HomeMy WebLinkAbout2020-10-19-I01L Glynn Village South Park and Trail Amenity_Change Order 1AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: October 19, 2020
AGENDA ITEM:Consideration of approval of Change Order No. 1 to All Star Concrete, for the
Glynn Village Park and Trail Amenity Project increasing the contract in the
amount of $2,756.25.
FORMAT:Consent
SYNOPSIS INCLUDING PRO & CON: Change Order No. 1 to All Star Concrete, in the amount of
$2,756.25 is for contractor time searching for an existing drain pipe that was
on the plans but was not built per City records when the development was
constructed. The cost also includes the construction of a revised drainage
solution to drain the play area at the Trail Amenity. Representatives from
Genus Landscape Architects and City Staff have reviewed the quantities and
find them to be accurate.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Change Order No. 1
PREPARED BY:Matt Jermier