CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: June 3, 2019
AGENDA ITEM: Consideration of approval of Payment Estimate No. 4 to Air-Con Mechanical
for the Waukee Public Library RTU Replacement Project in the amount of
$33,516.43.
FORMAT: Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Payment Estimate No. 4 to Air-Con Mechanical in the
amount of $33,516.43 is for the Library RTU Replacement Project that was
recently approved. The pay estimate relates to installation of the new exterior
ductwork, ductwork insulation, electrical connections and temperature control
components.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the motion
ATTACHMENTS: I. Acceptance Letter from Modus
II. Payment Estimate No. 4
PREPARED BY: Brad Deets, Development Services Director
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1L
Page 1 of 1
May 28, 2019
William Peard, Mayor
City of Waukee
230 Hickman Rd
Waukee, IA 50263
RE: Waukee Public Library RTU Replacement | Application for Payment #4
Dear Mr. Peard:
I have reviewed May’s application for payment from Air-Con Mechanical for the Waukee
Public Library RTU Replacement project.
Modus recommends accepting the amount of $33,516.43 submitted by Air-Con
Mechanical Corporation for payment of installation of the new exterior ductwork, ductwork
insulation, electrical connections and temperature control components.
If you have any questions or concerns, please feel free to call my office at 515.251.7280.
Sincerely,
Holly Stevens, P.E.
Project #18-160