AGENDA ITEM:Consideration of approval of Change Order No. 2 to Caliber Concrete, LLC,
for the Fox Creek Park Phase 2 Project decreasing the contract in the amount
of -$21,621.00.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 to Caliber Concrete in the amount of
-$21,621.00 reflects deducts identified during the Value Management process.
The larger values in Change Order No. 2 include revising the grading plan to
eliminate any export or import of soils. The shade structures were slightly
revised providing additional savings. The amount listed above is the net
dollar value of the adds and deducts. We are anticipating at least one more
significant change order before the end of the project. The current total of
Change Order #1 and #2 is -$68,379 decrease to the original contract.
Representative from Genus and City Staff have reviewed the quantities and
find them to be accurate.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Change Order No. 2
PREPARED BY: Matt Jermier
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1J
gēnus [ landscape architects ]
3 2 5 E A S T 5TH S T R E E T
DES MOINES, IA 50309
T 515 284 1010
WWW.GENUS-LA.COM
January 16, 2019
Mr. Matt Jermier
Parks and Recreation Director, Waukee
805 University Avenue
Waukee, IA 50263
Re: Construction Change Order No. 2
Fox Creek Park Phase Two
City of Waukee, IA
Genus Project No. 17096
Dear Mr. Jermier:
Please find enclosed Change Order No. 2 in the amount of -$21,621.00.
This Change Order reflects deducts identified during the Value
Management process, as well as adds and deducts that have arisen
during the construction process to date. The amount listed above is
the net dollar value of the adds and deducts that comprise Change
Order No. 2. The quantities and changes completed to date have
been reviewed and agreed upon by the contractor and we hereby
recommend that the City of Waukee approve Change Order No. 2.
If you have any questions or comments regarding the enclosed, please
contact me at 515-284-1010.
Sincerely,
Dylan Jones, ASLA, PLA
Associate
CC: Jason Martin, Caliber Concrete LLC
Brett Douglas, Genus
309 Audubon St
City of Waukee Adair Ia 50002
Parks and Rec Dept.
805 University Ave
Waukee Ia. 50263
Fox Creek Park Phase 2
Change order #2
Original Contract amount 3225040
Revised contract amount with change order #1 3178282
Revised contract amount with CO#2 3156661
1 Water line revision reduce 2" to 1" copper 160'-2400
2 Reduce reduced pressure Zone Assembly to 1"-300
3 Enclosure for 1" rpz 861
4 Jointing revisions -1466
5 Revise earthwork making site balance -28635
6 Revise shade structure -11050
7 Revise sump pit enclsure -1762
8 Water line relocated at Drive 5152
9 Sanitary Connection revision 3776
10 Add valves at shower 512
11 Boulder quantity change 8600
12 Vapor Barrier 640
13 Installing 3/4" water line in to building 4451
TOTAL -21621
Net contract amount 3156661
City of Waukee Caliber Concrete