HomeMy WebLinkAbout2020-06-01-J02 Attivo Waukee Phase 2 - Site Plan
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: June 1, 2020
AGENDA ITEM: Consideration of approval of a resolution approving a site plan for Attivo
– Waukee Phase 2
FORMAT: Resolution
SYNOPSIS INCLUDING PRO & CON: Haverkamp Properties, LLC is requesting approval of
a site plan for the second phase of a multi-family, retirement, apartment
development, located south of NE Dellwood Drive and west of NE
Alice’s Road, containing approximately 16.57 acres. The project
includes an addition to the existing four-story apartment building. The
addition will add 43,000 square feet, bringing the total building area to
115,992 square feet (285 total units). The second phase will also include
the construction of underground parking.
The applicant has provided elevations for the proposed building addition
on the site, which meets the intent of the architectural guidelines within
the Site Plan Ordinance and matches the materials on the existing
building.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT: The Planning and Zoning
Commission reviewed the request at their meeting on May 26, 2020,
and recommended approval:
Approval of a Site Plan for Attivo – Waukee Phase 2 (835 NE Boston Parkway)
Senior Planner, Melissa DeBoer, introduced the request for approval of a site plan as presented by
the applicant, Haverkamp Properties LLC. The subject property is generally located south of NE
Dellwood Drive and west of NE Alice’s Road, containing approximately 16.57 acres.
Mrs. DeBoer advised that the site plan indicates an addition to the existing four story apartment
building. The addition will add 43,000 square feet to the building area and provide an additional
83 units. The second phase will also include the construction of underground parking and single
story attached garage units. The site is currently served with public utilities that will continue to
support the addition, and storm water is already managed through existing detention ponds on
site. Internal sidewalks will be extended throughout the second phase of the site. At this time all
parking, landscaping, open space, and lighting ordinance requirements have been met and all
proposed materials are consistent with the current structure.
At this time staff would recommend approval subject to any remaining staff comments.
AGENDA ITEM: J2
Commissioner Frank questioned where the parking was located, the underground and
single story locations were called out.
Commissioner Koshy questioned if there would be a garage door to the underground
parking. Representative for the applicant, Erin Ollendike, advised there is an overhead
door for the underground garage.
Commissioner Hoifeldt questioned what material would be used for the retaining wall.
The information was unavailable from parties present, but the information would be sent
after the meeting.
Commissioner Hoifeldt moved to approve the Site Plan for Attivo- Waukee Phase 2 (835
NE Boston Parkway) subject to any remaining staff comments. Commissioner Inman
seconded the motion. Ayes: Ward, Broderick, Conley, Streit, Koshy, Inman, and
Hoifeldt. Nays: None. Motion Carries.
STAFF REVIEW AND COMMENT: Staff recommends approval of the site plan subject to
remaining staff comments.
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Resolution
II. Staff Report
III. Site Plan & Elevations
PREPARED BY: Melissa DeBoer, Senior Planner
REVIEWED BY:
THE CITY OF WAUKEE, IOWA
RESOLUTION 2020-
APPROVING THE SITE PLAN FOR ATTIVO – WAUKEE PHASE 2 (835 NE BOSTON
PARKWAY)
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE, IOWA
WHEREAS, the City of Waukee, Dallas County, State of Iowa, is a duly organized Municipal
Organization; AND,
WHEREAS, the City of Waukee Planning and Zoning Commission recommended approval of
the Site Plan for Attivo – Waukee Phase 2, subject to remaining staff comments on May 26,
2020; AND,
WHEREAS, the Site Plan for Attivo – Waukee Phase 2 is in general conformance with §160 –
Site and Building Development Standards Ordinance of the Waukee Municipal Code; AND,
WHEREAS, the Site Plan for Attivo – Waukee Phase 2 is in general conformance with §161 –
Landscaping and Open Space Ordinance of the Waukee Municipal Code; AND,
NOW THEREFORE BE IT RESOLVED by the City Council of the City of Waukee, Iowa on
this 1st day of June, 2020 that the Site Plan for Attivo – Waukee Phase 2 is approved.
____________________________
Courtney Clarke, Mayor
Attest:
___________________________________
Rebecca D. Schuett, City Clerk
RESULTS OF VOTE: AYE NAY ABSENT ABSTAIN
Anna Bergman
R. Charles Bottenberg
Chris Crone
Larry R. Lyon
Ben Sinclair
PLANNING AND ZONING COMMISSION STAFF REPORT
PROJECT: At tivo Waukee Phase 2 – Site Plan PREPARED BY: Melissa DeBoer, AICP – Senior Planner
REPORT DATE: May 22, 2020
MEETING DATE: May 26, 2020
GENERAL INFORMATION
Owner: Waukee Active Living, LLC
Developer:
Haverkamp Properties LLC
Project Manager: Erin Ollendike, PE, Civil Design Advantage
Request: The applicant is requesting approval of a site plan for
the second phase of a multi-family, retirement,
apartment development.
Location and Size: Property is located south of NE Dellwood Drive and
west of NE Alice’s Road, containing approximately
16.57 acres.
AREA MAP
ABOVE: Aerial of subject project area (outlined in RED) in relation to the surrounding area.
May 22, 2020
2 of 3
LAND USES AND ZONING
Location Existing Land Use Comprehensive Plan Current Zoning
Property in
Question
Multi-family Apartment
Development High Density Residential R-3 (Multi-Family Residential
District)/PD-1 (Planned
Development Overlay)
North Single Family Residential Single Family Residential R-2 (One and Two Family
Residential)
South Single Family Residential /
Townhome Residential
Single Family Residential /
Medium Density
Residential
R-2 (One and Two Family
Residential) / R-4 (Row Dwelling
and Townhome Dwelling) / C-4
(Office Park Commercial)
East Multi-family Apartment
Development
High Density Residential R-3 (M ulti-Family Residential
District)
West Single Family Residential Single Family Residential R-2 (One and Two Family
Residential)
BACKGROUND
A site plan for this site was approved by the Planning and Zoning Commission in August 2017. At the time, the
project was proposed in two phases. The first phase was recently completed and now the applicant wishes to
make some changes to the second phase, located at the north side of the site. The proposed changes include
the addition of underground parking and some minor changes to the building layout. This proposed site plan
shows attached garages rather than detached garages as was previously shown.
PROJECT DESCRIPTION
The project includes an addition to the existing four-story apartment building. The new addition will add
43,000 square feet to the existing building area, bringing the total building area to 115,992 square feet. The
second phase consists of 83 units, bringing the total apartment units for this project to 285 units. The second
phase will also include the construction of underground parking (83 spaces) and single-story attached garages
(81 spaces).
ACCESS AND PARKING
No new accesses are proposed. Two accesses exist to this site. One off of NE Dellwood Drive and one off of
NE Boston Parkway.
The total amount of parking required for this site is 1.5 spaces per unit. The new phase will be adding a total
of 196 parking spaces to the overall parking count, bringing the overall site to 491 parking spaces provided.
The overall parking spaces required for this site is 428 spaces, they are exceeding the requirement.
SIDEWALKS/TRAILS
Phase 2 includes the addition of sidewalks internal to the site, including both the courtyard and the parking
areas, in order to provide walkability for the residents. Public sidewalks and trails already exist adjacent to the
site, along the public streets.
UTILITIES
This site will be serviced with all public utilities. Storm water will be managed through the existing detention
ponds located throughout the site.
May 22, 2020
3 of 3
LANDSCAPING & OPEN SPACE
A minimum of 20% of the project area is required to be open space. The total amount of open space
proposed is 39%.
Plantings are provided throughout the site in compliance with the Landscape & Open Space Ordinance. Most
plantings already exist with Phase 1. Phase 2 is adding additional plantings in the courtyard area and in the
open space near the entrance into the underground parking.
ELEVATIONS
The elevations of the addition will match the existing building. The materials proposed are brick in shades of
red and tan, hardboard siding in shades of tan and brown, architectural panels, and metal trim.
MISCELLANEOUS
The applicant has provided a lighting plan which meets the City of Waukee Site Plan Ordinance requirements.
The majority of the site lighting already exists and was installed with Phase 1. Phase 2 includes the addition of
4 parking lot light poles, several wall pack light fixtures on the building addition and a few bollard light fixtures
within the courtyard area.
STAFF RECOMMENDATION
The proposed site plan is in general conformance with the Zoning Ordinance, Subdivision Ordinance, Site Plan
Ordinance and Comprehensive Plan. Staff recommends approval subject to any remaining staff comments.
ATTIVO - WAUKEE PHASE 23405 SE CROSSROADS DR. SUITE G, GRIMES, IOWA 50111PH: (515) 369-4400 Fax: (515) 369-4410CIVIL DESIGN ADVANTAGEUTILITY WARNINGCONSTRUCTION SCHEDULESUBMITTAL DATESINDEX OF SHEETSVICINITY MAPGENERAL LEGENDATTIVO - WAUKEE PHASE 2SITE PLAN FOR:WAUKEE, IOWAPRELIMINARYNOT FOR CONSTRUCTIONllllllwww.iowaonecall.com1-800-292-8989ONE CALLIOWAONE CALLKnow what'sbefore you dig.below.CallALICE'S ROAD N. WARRIOR LANEHICKMAN ROAD (HWY 6)NE FOX RUN TRAILWAUKEE CORPORATELIMITSNE DARTMOOR DRIVE NE DOUGLAS PKWYNE BOSTON PKWYNE DELLWOOD DRIVEDEVELOPMENT SUMMARYARCHITECTSURVEYORZONINGOWNERENGINEERLEGAL DESCRIPTIONDATE OF SURVEYBENCHMARKSNOTESDEVELOPERBULK REGULATIONSPROPERTY ADDRESSMM MMMMMM MMMMMMMMMMMMMMMMPROJECT
CIVIL DESIGN ADVANTAGE1909.455ATTIVO - WAUKEE PHASE 2
ENGINEER: EKO EI: GH/JWM
REVISIONS DATE
WAUKEE, IOWA8 FIRST SUBMITTAL 03/24/2020
PHONE: (515) 369-4400 FAX: (515) 369-4410
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 04/14/2020
THIRD SUBMITTAL 05/12/20202DETAILS12" SUBGRADE PREPARATIONCURB RAMPSFOR CLASS B OR C SIDEWALKCLASS 'A' CURB AND SIDEWALKDETECTABLE WARNING DETAILHYDRANT ASSEMBLY DETAILTYPICAL SIGN POST6" PCC INTEGRAL CURBSTANDARD PCC CURB & GUTTERHDPE INTAKE BASINDUCTILEIRON-DONOTPOLLUTDRA
I
N
S
T
O
WAT E R W A Y SENYLOPLAST PERPENDICULAR CURB RAMP @ CLASS 'A' INTEGRAL CURB4' X 4' SW-513 INTAKE (ST-14)RETAINING WALL SPOT ELEVATIONREFERENCE DETAILORIFICE PLATE
UPCIVIL DESIGN ADVANTAGE1909.455ATTIVO - WAUKEE PHASE 2
ENGINEER: EKO EI: GH/JWM
REVISIONS DATE
WAUKEE, IOWA8 FIRST SUBMITTAL 03/24/2020
PHONE: (515) 369-4400 FAX: (515) 369-4410
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 04/14/2020
THIRD SUBMITTAL 05/12/20203DEMOLITION PLAN DEMOLITION NOTES
UPCIVIL DESIGN ADVANTAGE1909.455ATTIVO - WAUKEE PHASE 2
ENGINEER: EKO EI: GH/JWM
REVISIONS DATE
WAUKEE, IOWA8 FIRST SUBMITTAL 03/24/2020
PHONE: (515) 369-4400 FAX: (515) 369-4410
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 04/14/2020
THIRD SUBMITTAL 05/12/20204DIMENSION PLAN GENERAL NOTESTRAFFIC CONTROL NOTESPAVEMENT THICKNESSSIGN LEGENDVANACCESSIBLESIGN DETAIL(1" = 20' FULL-SIZE)LOCATION
UPGRADING NOTESCIVIL DESIGN ADVANTAGE1909.455ATTIVO - WAUKEE PHASE 2
ENGINEER: EKO EI: GH/JWM
REVISIONS DATE
WAUKEE, IOWA8 FIRST SUBMITTAL 03/24/2020
PHONE: (515) 369-4400 FAX: (515) 369-4410
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 04/14/2020
THIRD SUBMITTAL 05/12/20205GRADING PLAN DETAIL 'A' DETAIL 'B' DETAIL 'C' DETAIL 'D' DETAIL 'F' DETAIL 'E'
5 5/8
"17' - 0
3
/4"5 5/8"5 5/8"17' - 0 3/4"5 5/8"8x8 POST8x8 POST8x8
P
O
S
T 8x8 POST1S1019"1' - 0"9"
2' - 6"9"1' - 0"9"2' - 6"
8' - 6"8' - 6"
9"1' - 0"9"
2' - 6"
9"1' - 0"9"
2' - 6"9"1' - 0"9"2' - 6"
SLABSPANSLABSPAN TOP OF 8" SLABSITE EL. = [ 1021
' -
0"
]PROJECT EL
. =
[ 0
' -
0"
]SEE 1 / S201
FOR
REINF.5 5/8"11' - 0
3
/4"5 5/8"
5 5/8"11' - 0 3/4"5 5/8"6x6 POST6x
6
PO
S
T6x6 POST6x6 POST2S1019"1' - 0"9"
2' - 6"
9"1' - 0"9"
2' - 6"9"1' - 0"9"2' - 6"9"1' - 0"9"2' - 6"
SLABSPAN TOP OF 8" SLABSITE EL
. =
[ 1021'
- 0
" ]PROJECT EL
. =
[ 0
' -
0"
]SEE 1 / S201
FOR
REINF.UPRl lllll lllll lllll lllll lllll lllll lllll lllll lllll lllllllllllllllllllllllllllllllllllllll lllll llllDA #13.62 ACll
l l l l l
l
l
l
llllllllllllllll l l
l
ll
lllllEROSION AND SEDIMENT CONTROL PLANRllllSWPPP LEGENDATTIVO - WAUKEE PHASE 2VICINITY MAPWAUKEE, IOWAATTIVO - WAUKEE PHASE 2DISCHARGE POINT SUMMARYSTABILIZATION QUANTITIESEROSION AND SEDIMENT CONTROL PLAN6 NOTES:CIVIL DESIGN ADVANTAGE1909.455ATTIVO - WAUKEE PHASE 2
ENGINEER: EKO EI: GH/JWM
REVISIONS DATE
WAUKEE, IOWA8 FIRST SUBMITTAL 03/24/2020
PHONE: (515) 369-4400 FAX: (515) 369-4410
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 04/14/2020
THIRD SUBMITTAL 05/12/2020
ALICE'S ROAD N. WARRIOR LANEHICKMAN ROAD (HWY 6)NE FOX RUN TRAILWAUKEE CORPORATELIMITSNE DARTMOOR DRIVE NE DOUGLAS PKWYNE BOSTON PKWYNE DELLWOOD DRIVEMM MMMMMM MMMMMMMMMMMMMMMMPROJECT
UP6x6 POST6x6 POST 2S101SLABSPAN TOP OF 8" SLABSITE EL. = [ 1021' - 0" ]PROJECT EL. = [ 0' - 0" ]SEE 1 / S201 FOR REINF.
CIVIL DESIGN ADVANTAGE1909.455ATTIVO - WAUKEE PHASE 2
ENGINEER: EKO EI: GH/JWM
REVISIONS DATE
WAUKEE, IOWA8 FIRST SUBMITTAL 03/24/2020
PHONE: (515) 369-4400 FAX: (515) 369-4410
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 04/14/2020
THIRD SUBMITTAL 05/12/20207UTILITY PLAN UTILITY NOTESDOWNSPOUT CONNECTIONWITH WYE
UPXref G:\Current Projects\2017 RRE Projects\RRE17263 Senior Apartments Waukee\Pergolas\20181102 Waukee Senior Apartments Pergolas_Foundation Plan-Senior Living Pergola Large-rvt-1-TOP OF SLAB.dwg8x8 PO
ST
8x8 POST
8x8
POST
8x8 POST
1S101SLABSPANSLABSPANTOP OF 8" SLABSITE EL. = [ 1021' - 0" ]PROJECT EL. = [ 0' - 0" ]SEE 1 / S201 FOR REINF.Xref G:\Current Projects\2017 RRE Projects\RRE17263 Senior Apartments Waukee\Pergolas\20181102 Waukee Senior Apartments Pergolas_Foundation Plan-Senior Living Pergola Small-rvt-1-TOP OF SLAB.dwg6x6 POST
6x6
POST 6x6 POST6x6 POST2S101SLABSPANTOP OF 8" SLABSITE EL. = [ 1021' - 0" ]PROJECT EL. = [ 0' - 0" ]SEE 1 / S201 FOR REINF.Xref G:\Current Projects\2017 RRE Projects\RRE17263 Senior Apartments Waukee\Pergolas\20181102 Waukee Senior Apartments Pergolas_Foundation Plan-Senior Living Pergola Small-rvt-1-TOP OF SLAB.dwg6x6 POST6x6 POS
T
6x6
POST6x6 POST
2S101SLABSPANTOP OF 8" SLABSITE EL. = [ 1021' - 0" ]PROJECT EL. = [ 0' - 0" ]SEE 1 / S201 FOR REINF.NE BOSTON PARKWAY
NE DELLWOOD DRIVEPLANT SCHEDULE PHASE 2CIVIL DESIGN ADVANTAGE1909.455ATTIVO - WAUKEE PHASE 2
ENGINEER: EKO EI: GH/JWM
REVISIONS DATE
WAUKEE, IOWA8 FIRST SUBMITTAL 03/24/2020
PHONE: (515) 369-4400 FAX: (515) 369-4410
3405 S.E. CROSSROADS DRIVE, SUITE G
GRIMES, IOWA 50111
SECOND SUBMITTAL 04/14/2020
THIRD SUBMITTAL 05/12/20208LANDSCAPE PLAN LANDSCAPE NOTESLANDSCAPE REQUIREMENTSEXISTING 40' BUFFER (WEST)EXISTING 30' BUFFER (SOUTH)EXISTING 30' BUFFER (NORTH)PHASE 1 - PLANT SCHEDULEOVERSTORY TREESEVERGREEN TREESORNAMENTAL TREESSHRUBSPERENNIALSPHASE 1LANDSCAPING
PHASE 1LANDSCAPING PHASE 1LANDSCAPINGPHASE 1LANDSCAPING
PHASE 1LANDSCAPING
PHASE 1LANDSCAPINGPHASE 1LANDSCAPINGPHASE 1LANDSCAPING
EXISTING BUILDINGEXISTING BUILDINGD E S I G N
PRACTICPRELIMINARY NOT FOR CONSTRUCTIONElevations19-001Attivo Trail Phase II2020-03-24
1/16" = 1'-0"1 North Elevation
1/16" = 1'-0"3 West Elevation
1/16" = 1'-0"4 East Elevation