HomeMy WebLinkAbout2020-06-01-J01O Lift Station No 3 Rehab Phase 2_Pmt Est 4CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: June 1, 2020
AGENDA ITEM:Consideration of approval of Partial Payment Estimate No. 4 to Synergy
Contracting, LLC for the Lift Station No. 3 Rehabilitation Phase 2 –
Backup Pump Replacement Project in the amount of $19,401.37
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Synergy Contracting, LLC requested Payment
Estimate No. 4 for the work completed on the Lift station No. 3
Rehabilitation Phase 2 – Backup Pump Replacement Project in the
amount of $19,401.37. Veenstra & Kimm, Inc. has reviewed the
payment estimate and recommends payment.
The partial payment is for pay period April 30, 2020 to May 26, 2020.
This pay estimate is for work on mobilization, surface restoration,
granular surfacing, PCC replacement and fencing.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $19,401.37
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Partial Payment No. 4
ATTACHMENTS: I. Partial Payment No. 4
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
AGENDA ITEM: J1O