HomeMy WebLinkAbout2020-10-19-I07 NW 10th St, W Hickman to NW Douglas_PSA Amend 1CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: October 19, 2020
AGENDA ITEM:Consideration of approval of a resolution approving Engineering Services
Amendment No. 1 between Foth Infrastructure and Environment, LLC and the
City of Waukee [North 10th Street Improvement Project, Hickman Road to
NW Douglas Boulevard]
FORMAT:Resolution
SYNOPSIS INCLUDING PRO & CON: The original agreement was approved by City Council on
February 4, 2019. The City and the Consultant agree to amend the original agreement to include
additional services associated with:
Additional Project Coordination to finalize adjacent Easements
Additional Project Coordination for Utility Relocations
Additional Design Survey Services to incorporate adjacent Development Agreements
Additional Design Services to incorporate adjacent Development Agreements
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The total Hourly Not-to-Exceed
fees for the professional engineering services described in the agreement are as follows:
I.Basic Services of the Consultant
a.Task A –Stratford Crossing Easements $ 16,300.00
b.Task B –Utility Relocations (MidAmerican Energy) $ 19,400.00
c.Task C – Moore Parcel Development Agreement $ 15,500.00
d.Task D –Utility Relocations (Century Link, UPN & Mi-fiber) $ 8,000.00
e.Task E –Utility Relocations (City Gas) $ 8,000.00
f.Task F – Credit costs incurred for water main lowering ($ 9,902.39)
TOTAL $ 57,297.61
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Resolution and Agreement.
ATTACHMENTS: I. Resolution
II. Engineering Services Amendment No. 1
PREPARED BY: Beth Richardson
REVIEWED BY: Rudy Koester RK
AGENDA ITEM: I7
THE CITY OF WAUKEE, IOWA
RESOLUTION 2020-
APPROVING ENGINEERING SERVICES AGREEMENT AMENDMENT NO. 1 BETWEEN
FOTH INFRASTRUCTURE AND ENVIRONMENT, LLC, AND THE CITY OF WAUKEE
[NORTH 10TH STREET IMPROVEMENT PROJECT, HICKMAN ROAD TO
NW DOUGLAS BOULEVARD]
IN THE NAME AND BY THE AUTHORITY OF THE CITY OF WAUKEE, IOWA
WHEREAS, the City of Waukee, Dallas County, State of Iowa, is a duly organized Municipal
Organization; AND,
WHEREAS, on February 4, 2019, the Waukee City Council approved an Agreement for Professional
Consulting Services with Foth Infrastructure and Environment, LLC, related to the design and
construction administration of improvements to North 10th Street from Hickman Road north to NW
Douglas Boulevard (Resolution #19-051); AND,
WHEREAS, Engineering Services Agreement Amendment No. 1 is proposed to address additional
project coordination and design services;
NOW THEREFORE BE IT RESOLVED by the City Council of the City of Waukee that the
Engineering Services Agreement Amendment No. 1 between Foth Infrastructure and Environment,
LLC, and the City of Waukee [North 10th Street Improvement Project, Hickman Road to NW Douglas
Boulevard] is hereby approved.
Passed by the City Council of the City of Waukee, Iowa, and approved the 19th day of October, 2020.
____________________________
Courtney Clarke, Mayor
Attest:
___________________________________
Rebecca D. Schuett, City Clerk
RESULTS OF VOTE: AYE NAY ABSENT ABSTAIN
Anna Bergman
R. Charles Bottenberg
Chris Crone
Larry R. Lyon
Ben Sinclair
Foth Infrastructure and Environment, LLC N. 10th Street Improvements
Project Number 19W003.00 Hickman Rd to NW Douglas Blvd
Waukee, Iowa
Page 1
ENGINEERING SERVICES AMENDMENT NO. 1
PROJECT NO. 19W003.00
THIS AMENDMENT, made and entered into this day of 2020 by and between,
the CITY OF WAUKEE, IOWA, hereinafter referred to as the “City”, and FOTH INFRASTRUCTURE AND
ENVIRONMENT, LLC., hereinafter referred to as the "Consultant", for professional services in connection with the
preliminary survey and mapping, functional design, project coordination, preliminary design, final plans and specifications,
for the proposed construction of N 10th Street Improvements, from Hickman Road to NW Douglas Boulevard, hereby
amends the original Agreement dated February 4th, 2019 as follows:
The City and Consultant agree to amend the original Agreement to include additional services associated with:
Additional Project Coordination to finalize adjacent Easements
Additional Project Coordination for Utility Relocations
Additional Design Survey Services to incorporate adjacent Development Agreements
Additional Design Services to incorporate adjacent Development Agreements
I. Basic Services of the Consultant
TASK A – Additional Services for Stratford Crossing Easements
The Consultant completed the following additional service as part of the project.
Task A.1 Exhibit Preparation
Exhibits for the project meetings consisted of aerial mosaics for the project with the major project features
indicated on the aerial photograph. Include coloring, lettering, and other techniques to delineate the
proposed design concepts and right of-way needs, including typical sections of the roadway. The figure
indicated right-of-way needs, property lines, property ownership, access control lines, grading limits, and new
project improvements.
Task A.2 Project Coordination with Adjacent Landowner’s Engineering Consultant
The Consultant conducted additional meetings to address specific conflicts and concerns. Meetings coordinated
the proposed City project with proposed site improvements required to ensure underground utilities do not
conflict with roadway improvements or future commercial site develop.
Task A.3 Additional Platting Services
Provided acquisition plats and legal descriptions for property to be acquired for the Project and perform land
corner and lot surveys as needed for the preparation of the acquisition plats and legal descriptions for each
parcel. Said plats and legal descriptions shall comply with requirements of the Iowa Code and shall be prepared
by or under the direct supervision of a licensed land surveyor under the laws of the State of Iowa. The following
numbers of additional plats were delivered.
Permanent (Fee Title) Right-of-Way Acquisition Plat 3
Permanent Easements
Public Utility Easement 1
Public Facility and Use Easement 2
Legal Descriptions
Sign Easements 3
Task A Subtotal - $16,300.00
Foth Infrastructure and Environment, LLC N. 10th Street Improvements
Project Number 19W003.00 Hickman Rd to NW Douglas Blvd
Waukee, Iowa
Page 2
TASK B –Additional Services for Utility (MidAmerican Energy) Relocations
The Consultant completed the following additional service as part of the project.
Task B.1 Project Coordination with MidAmerican
The Consultant conducted additional meetings to address specific conflicts and concerns. Meetings coordinated
the proposed City project with proposed relocations required to ensure MidAmerican facilities should not be
impacted with future projects.
Task B.2 Additional Platting Services
Provided acquisition plats and legal descriptions for property to be acquired for the Project and perform land
corner and lot surveys as needed for the preparation of the acquisition plats and legal descriptions for each
parcel. Said plats and legal descriptions shall comply with requirements of the Iowa Code and shall be prepared
by or under the direct supervision of a licensed land surveyor under the laws of the State of Iowa. The following
numbers of additional plats were delivered.
Permanent Easements
Public Facilities and Use Easement 3
Task B.3 Additional Design Services
The Consultant designed a proposed profile the length of the project to avoid existing utilities installed by the
High School Site as well as proposed utilities installed with the NW 10th Street Project. This task also
includes creation of plan and profile sheets detailing running line and depths to be staked in the field.
Task B.4 Additional Construction Survey
The Consultant performed construction stating to establish correct running line and depth to ensure
MidAmerican Energy’s contractor installed the utility in the correct location.
Task B Subtotal - $19,400.00
TASK C – Additional Services for Moore Parcel Development Agreement
The Consultant completed the following additional service as part of the project.
Task C.1 Exhibit Preparation
Exhibits for the project meetings consisted of aerial mosaics for the project with the major project features
indicated on the aerial photograph. Include coloring, lettering, and other techniques to delineate the
proposed design concepts and right of-way needs, including typical sections of the roadway. The figure
indicated right-of-way needs, property lines, property ownership, access control lines, grading limits, and new
project improvements.
Task C.2 Additional Topographic Survey
The Consultant performed the following additional topographic surveys to determine, the potential revised
location of the house and the amount of additional earthwork needed for driveway and sidewalk tie in
elevations. This information was used to develop the existing ground DTM for the Project site.
Task C.3 Additional Design Services
The Consultant designed a preliminary site plan meeting City of Waukee standards for potential house
relocation.
Task C Subtotal - $15,500.00
TASK D –Additional Services for Utility (Century Link, UPN and mi-Fiber) Relocations
The Consultant completed the following additional service as part of the project.
Task D.1 Project Coordination with Utility Companies
The Consultant conducted additional meetings to address specific conflicts and concerns. Meetings coordinated
the proposed City project with proposed relocations required to ensure CenturyLink and mi-Fiber facilities should
not be impacted with future developments adjacent to NW 10th Street.
Foth Infrastructure and Environment, LLC N. 10th Street Improvements
Project Number 19W003.00 Hickman Rd to NW Douglas Blvd
Waukee, Iowa
Page 3
Task D.2 Additional Construction Survey
The Consultant performed construction stating to establish correct running line and depth to ensure utility’s
contractor installed the conduits in the correct location for connections from existing facilities into the new
Joint Utility Trench.
Task D Subtotal - $8,000.00
TASK E –Additional Services for Utility (City Gas) Relocations
The Consultant completed the following additional service as part of the project.
Task E.1 Project Coordination with Utility Companies
The Consultant conducted additional onsite meetings to address specific conflicts and concerns. Meetings
coordinated the proposed roadway project with proposed relocations required to ensure City’s Gas Main facilities
should not be impacted with future developments adjacent to NW 10th Street.
Task E.2 Additional Construction Survey
The Consultant performed construction stating along NW 10th Street and NW Sunrise Drive to establish
correct running line and depth to ensure City’s gas contractor installed the main in the correct location to
avoid upcoming sewer and water installations.
Task E Subtotal - $8,000.00
TASK F – Credit equal to the costs incurred for water main lowering underneath NW Sunrise Drive
The Consultant provided a finished grade profile based on typical section to which the water main was installed. This
profile did not accurately account for the construction of NW Sunrise Drive and resulted in the main not having the
necessary cover.
Task F Subtotal - ($9,902.39)
Foth Infrastructure and Environment, LLC N. 10th Street Improvements
Project Number 19W003.00 Hickman Rd to NW Douglas Blvd
Waukee, Iowa
Page 4
In consideration for these services, the City agrees to adjust the compensation for services performed by the Consultant.
These fees are based on the standard hourly rates of the Consultant’s personnel actually engaged in the performance of
the services, plus direct out-of-pocket costs for expenses incurred by personnel who are actually engaged in the work and
other direct costs. The total Hourly Not-to-Exceed fees for the professional engineering services as described in this
amendment are as follows:
I. Basic Services of the Consultant
Task A $ 16,300.00
Task B $ 19,400.00
Task C $ 15,500.00
Task D $ 8,000.00
Task E $ 8,000,00
Task E $ -9,902.39
Total $ 57,297.61
THIS AMENDMENT is subject to all provisions of the original Agreement.
THIS AMENDMENT, together with the original Agreement represents the entire and integrated AGREEMENT
between the City and Consultant.
THIS AMENDMENT executed the day and year written above.
CONSULTANT CITY OF WAUKEE
BY: BY:
Name: Patrick P. Kueter , P.E. Name: Courtney Clarke
Title: Senior Client Director Title: Mayor
WITNESS ATTEST
Name: Joshua C. DeBower, P.E. Name: Rebecca D. Schuett
Title: Lead Civil Engineer Title: City Clerk
Agr-2020-0821-Waukee-NW 10th Street-Amend No-1.doc