HomeMy WebLinkAbout2019-09-03-I03B Wastewater Treatment Facillity Demolition_Award ContractAGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: September 3, 2019
AGENDA ITEM:Consideration of approval of a resolution awarding contract [Wastewater
Treatment Facility Demolition Project]
FORMAT:Resolution
SYNOPSIS INCLUDING PRO & CON: The project bid letting was held at Waukee City Hall
on Wednesday, August 28, 2019, at 2:00 p.m. Four (4) apparent bids
were received, with the low bid submitted by Wenthold Excavating of
Cambridge, IA, in the amount of $943,800.00.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:$943,800.00
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: City staff recommends awarding contract to Wenthold
Excavating of Cambridge, IA, in the amount of $943,800.00.
RECOMMENDATION: Approve the resolution
ATTACHMENTS: I. Proposed resolution
II. V&K letter of recommendation
III. Bid tabulation
PREPARED BY: Becky Schuett
REVIEWED BY:
I3B
RESOLUTION 19-
RESOLUTION MAKING AWARD OF CONSTRUCTION
CONTRACT FOR THE WASTEWATER TREATMENT
FACILITY DEMOLITION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WAUKEE, STATE
OF IOWA:
Section 1.That the following bid for the construction of certain public improvements
described in general as the Wastewater Treatment Facility Demolition, described in the plans and
specifications heretofore adopted by this Council on September 3, 2019, be and is hereby accepted,
the same being the lowest responsive, responsible bid received for such work, as follows:
Contractor: Wenthold Excavating of Cambridge, IA
Amount of bid: $943,800.00
Portion of project: All construction work
Section 2.That the Mayor and Clerk are hereby directed to execute the contract with the
contractor for the construction of the public improvements, such contract not to be binding on the
City until approved by this Council.
PASSED AND APPROVED this 3rd day of September, 2019.
Mayor
ATTEST:
City Clerk