CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: December 21, 2020
AGENDA ITEM:Consideration of approval of Change Order No. 1 to TD&I Cable
Maintenance for the Warrior Lane Joint Utility Trench project increasing
the contract price in the amount of $24,000.00
FORMAT:Motion
SYNOPSIS INCLUDING PRO & CON: Change Order No. 1 is for reduction in the quantity
of Type I handholes, increase in the quantity of Type IV handholes and
reduction in the quantity of handholes provided by Utility Providers.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price in the amount of $24,000.00.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Motion to Approve.
ATTACHMENTS: I. Change Order No. 1
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Sara Kappos SKK
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1S
Project# 4185870
December 16th, 2020
TO: Rudy Koester
City of Waukee
805 University Ave
Waukee IA, 50263
RE: Change Order #1
Warrior Lane Joint Utility Trench
SH Project Number 4185870
Mr. Koester,
Please find attached Change Order #1 for the Warrior Lane Joint Utility Trench. The change order
includes the following items:
• Reduction in the quantity of Type I Handholes
• Increase in the quantity of Type IV Handholes
• Reduction in the quantity of handholes provided by Utility Providers
This change order eliminates the Type I Handholes on the project and changes all the handholes to
Type IV. Type I handholes are small round handholes and Type IV handholes are larger rectangular
handholes. After bidding the unit prices for the Type I and Type IV were the same and through
discussions with City Staff, the contractor, and the engineer it was decided to recommend changing the
handholes to the larger type IV. Additionally, the unit price of $2,600 for type IV handholes is a
favorable price in regard to historical perspectives and thus additional type IV handholes are included in
this change order to add value to the Joint Utility Trench.
We have reviewed the change order items and unit prices, both are line with anticipated amounts. If
City staff concurs with this change, we recommend the City of Waukee approve this change order in the
amount of $24,000 to the construction contract for the Warrior Lane Joint Utility Trench with TD&I Cable
Maintenance of Lakeland, MN.
Sincerely,
Shive-Hattery, Inc.
Nathan Hardisty, PE
Project Manager
Enc. Change Order #1
City of Waukee
230 W Hickman Road
Waukee, IA 50263 Distribution:
Owner __X__
Engineer __X__
Contractor __X__
Contractor:
1378 Quinlan Circle South
Lakeland, MN 55043 $389,134.25 September 17, 2020
CO-1.1 EA $2,600.00 (20)($52,000.00)
CO-1.2 EA $2,600.00 30 $78,000.00
CO-1.3 EA $2,000.00 (1)($2,000.00)
$24,000.00
$389,134.25
$0.00
$389,134.25
$24,000.00
$413,134.25
6.17%
0 Days
March 1, 2021
Date:
Approved By:
City of Waukee
Signature:
Name:
Title:
Date:
Recommended By:
Shive-Hattery
Signature:
Name: Nathan T. Hardisty, PE
Title: Project Manager
Name:
Title:
Date:
Warrior Lane Joint Utility Trench
4185870
Net Change by previously authorized Change Orders
The Contract Sum prior to This Change Order was
The Contract Sum will be increased by this Change Order in the amount of
The new Contract Sum including this Change Order will be
Description
THE CONTRACT IS CHANGED AS FOLLOWS:
CO-1.1 - Deduction of qty 20 Type I Handholes, Furnish and Install. These will be replaced with Type IV Handholes.
CO-1.2 - Addition of qty 30 Type IV Handholes, Furnish and Install. These replace the 20 Type I Handholes and add an additional 10 Type IV handholes to provide
a consitancy between the 4 Handholes Banks (10 Handholes at each bank)
CO-1.3 - Deduction of qty 1 Handhole and Junction Box, Furnish and Install Only. It was discussed with the utilities, and no utilities requested to have the
contractor install an utility provided handhole.
Item Value AdjustmentQuantity AdjustmentUnit Price
Signature:
TD & I Cable Maintenance, Inc
CHANGE ORDER
Aggregate Change Order as a percent of Original Contract
The date of Final Completion as of the date of this Change Order therefore is
NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER
Deduct Type I Handholes, Furnish and Install
Add Type IV Handholes, Furnish and Install
Deduct Handhole and Junction Box, Install Only
Project Title
S-H Project File Number
Orig. Contract Amount & Date
Change Order Number
Date
Unit
December 16th, 2020
1
The Contract Time will be changed by
CHANGE ORDER SUMMARY
Contractor:
TD & I Cable Maintenance, Inc
TOTAL
The Original Contract Sum was
1 of 1P:\Projects\DM\4185870\Construction\JUT\CASupport\CO\CO #1\Warrior Lane Joint Utility Trench Change Order #1