Springfield, IL • Liberty, MO • Rochester, MN
VEENSTRA & KIMM, INC.
3000 Westown Parkway • West Des Moines, Iowa 50266-1320
515-225-8000 • 515-225-7848(FAX) • 800-241-8000 (WATS)
July 14, 2021
Rudy Koester
Director of Public Works
City of Waukee
805 University Avenue
Waukee, Iowa 50263
WAUKEE, IOWA
LITTLE WALNUT CREEK NORTH TRUNK SEWER – PHASE 1 AND WATER MAIN EXTENSIONS
PAY ESTIMATE NO. 3
Enclosed are three copies of executed Pay Estimate No. 3 for work on the Little Walnut Creek North
Trunk Sewer – Phase 1 and Water Main Extensions project, under the contract between the City of
Waukee and Priority Excavating, LLC dated January 18, 2021. The partial payment estimate is for the
period June 12, 2021 to July 2, 2021.
We are recommending that payment for quantities completed in the month of June be withheld to
protect from loss on account of the grounds found in the following subparagraphs of the General
Conditions of the project specifications:
28.1.2 Claims filed or reasonable evidence indicating probable filing of claims.
28.1.4 A reasonable doubt that contract can be completed for balance then unpaid.
28.1.6 Claims of Owner for liquidated damages.
We are however recommending that payment be made for stored materials for the sanitary
manholes that have been delivered to the site.
We have checked the estimate and recommend payment to Priority Excavating, LLC in the amount of
$69,426.67.
Please sign all copies of Pay Estimate No. 3 in the space provided and return one signed copy of the
partial payment estimate to our office. Please forward one signed copy of Pay Estimate No. 3 with
payment to Priority Excavating, LLC.
Rudy Koester
July 14, 2021
Page 2
If you have any questions, please contact us at 225-8000.
VEENSTRA & KIMM, INC.
Andy Willcuts
ARW:kld
275332
Enclosures
cc: Priority Excavating, LLC
Sara Kappos, City of Waukee – w/enclosure (email)
Beth Richardson, City of Waukee – w/enclosure (email)
Becky Schuett, City of Waukee – w/enclosure (email)
Tara Kammerer, City of Waukee – w/enclosure (email)
Date: PAY ESTIMATE NO. 3
Project Title Contractor
Original Contract
Amount & Date $1,427,080.00 January 18, 2021 Pay Period June 12, 2021 to July 2, 2021
BID ITEMS
Estimated Extended Quantity Value
Description Unit Quantity Unit Price Price Complete Completed
1.1 LS 1 65,000.00$ 65,000.00$ 50%32,500.00$
1.2 Erosion Control and SWPPP LS 1 16,875.00$ 16,875.00$ 40%6,750.00$
1.3 LS 1 17,750.00$ 17,750.00$ 100%17,750.00$
1.4 TONS 25 40.00$ 1,000.00$ -$
1.5 Seeding LS 1 13,750.00$ 13,750.00$ -$
1.6 TONS 33 100.00$ 3,300.00$ -$
1.7 LF 100 25.00$ 2,500.00$ -$
1.8 SY 1,350 3.50$ 4,725.00$ -$
1.9 EA 1 17,200.00$ 17,200.00$ -$
1.10 LS 2 1,750.00$ 3,500.00$ -$
1.11 LF 315 42.00$ 13,230.00$ 300 12,600.00$
1.12 LF 85 70.00$ 5,950.00$ -$
1.13 LF 1,900 90.00$ 171,000.00$ 1,867 168,030.00$
1.14 LF 1,200 35.00$ 42,000.00$ -$
1.15 EA 9 5,000.00$ 45,000.00$ 2 10,000.00$
1.16 EA 1 1,500.00$ 1,500.00$ -$
1.17 EA 1 4,500.00$ 4,500.00$ -$
1.18 EA 1 2,500.00$ 2,500.00$ 1 2,500.00$
1.19 EA 7 3,500.00$ 24,500.00$ -$
1.20 EA 1 3,000.00$ 3,000.00$ -$
1.21 LF 20 100.00$ 2,000.00$ -$
1.22 LF 240 900.00$ 216,000.00$ 150 135,000.00$
1.23 LF 3,000 197.00$ 591,000.00$ -$
1.24 EA 7 2,500.00$ 17,500.00$ -$
1.25 EA 5 3,500.00$ 17,500.00$ -$
1.26 EA 2 2,000.00$ 4,000.00$ -$
1.27 VF 180 160.00$ 28,800.00$ -$
1.28 VF 180 300.00$ 54,000.00$ -$
1.29 EA 1 37,500.00$ 37,500.00$ -$
Total 1,427,080.00$ 385,130.00$
8" Sanitary Sewer in Place
Water Service Connection
12" Gate Valve
Reconnect Existing Hydrant
Priority Excavating, LLC
9550 Hickman Road, Suite 101
Clive, Iowa 50325
2" Tapping Saddle and Valve
Flushing Hydrant
LITTLE WALNUT CREEK NORTH TRUNK SEWER
PHASE 1 AND WATER MAIN EXTENSIONS
WAUKEE, IOWA
Rip-Rap
Rolled Erosion Control Product, Type
2
Abandon Well
2" Water Main Directional Bored in
Place
Connection to Existing System
Mobilization
July 13, 2021
Clearing and Grubbing
Stabilizing Material
Field Drain Tiles
Connection to Existing Manhole
24" Sanitary Sewer in Place
48" SW-301 Standard Manholes
Internal Drop Connection
60" SW-301 Standard Manholes
60" Manhole Extra Depth
48" Manhole Extra Depth
24" Sanitary Sewer Augered in Place
in Steel Casing
6" Water Main Directional Bored in
Place or in Open Cut
12" Water Main Directional Bored in
Place
12" Water Main Directional Bored in
Place or in Open Cut
Hydrant Assembly
VEENSTRA & KIMM, INC.
3000 Westown Parkway West Des Moines, Iowa 50266-1320
515-225-8000 515-225-7848(FAX) 800-241-8000 (WATS)
V-K Job No. 275332
MATERIALS STORED SUMMARY
Description Unit QTY Unit Price Extended Cost
Water Main Materials (Core & Main INV#N655818)LS 0.38 74,102.12$ 28,222.32$
Water Main Materials (Core & Main INV#N971860)LS 0.38 61,204.00$ 23,309.98$
Water Main Materials (Core & Main INV#O012658)LS 0.38 9,674.61$ 3,684.64$
Water Main Materials (Core & Main INV#O095570)LS 0.38 3,691.50$ 1,405.93$
Sanitary Sewer Materials (Core & Main INV#N649883)LS 0.95 41,125.64$ 39,233.36$
Sanitary Sewer Materials (Core & Main INV#O060903)LS 0.95 14,380.35$ 13,718.68$
Sanitary Sewer Materials (Core & Main INV#O075868)LS 0.95 39,997.97$ 38,157.57$
Sanitary Sewer Materials (Core & Main INV#O084756)LS 0.95 12,364.94$ 11,796.00$
Midstate Precast Invoice No. 8447 LS 1.00 9,460.65$ 9,460.65$
Midstate Precast Invoice No. 8448 LS 1.00 6,449.05$ 6,449.05$
Midstate Precast Invoice No. 8449 LS 1.00 8,258.55$ 8,258.55$
Midstate Precast Invoice No. 8468 LS 1.00 8,241.40$ 8,241.40$
Midstate Precast Invoice No. 8471 LS 1.00 8,377.90$ 8,377.90$
Midstate Precast Invoice No. 8498 LS 1.00 7,994.35$ 7,994.35$
Midstate Precast Invoice No. 8499 LS 1.00 8,094.85$ 8,094.85$
Midstate Precast Invoice No. 8514 LS 1.00 7,402.10$ 7,402.10$
Midstate Precast Invoice No. 8515 LS 1.00 8,801.85$ 8,801.85$
-$ -$
-$ -$
-$ -$
-$ -$
-$ -$
-$ -$
-$ -$
-$ -$
-$ -$
-$ -$
-$ -$
-$ -$
-$ -$
232,609.19$ TOTAL MATERIALS STORED
V-K Job No. 275332
SUMMARY
Contract Price Value Completed
Original Contract Price $1,427,080.00 385,130.00$
Approved Change Orders (list each)-$
TOTAL ALL CHANGE ORDERS -$ -$
Revised Contract Price 1,427,080.00$ 385,130.00$
Materials Stored 232,609.19$
Value of Completed Work and Materials Stored 617,739.19$
Less Retained Percentage (5%)30,886.96$
Net Amount Due This Estimate 586,852.23$
Less Estimate(s) Previously Approved No.1 363,371.94$
No.2 154,053.62$
No.3
No.4
No.5
No.6
No. 7
No. 8
No. 9
No. 10
No. 11
No. 12
Less Total Pay Estimates Previously Approved 517,425.56$
Amount Due This Estimate 69,426.67$
The amount 69,426.67$ is recommended for approval for payment in accordance with the terms of
the contract.
Quantities Complete Submitted By:Recommended By:Approved By:
Signature:Signature:Signature:
Name:Name:Name:
Title:Title:Project Engineer Title:
Date:Date:Date:
Priority Excavating, LLC Veenstra & Kimm, Inc.
V-K Job No. 275332