HomeMy WebLinkAbout2020-05-18-I01K ICN Master Agreement_Amendment 2AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: May 18, 2020
AGENDA ITEM:Consideration of approval of a resolution approving Amendment No. 2
to Master Agreement for Shared Use Projects 15-109 (Iowa
Communications Network)
FORMAT:Resolution
SYNOPSIS INCLUDING PRO & CON: The amendment is to allow Iowa Communications
Network (ICN) access to a 72 count fiber cable segment owned by the City of Waukee along Grand
Prairie Parkway within Waukee.
ICN will allow Waukee access to a 96 count fiber cable segment jointly used by the Iowa
Department of Transportation/ICN along Interstate 80 from Ute Avenue/R-22 interchange to
Jordan Creek Parkway interchange, and along Grand Prairie Parkway from the south side of I-80
north to a Waukee hand hole for connecting the two networks; approximately 4.66 route miles.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Staff recommends approval of Amendment No. 2
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Amendment No. 2 Master Agreement for Shared Use Projects 15-109
PREPARED BY:Beth Richardson
REVIEWED BY:Rudy Koester RK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
I1K
THE CITY OF WAUKEE, IOWA
RESOLUTION 2020-
APPROVING AMENDMENT NO. 2 TO AGREEMENT 15-109, MASTER
AGREEMENT FOR SHARED USE PROJECTS [IOWA COMMUNICATIONS
NETWORK]
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE, IOWA
WHEREAS, the City of Waukee, Iowa is a duly organized municipality within Dallas
County; AND,
WHEREAS, on February 2, 2015, the Waukee City Council approved entering into a
28E agreement related to Ownership and Operation of a Consolidated Dispatch Center
for Police, Fire and Emergency Medical Services (hereinafter referred to as “Westcom”)
(Resolution #15-046); AND,
WHEREAS, on April 4, 2016, the Waukee City Council approved Agreement 15-109,
Master Agreement for Shared Use Projects (Iowa Communications Network) (hereinafter
referred to as the “Master Agreement”) (Resolution #16-115); AND,
WHEREAS, on October 3, 2016, the Waukee City Council approved Amendment No. 1
to the Master Agreement (Resolution #16-421); AND,
WHEREAS, Amendment No. 2 to the Master Agreement is proposed concerning the use
of fiber cable along Grand Prairie Parkway by Iowa Communications Network, and the
use of fiber cable along Interstate 80 by the City of Waukee.
NOW THEREFORE BE IT RESOLVED by the City of Waukee City Council in
session this 18th day of May, 2020, that the Amendment No. 2 to Agreement 15-109,
Master Agreement for Shared Use Projects (Iowa Communications Network) is hereby
approved.
____________________________
Courtney Clarke, Mayor
Attest:
___________________________________
Rebecca D. Schuett, City Clerk
RESULTS OF VOTE: AYE NAY ABSENT ABSTAIN
Anna Bergman
R. Charles Bottenberg
Chris Crone
Larry R. Lyon
Ben Sinclair
1
AMENDMENT 2
To MASTER AGREEMENT FOR SHARED USE PROJECTS 15-109
THIS AMENDMENT is between the State of Iowa, Iowa Telecommunications and Technology Commission operating the
Iowa Communications Network, (collectively the “ICN”) and City of Waukee (“Waukee”). In consideration of the mutual
promises herein made, ICN and Waukee agree as follows:
SECTION 1. PURPOSE OF AMENDMENT. The Parties intend to amend the Agreement to add Amendment 2,
Schedule A.1, Scope of Services, Appendix 1, Designated Route and Fiber Assignment Matrix with Responsibilities and
Appendix 2, As-Built Drawings for the exchange of fiber optic networks along Grand Prairie Parkway from University Ave
to Interstate 80 (Waukee segment), for Interstate 80 from Ute Ave to Jordan Creek Parkway, including the tie cable
crossing at Grand Prairie Parkway (ICN segment in conjunction with the Iowa DOT Traffic Operation Bureau) in Waukee,
and W. Des Moines, Iowa.
SECTION 2. AMENDMENT ALLOWED. Section 3.1 of the Agreement provides for this Amendment with mutual
written consent of the Parties.
SECTION 3. EXECUTION. In witness whereof in full consideration of the mutual covenants set forth above for other
good and valuable consideration the receipt, adequacy and legal sufficiency of which are hereby acknowledged, the
Parties have entered into the above Amendment and have caused their duly authorized representatives to execute this
Amendment. All previous terms and conditions shall remain in full force and effect with the exception of previously
mentioned modifications in this document.
CITY OF WAUKEE
By: Date:
Title:
IOWA COMMUNICATIONS NETWORK
By: Date:
Title:
2
Schedule A.1
Scope of Services
City of Waukee and ICN – Amendment 1
Project Description:
The City of Waukee and ICN have agreed to an exchange of facilities in order to allow Waukee and the ICN access to
segments of fiber optic cable along Grand Prairie Parkway and Interstate 80 within Waukee and W. Des Moines, Iowa.
Waukee will allow ICN access to a 72 fiber cable segment owned by Waukee along Grand Prairie Parkway from the
intersection of University Ave south to Interstate 80; approximately 2.14 route miles.
The ICN will allow Waukee access to a 96 fiber joint use Iowa DOT/ICN cable segment along Interstate 80 from Ute Ave
to Jordan Creek Parkway, and along Grand Prairie Parkway from the south side of I-80 north to a Waukee handhole for
connecting the two networks; approximately 4.66 route miles.
See Appendix 1 for “Designated Route and Fiber Assignment Matrix with Responsibilities” and Appendix 2 for Overview
Map.
WAUKEE RESPONSIBILITIES. Waukee will own and maintain their network as detailed below under Appendix 1.
ICN RESPONSIBILITIES. The ICN will own and maintain their network as detailed below under Appendix 1.
ICN PROPERTY. Except as provided in the Installation of Waukee Equipment section of this Scope of Services, Waukee
shall not, and shall not permit others, to rearrange, disconnect, remove, attempt to repair or otherwise tamper with any
ICN property without the written consent of the ICN. The Parties agree that no party other than the ICN or a contractor
under the direct supervision of the ICN shall be permitted to perform maintenance or splicing on the Fiber. Splicing and
Maintenance information is more fully explained in Exhibits A & B attached to the Amendment.
WAUKEE PROPERTY. Except as provided in the Installation of ICN Equipment section of this Scope of Services, ICN
shall not, and shall not permit others, to rearrange, disconnect, remove, attempt to repair or otherwise tamper with any
Waukee property without the written consent of the Waukee. The Parties agree that no party other than the Waukee or a
contractor under the direct supervision of the Waukee shall be permitted to perform maintenance or splicing on the Fiber.
Splicing and Maintenance information is more fully explained in Exhibits A & B attached to the Agreement.
FIBER MAINTENANCE
A. Except as stated below related to fiber repairs to Waukee owned fibers segments IRU’d to ICN pursuant to this
agreement, The Fiber Segment owner or its authorized contractor shall perform all maintenance on the Fiber, including
any Fiber repairs, Fiber restoration, and Fiber relocation that may become necessary during the term of this Agreement.
If a Fiber Segment owner incurs any costs associated with Fiber repairs, Fiber restoration, or Fiber relocation, the owner
shall be reimbursed based upon the other party’s proportional share of fibers. In the event that the fiber repairs are
necessitated by fiber damage caused by a third party, Fiber Segment owner will first attempt to recover the cost of repair
from the negligent third party. If Fiber Segment owner is unable to recover the full cost of damage repair from the third
party, the parties shall proportionally share of the costs for the repair. In the event of a fiber cut or other need for an
emergency repair, upon notification by the other party, the Fiber Segment owner shall commence to respond to correct
the interruption in service. In the event of a service interruption, the parties shall contact each other at the numbers listed
in Exhibit B of the Agreement. Upon repair and when appropriate, the party performing the repairs will invoice the other
party for their proportional share of the costs for the repair.
B. If Waukee or a contractor operating under the direction of Waukee performs any activity, such as, but not limited
to: splicing, accesses splice cases, or performs any other procedure that could accidentally disrupt the passage of light in
the Fibers or otherwise directly impact the ICN’s designated fibers, the activity must be preplanned five (5) working days
in advance and performed during established ICN Maintenance Windows (normally midnight - 6 AM.) Waukee shall call
the ICN Service Desk at 515-725-4400 or 1-800-572-3940 to establish all maintenance windows. Waukee may modify its
designated Dark Fiber by splicing, terminating, or otherwise extending its facilities. The five working day notice does not
apply to emergency repairs.
3
C. Cable damage or fiber cuts are designated as "interruptions of service" and must be acknowledged by Waukee
within 30 minutes of notification by the ICN Service Desk. Service restoration standards as follows must be met.
Timeframes beginning with notification or knowledge of outage are not to exceed:
A. Technicians on site of suspected fiber cut Two (2) hours
B. Identification of cut location and damaged fibers Four (4) hours
C. First fiber is restored Six (6) hours
D. All fibers spliced and all services restored Eight (8) hours
D. Within Waukee owned fiber segments, if Waukee or a Waukee authorized contractor is unable to restore service
to the ICN designated fiber within the time frames listed above, Waukee will grant the ICN reasonable access for ICN
and/or ICN authorized contractors to restore the interrupted service on the fibers ICN has an IRU. ICN shall incur the cost
to repair the fibers IRU’d to ICN to restore ICN services. Waukee will utilize its contractor to repair the balance of their
owned fibers and the infrastructure for the permanent repair.
If a service interruption occurs within a Waukee owned fiber segment, Waukee will first seek reimbursement
from the at fault third party. Reimbursement sought, by Waukee from the at fault third party shall include the
costs ICN incurred to repair its IRU’d fibers. Upon collection by Waukee, Waukee shall reimburse the ICN for
its repair costs.
E. Unless otherwise specifically provided in this agreement, the ICN and Waukee shall proportionally share costs as
they relate to, but not limited to, changes, upgrades, and emergency repairs, etc. that are or may be required in order to
maintain proper operation of the IRU’d fiber located within the City Limits of Waukee. Cost sharing shall be calculated
based on each Party’s proportionate share of fibers within each fiber segment.
If cable changes or modifications, except relocates or moves, to IRU’d fiber are at the request or requirement
of Waukee or ICN, the requesting/requiring Party shall be responsible for the associated costs.
If cable located within the City of Waukee is requested or required to be moved or relocated by Waukee, the
cost shall be shared proportionally between the ICN and Waukee.
If the fiber located with the City limits of Waukee must be moved or altered at the request or requirement of a
third party, and if the cost is unable to be recovered from the third party, the cost shall be shared
proportionally between the ICN and Waukee.
If Waukee or ICN allocates some of their fibers to other entities, it shall be the fiber owner’s responsibility to
collect the fair/proportional share of costs for relocates and/or repairs from those entities.
F. ICN shall save and hold Waukee harmless from any and all third party claims, demands, suits, and/or damages,
including but not limited to attorney’s fees, expenses and costs incurred by Waukee in defending the same, that may arise
by virtue of an “interruption of service” in ICN owned fiber segments, and/or Waukee owned fiber segments, regardless of
cause. ICN further agrees that it shall not seek, or otherwise be entitled to, compensation or otherwise claim damages of
any kind or nature from Waukee for any “interruption of service” that may occur in any Waukee owned fiber segments,
including but not limited to those IRU’d to the ICN pursuant to this agreement, regardless of cause.
COMPENSATION. No fees will be exchanged between the Parties for use of the conduit, installation of cable and initial
splicing of the cable.
TERM. The Term of this Amendment shall be coterminous with Master Agreement 15-109.
4
APPENDIX 1
Designated Route and Fiber Assignment Matrix with Responsibilities
DESCRIPTION OF ROUTE & FIBER ASSIGNMENTS:
Waukee Responsibilities/Ownership:
Waukee will own the conduit and cable for their segment along Grand Prairie Parkway from the intersection of
University Ave at the NW traffic control cabinet, south to Interstate 80 to and access handhole; approximately
2.14 route mile.
A. Non-Recurring Fiber Fee: N/A
B. Annual Maintenance Fee: N/A
C. Non-Recurring Installation Charges: N/A
D. Collocation Required: N/A
E. Locate Responsibility: Waukee
F. Maintenance Responsibility: Waukee
G. Emergency Maintenance Responsibility: Waukee
H. Relocation Responsibility: Waukee. Proportionate sharing based on allocation of fibers.
I. Term: Coterminous with the Master Agreement
Fiber Allocations Waukee Cable Ownership:
Sheath Identifier Tube/Stand Identifier IRU Assignment
72 Strand Single Mode Sheath Blue Waukee
Orange Waukee
Green Waukee
Brown Waukee
Slate ICN
White ICN
5
ICN Responsibilities/Ownership:
ICN, with a corresponding agreement with the Iowa DOT Traffic Operations Bureau, will provide access to the
City of Waukee to fiber optic strands on the Iowa DOT joint use network along Interstate 80 from Ute Ave, SW
corner, to Jordan Creek Parkway, SW corner, and along Grand Prairie Parkway from the south side of I-80 north
to a Waukee handhole for connecting the two networks.
ICN will coordinate with the Iowa DOT for the initial cable installation and splicing required to connect the two
networks at Grand Prairie Parkway.
A. Non-Recurring Fiber Fee: N/A
B. Annual Maintenance Fee: N/A
C. Non-Recurring Installation Charges: N/A
D. Collocation Required: N/A
E. Locate Responsibility: ICN
F. Maintenance Responsibility: ICN
G. Emergency Maintenance Responsibility: ICN
H. Relocation Responsibility: ICN. Proportionate sharing based on allocation of fibers.
I. Term: Coterminous with the Master Agreement
Fiber Allocations ICN Cable Allocation:
Sheath Identifier Tube/Stand Identifier IRU Assignment
96 Strand Single Mode Sheath Blue Iowa DOT
Iowa DOT Cable Segments Orange Iowa DOT
Identified as Links 4066, 4066-2A Green Iowa DOT
Brown Iowa DOT
Slate ICN
White ICN
Red City of Waukee
Black City of Waukee
6
APPENDIX 2
Route Overview Drawings
Overview Map Below of the route segments to be exchanged along Grand Prairie Parkway and Interstate 80. Detailed engineering
plans to be provided by each entity.