HomeMy WebLinkAbout2020-12-07-H04 NW 2nd St, NW Venture Dr to NW Douglas Pkwy_PHAGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: December 7, 2020
AGENDA ITEM:Public Hearing on proposed plans, specifications, form of contract and
estimate of cost [NW 2nd Street Project, NW Venture Drive to NW
Douglas Parkway]
FORMAT:Public Hearing
SYNOPSIS INCLUDING PRO & CON: The project to construct the NW 2nd Street includes
all materials, labor and equipment necessary for installation of approximately: 80,000 CY of
Grading, 30,000 SY of Modified Subbase, 7,500 SY of 9" PCC Pavement, 21,000 SY of 8" PCC
Pavement, 7,500 SY of PCC Trail/Sidewalk, 6,000 LF of Water Main, 5,400 LF of Storm Sewer,
74 EA Intakes or Manholes, one Reinforced Box Culvert, traffic signalization, surface restoration
and miscellaneous related work and appurtenances.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Hold Public Hearing.
ATTACHMENTS: I. Notice of Public Hearing
PREPARED BY:Beth Richardson
REVIEWED BY:Rudy Koester RK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
H4
NOTICE OF PUBLIC HEARING
NPH - 1
NW 2ND STREET CONSTRUCTION
NW VENTURE DRIVE TO NW DOUGLAS PARKWAY
WAUKEE, IOWA
FOTH PROJECT NO. 19W020.01
The City Council of Waukee, Iowa, will hold a public hearing on the proposed Plans,
Specifications, Form of Contract, and Estimate of Costs for the construction of the above
referenced public improvements at 5:30 p.m. on Monday, December 7, 2020 . At said hearing,
any interested person may appear and file objections thereto or to the cost of the improvements.
Due to public health concerns and guidance, in accordance with Iowa Code Sections 21.4(1)(b)
and 21.8, this meeting of the Waukee City Council will be conducted electronically as holding
the meeting in person is impossible or impractical. However, the public is encouraged to access
the meeting electronically in the manner specified below.
The meeting shall be conducted via Zoom at the following link or phone numbers:
https://zoom.us/j/352651371
Meeting ID: 352-651-371
Or by phone:
+1 646-558-8656 or
+1 312-626-6799 or
+1 301-715-8592
All persons wishing to observe or participate in this meeting may do so via Zoom or telephone.
Please contact the City Clerk’s office at 978-7904 or bschuett@waukee.org if you have questions
or electronic accessibility issues.
This project includes the furnishing of all labor, equipment, and materials for the construction of
the NW 2nd Street Construction from NW Venture Drive to NW Douglas Parkway in Waukee,
generally described as follows:
Construct the NW 2nd Street Construction including all materials, labor and equipment
necessary for installation of approximately: 80,000 CY of Grading, 30,000 SY of
Modified Subbase, 7,500 SY of 9" PCC Pavement, 21,000 SY of 8" PCC Pavement,
7,500 SY of PCC Trail/Sidewalk, 6,000 LF of Water Main, 5,400 LF of Storm Sewer,
74 EA Intakes or Manholes, one Reinforced Box Culvert, traffic signalization,
surface restoration and miscellaneous related work and appurtenances.
Courtney Clark, Mayor
ATTEST:
Rebecca D. Schuett, City Clerk
Publish: November 19, 2020