CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: February 4, 2019
AGENDA ITEM:Consideration of approval of Change Order No. 1 to RW Excavating
Solutions, for the Sugar Creek Golf Course Water Supply Project increases
the contract in the amount of $24,270.00.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 1 to RW Excavating Solutions in the
amount of $24,270.00. During the pond excavation the material being
dredged was determined to be unsuitable for disposal onsite as planned during
the design process, and was recommend to be disposed of offsite. The
original intent of the design was to mix the dredge spoils with the other
excavated soils and place in the proposed berm at the end of the driving range.
Duet to the amount of dredge spoils, silt material which does not support
shaping due to a lack of cohesion between soil particles, there was not enough
competent soil to mix the spoils with. After evaluation, it was decided that if
the original design approach was followed, the berm would not be able to
support golf course operation at project completion. Change Order No. 1
includes the cost for removing the dredge spoils, disposing the material offsite
and for the cost of maintaining the truck route on/off the golf course.
Representative from Bolten & Menk and City Staff have reviewed the
quantities and find them to be accurate.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Change Order No. 1
PREPARED BY: Matt Jermier
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1G
h:\waukee_ci_ia\a13114815_sugar creek gc irrigation well\7_construction\e_pay applications\ltr-01302019_waukee scgc_co#1 recommendation.docx
January 30, 2019
Mr. Matt Jermier
Director of Parks and Recreation
City of Waukee, Iowa
805 University Ave
Waukee, Iowa 50263
RE: Sugar Creek Municipal Golf Course Water Supply Project - Change Order 1
Dear Mr. Jermier:
Submitted for your approval is Change Order 1. During the pond excavation at the Sugar Creek
Municipal Golf Course, the material being dredged was determined to be unsuitable for disposal onsite as
planned during the design process, and should be disposed of offsite. The original intent of the design
was to mix the dredge spoils with the other excavated soils and placed in the proposed berm. Due to the
amount of dredge spoils, silt material which does not support shaping due to a lack of cohesion between
soil particles, there was not enough competent soil to mix the spoils with. After evaluation, it was
decided that if the original design approach was followed, the berm would not be able to support golf
course operations at project completion. It was determined that the dredge spoils would be disposed at an
area at the public works facility north of the golf course using road legal dump trucks.
Change Order #1 includes the cost for removing the dredge spoils, disposing the material offsite and for
the cost of maintaining the truck route on/off the golf course. The original contract value of $135,805.00
will be increased by $24,270.00 to a new contract value of $160,075.00. Please see the Change Order 1
for a full summary of the additional items.
It is anticipated that the total cost of the construction contract will be less than the revised contract amount
as approved with this change order, approximately $15,000 due to underrunning of other contract line
items. The exact amount of the deductions will be made at project closeout, and included in the final
contract closeout change order.
Bolton & Menk, Inc. recommends the approval of Change Order 1. Please let me know if you have any
questions.
Sincerely,
Bolton & Menk, Inc.
Chadd Kahlsdorf, P.E., PMP
Project Manager
H:\WAUKEE_CI_IA\A13114815_Sugar Creek GC Irrigation Well\7_Construction\E_Pay Applications\Sugar Creek Water Supply Change Order 1.xlsx1 of 1
309 E 5th Street, Suite 202 CHANGE ORDERDes Moines, IA 50309
(515) 259-9190 Fax (515) 233-4430 Distribution:
Owner __X__
Engineer __X__
Contractor __X__
Other _____
Contractor:RW Excavating Solutions Project Title Sugar Creek Municipal Golf Course
Water Supply Project
13293 S. 88th Avenue West BMI Project File Number A13.114815
Prairie City, IA 50228 Orig. Contract Amount & Date $135,805.00 10/10/18
Change Order Number 1
Date 01/28/19
THE CONTRACT IS CHANGED AS FOLLOWS: Items listed below are additional line items to complete pond
excavation. Item C01.1 is for the excavation and offsite disposal of pond dredge spoils. Item C01.2 is for the
additional cost to maintain the truck haul route on/off the golf course and maintain the pavement on Ute Ave.
Item Description Unit Unit Price Quantity Adjustment Value
Adjustment
CO1.1 EXCAVATION, CLASS 10, UNSUITABLE SOIL EXPORT CY $10.50 1,740 $18,270.00
CO1.2 ADDITIONAL MOBILIZATION LS $6,000.00 1.00 $6,000.00
TOTAL $24,270.00
CHANGE ORDER SUMMARY
The Original Contract Sum was $135,805.00
Net Change by previously authorized Change Orders $0.00
The Contract Sum prior to This Change Order was $135,805.00
The Contract Sum will be increased by this Change Order in the amount of $24,270.00
The new Contract Sum including this Change Order will be $160,075.00
Aggregate Change Order as a percent of Original Contract 0.00%
The Contract Time will be changed by 0 Days
The date of Final Completion as of the date of this Change Order therefore is March 1, 2019
NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER
Contractor:Recommended By:Approved By:
RW Excavating Solutions Bolton & Menk, Inc.City of Waukee
Signature:Signature:Signature:
Name: John Readout Name: Chadd Kahlsdorf, P.E., P.M.P.Name: Tim Moerman
Title: Project Manager Title: Project Manager Title: City Administrator
Date:Date:Date: