HomeMy WebLinkAbout2019-08-05-J01Q Heart of the Warrior Trail Extension_Pmt Est 1AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: August 5, 2019 AGENDA ITEM:Consideration of approval of Payment Estimate No. 1 to Caliber Concrete LLC., for the Heart of the Warrior Trail Extension Project in the amount of $75,732.20 FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: Payment Estimate No. 1 to Caliber Concrete LLC. is for mobilization, traffic control, removal of shared use path, earthwork, and trail installation. The quantities completed to date have been reviewed and agreed upon by the contractor, City of Waukee Staff, and project engineer Bolton & Menk. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: Approve Payment RECOMMENDATION: Approve the resolution. ATTACHMENTS: I. Letter of Recommendation II. Payment Estimate No. 1 PREPARED BY: Matt Jermier REVIEWED BY: PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: J1Q h:\waukee_ci_ia\a13118227_heart of warrior trail\7_construction\e_pay applications\ltr-07302019_waukee hotwe_pay app#1 recommendation.docx July 30, 2019 Mr. Matt Jermier Director of Parks and Recreation City of Waukee, Iowa 805 University Ave Waukee, Iowa 50263 RE: Heart of Warrior Trail Extension – Pay Application 1 Dear Mr. Jermier: Submitted for your approval is partial Pay Application 1 for the above-mentioned project. Pay Application 1 is for $79,718.11 minus 5% retainage of $3,985.91 for a total payment of $75,732.20. The work completed includes grading for the trail, construction of the trail, and other miscellaneous work. Please see Pay Application 1 for a full summary of the items completed that are included in this payment . Bolton & Menk, Inc. recommends the approval of Pay Application 1. Please let me know if you have any questions. Sincerely, Bolton & Menk, Inc. Chadd Kahlsdorf, P.E., PMP Project Manager Prepared by: $88,548.11 05/06/19 309 E 5th Street, Suite 202 Des Moines, IA 50309 Contractor: (515) 259-9190 Fax (515) 233-4430 Caliber Concrete 309 Audubon Street Adair, IA, 50002 Item No.Description Unit Original Contract Quantity Unit Price Extended Price Total Installed Quantity Value Completed 1 TRAFFIC CONTROL LS 1.00 11,000.00$ 11,000.00$ 1.00 $ 11,000.00 2 REMOVAL OF SHARED USE PATH SY 207.00 11.41$ 2,361.87$ 207.00 $ 2,361.87 3 SHARED USE PATH, PCC, 6"SY 1416.00 44.39$ 62,856.24$ 1416.00 $ 62,856.24 4 CONVENTIONAL SEEDING, SEEDING, FERTILIZING, AND MULCHING SF 2150.00 1.20$ 2,580.00$ 0.00 $ - 5 FILTER SOCK, 12", INSTALL, MAINTAIN, AND REMOVAL LF 2500.00 2.50$ 6,250.00$ 0.00 $ - 6 CONSTRUCTION SURVEY LS 1.00 3,500.00$ 3,500.00$ 1.00 $ 3,500.00 TOTAL 88,548.11$ 79,718.11$ Unit Price Extended Cost -$ -$ -$ -$ TOTAL -$ Contract Price Approved Change Order 1 Approved Change Order 2 Revised Contract Price Materials Stored Retainage (5%) Liquidated Damages Total Earned Less Retainage Total Previously Approved $0.00 Amount Due This Request $75,732.20 Percent Complete 90% Percent of Contract Period Utilized 89% The amount $75,732.20 is recommended for approval for payment in accordance with the terms of the Contract PAY REQUEST SUMMARY 88,548.11$ Total Completed 79,718.11$ Total Approved 88,548.11$ -$ -$ BID ITEMS # of Units Name: Tim Moerman Title: City Administrator 3,985.91$ -$ 75,732.20$ MATERIALS STORED SUMMARY Description N/A -$ Date: Recommended By: Bolton & Menk, Inc. Signature: Name: Chadd Kahlsdorf P.E., PMP Title: Project Manager Date: Contractor: Total Previously Approved (list each) Checked By: City of Waukee Signature: Pay Request 1 Pay Request 2 Pay Request 3 Pay Request 4 Pay Request 5 Pay Request 6 Date: Title: Project Manager Name: Signature: Caliber Concrete Sugar Creek Golf Course Water Supply Project BMI Project # Estimated Completion Date: 07/30/19 1 08/09/19 A13.118227 Orig. Contract Amount & Date: Date: Pay Request Number: Pay Request 1 1 of 1