HomeMy WebLinkAbout2019-01-21-J01K Fox Creek Park Phase 2_Pmt Est 4AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: January 21, 2019
AGENDA ITEM:Consideration of approval of Payment Estimate No. 4 to Caliber Concrete
LLC., for the Fox Creek Park Phase II Project in the amount of $266,855.00.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Payment Estimate No. 4 to Caliber Concrete LLC. is for
building materials for the shelter, plumbing, and the installation of utilities.
Pay Estimate No. 4 also reflects Change Order #1 that was approved by the
City Council on November 5th. The quantities completed to date have been
reviewed and agreed upon by the contractor, City of Waukee Staff, and Genus
Landscape Architects.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Letter of Recommendation
II. Payment Estimate No. 4
PREPARED BY: Matt Jermier
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1K
gēnus [ landscape architects ]
3 2 5 E A S T 5TH S T R E E T
DES MOINES, IA 50309
T 515 284 1010
WWW.GENUS-LA.COM
January 11, 2019
Mr. Matt Jermier
Parks and Recreation Director, Waukee
805 University Avenue
Waukee, IA 50263
Re: Construction Pay Voucher No. 4
Fox Creek Park Phase Two
City of Waukee, IA
Genus Project No. 17096
Dear Mr. Jermier:
Please find enclosed Construction Pay Voucher No. 4 in the amount of
$266,855.00 for the above-referenced project. The work completed to
date has been reviewed and agreed upon by the contractor and we
hereby recommend that the City of Waukee approve Construction
Pay Voucher No. 4 for Caliber Concrete LLC.
If you have any questions or comments regarding the enclosed, please
contact Brett Douglas at 515-284-1010.
Sincerely,
Dylan Jones, ASLA, PLA
Associate
CC: Jason Martin, Caliber Concrete LLC
Brett Douglas, Genus