HomeMy WebLinkAbout2020-05-18-I01Q Wastewater Treatment Facility Demolition_Pmt Est 6AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: May 18, 2020
AGENDA ITEM:Consideration of approval of Partial Payment Estimate No. 6 to
Wenthold Excavating, LLC for the Wastewater Treatment Facility
Demolition Project in the amount by $17,208.30.
FORMAT:Action
SYNOPSIS INCLUDING PRO & CON: Wenthold Excavating, LLC requested Payment
Estimate No. 6 for the work completed on the Wastewater Treatment
Facility Demolition Project in the amount of $17,208.30. Veenstra &
Kimm, Inc. has reviewed the payment estimate and recommends
payment.
The partial payment is for pay period April 8, 2020 to May 5, 2020.
Work completed for this pay is for excavation and silt fence.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $17,208.30
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Partial Payment No. 6
ATTACHMENTS: I. Partial Payment No. 6