CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: December 7, 2020
AGENDA ITEM:Public Hearing on proposed plans, specifications, form of contract and
estimate of cost [NW Douglas Parkway Project, NW 10th Street to NW
2nd Street]
FORMAT:Public Hearing
SYNOPSIS INCLUDING PRO & CON: The NW Douglas Parkway Project, NW 10th Street
to NW 2nd Street, includes all materials, labor and equipment necessary for construction of
approximately: 21,500 CY of Grading, 13,500 SY of Modified Subbase, 11,000 SY of 10" PCC
Pavement, 3,000 SY of PCC Trail/Sidewalk, 1,090 LF of Water Main, 2,500 LF of Storm Sewer,
19 EA Intakes or Manholes, 3,100 LF of Joint Utility Trench, surface restoration and miscellaneous
related work and appurtenances.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Hold Public Hearing.
ATTACHMENTS: I. Notice of Public Hearing
PREPARED BY:Beth Richardson
REVIEWED BY:Rudy Koester RK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
H3
NOTICE OF PUBLIC HEARING
NPH - 1
NW DOUGLAS PARKWAY CONSTRUCTION
NW 10TH STREET TO NW 2ND STREET
WAUKEE, IOWA
FOTH PROJECT NO. 19W029.01
The City Council of Waukee, Iowa, will hold a public hearing on the proposed Plans, Specifications,
Form of Contract, and Estimate of Costs for the construction of the above referenced public
improvements at 5:30 p.m. on Monday, December 7, 2020. At said hearing, any interested person may
appear and file objections thereto or to the cost of the improvements.
Due to public health concerns and guidance, in accordance with Iowa Code Sections 21.4(1)(b) and
21.8, this meeting of the Waukee City Council will be conducted electronically as holding the meeting
in person is impossible or impractical. However, the public is encouraged to access the meeting
electronically in the manner specified below.
The meeting shall be conducted via Zoom at the following link or phone numbers:
https://zoom.us/j/352651371
Meeting ID: 352-651-371
Or by phone:
+1 646-558-8656 or
+1 312-626-6799 or
+1 301-715-8592
All persons wishing to observe or participate in this meeting may do so via Zoom or telephone. Please
contact the City Clerk’s office at 978-7904 or bschuett@waukee.org if you have questions or
electronic accessibility issues.
This project includes the furnishing of all labor, equipment, and materials for the construction of the
NW Douglas Parkway Construction from NW 10th Street to NW 2nd Street in Waukee, generally
described as follows:
Construct the NW Douglas Parkway Construction including all materials, labor and equipment
necessary for installation of approximately: 11,000 CY of Grading, 8,500 SY of Modified
Subbase, 7,000 SY of 10" PCC Pavement, 3,000 SY of PCC Trail/Sidewalk, 140 LF of
Water Main, 1,400 LF of Storm Sewer, 11 EA Intakes or Manholes, 3,100 LF of Joint
Utility Trench, surface restoration and miscellaneous related work and appurtenances.
The project also includes 10,500 CY of Grading, 5,000 SY of Modified Subbase, 4,000 SY
of 10" PCC Pavement, 950 LF of Water Main, 1,100 LF of Storm Sewer, 8 EA Intakes or
Manholes, surface restoration and miscellaneous related work and appurtenances which
will be bid as an alternate to the project.
Courtney Clarke, Mayor
ATTEST:
Rebecca D. Schuett, City Clerk
Publish: November 19, 2020