CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: April 1, 2019
AGENDA ITEM:Consideration of approval of Change Order No. 3 to Caliber Concrete, LLC,
for the Fox Creek Park Phase 2 Project increasing the contract in the amount
of $12,109.00
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 3 to Caliber Concrete in the amount of
$12,109.00 reflects cost adds to correct items identified during the Building
Official’s code review, as well as items discussed in progress meetings to
date, such as: changing the storage room ceiling type, altering the play tunnel
design for improved constructability and safety, adding brackets and
galvanization to the transformer gates, and modifying bathroom walls/ceilings
to work with framing. Representative from Genus and City Staff have
reviewed the quantities and find them to be accurate.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Change Order No. 3
PREPARED BY: Matt Jermier
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1Q
gēnus [ landscape architects ]
3 2 5 E A S T 5TH S T R E E T
DES MOINES, IA 50309
T 515 284 1010
WWW.GENUS-LA.COM
March 26, 2019
Mr. Matt Jermier
Parks and Recreation Director, Waukee
805 University Avenue
Waukee, IA 50263
Re: Construction Change Order No. 3
Fox Creek Park Phase Two
City of Waukee, IA
Genus Project No. 17096
Dear Mr. Jermier:
Please find enclosed Change Order No. 3 in the amount of $12,109.00.
This Change Order reflects cost adds to correct items identified during
the Building Official’s code review, as well as items discussed in
meetings to date, such as: changing the storage room ceiling t ype,
altering the play tunnel design for improved constructability and
safety, adding brackets and galvanization to the transformer gates,
and modifying bathroom walls/ceilings to work with framing. The
amount listed above is the net dollar value of the added costs that
comprise Change Order No. 3. The quantities and changes completed
to date have been reviewed and agreed upon by the contractor and
we hereby recommend that the City of Waukee approve Change
Order No. 3.
If you have any questions or comments regarding the enclosed, please
contact me at 515-284-1010.
Sincerely,
Dylan Jones, ASLA, PLA
Associate
CC: Jason Martin, Caliber Concrete LLC
Brett Douglas, Genus
309 Audubon St
City of Waukee Adair Ia 50002
Parks and Rec Dept.
805 University Ave
Waukee Ia. 50263
Fox Creek Park Phase 2
Change order #3
Original Contract amount 3225040
Revised contract amount with change order #1 3178282
Revised contract amount with CO#2 3156661
Revised contract amount with CO#3 3168770
1 Revise rain diverters 330
2 Add signage at fire cabinet 25
3 Add fire cabinet 320
4 Drop ceiling at storage room 330
5 Insulation at family restrooms 747
6 Drip pan hose bib and blow outs 2155
7 Changing Back flow prenter 2168
8 Add access panels 225
9 Furring wall and dropping ceiling 550
10 Play tunnel opening 2376
11 Transformer gate changes 2883
TOTAL 12109
Net contract amount 3168770
City of Waukee Caliber Concrete