HomeMy WebLinkAbout2019-04-01-J01Q Fox Creek Park Phase 2_Change Order 3AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: April 1, 2019 AGENDA ITEM:Consideration of approval of Change Order No. 3 to Caliber Concrete, LLC, for the Fox Creek Park Phase 2 Project increasing the contract in the amount of $12,109.00 FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Change Order No. 3 to Caliber Concrete in the amount of $12,109.00 reflects cost adds to correct items identified during the Building Official’s code review, as well as items discussed in progress meetings to date, such as: changing the storage room ceiling type, altering the play tunnel design for improved constructability and safety, adding brackets and galvanization to the transformer gates, and modifying bathroom walls/ceilings to work with framing. Representative from Genus and City Staff have reviewed the quantities and find them to be accurate. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: Approve Payment RECOMMENDATION: Approve the resolution. ATTACHMENTS: I. Change Order No. 3 PREPARED BY: Matt Jermier REVIEWED BY: PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: J1Q gēnus [ landscape architects ] 3 2 5 E A S T 5TH S T R E E T DES MOINES, IA 50309 T 515 284 1010 WWW.GENUS-LA.COM March 26, 2019 Mr. Matt Jermier Parks and Recreation Director, Waukee 805 University Avenue Waukee, IA 50263 Re: Construction Change Order No. 3 Fox Creek Park Phase Two City of Waukee, IA Genus Project No. 17096 Dear Mr. Jermier: Please find enclosed Change Order No. 3 in the amount of $12,109.00. This Change Order reflects cost adds to correct items identified during the Building Official’s code review, as well as items discussed in meetings to date, such as: changing the storage room ceiling t ype, altering the play tunnel design for improved constructability and safety, adding brackets and galvanization to the transformer gates, and modifying bathroom walls/ceilings to work with framing. The amount listed above is the net dollar value of the added costs that comprise Change Order No. 3. The quantities and changes completed to date have been reviewed and agreed upon by the contractor and we hereby recommend that the City of Waukee approve Change Order No. 3. If you have any questions or comments regarding the enclosed, please contact me at 515-284-1010. Sincerely, Dylan Jones, ASLA, PLA Associate CC: Jason Martin, Caliber Concrete LLC Brett Douglas, Genus 309 Audubon St City of Waukee Adair Ia 50002 Parks and Rec Dept. 805 University Ave Waukee Ia. 50263 Fox Creek Park Phase 2 Change order #3 Original Contract amount 3225040 Revised contract amount with change order #1 3178282 Revised contract amount with CO#2 3156661 Revised contract amount with CO#3 3168770 1 Revise rain diverters 330 2 Add signage at fire cabinet 25 3 Add fire cabinet 320 4 Drop ceiling at storage room 330 5 Insulation at family restrooms 747 6 Drip pan hose bib and blow outs 2155 7 Changing Back flow prenter 2168 8 Add access panels 225 9 Furring wall and dropping ceiling 550 10 Play tunnel opening 2376 11 Transformer gate changes 2883 TOTAL 12109 Net contract amount 3168770 City of Waukee Caliber Concrete