HomeMy WebLinkAbout2019-10-07-K11City Hall Renovation_Change Order 3 AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: October 7, 2019
AGENDA ITEM: Consideration of approval of Change Order No. 3 to Ball Team, LLC, for the
Waukee City Hall Renovation Project increasing the contract in the amount of
$142,874.00 and amending the project completion date
FORMAT: Consent Agenda
SYNOPSIS INCLUDING PRO & CON: The proposed Change Order No. 2 consists primarily of
the landscaping project that was added to the project after discussion during a
Council Work Session. Additionally it was discovered during demolition that
there was a small area of mold in the Development Services Director’s office
that had to be addressed. The remaining items consist of electronic door
hardware, security cameras and electricity to the new monument sign.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $142,874.00
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: The original project bid was way under the project estimate
and project budget. The additional items within change order no. 3 can be
accommodated within the original project budget.
RECOMMENDATION: Approve the Change Order
ATTACHMENTS: I. Recommendation Letter from Shive Hattery
II. Change Order No. 3
PREPARED BY: Brad Deets
REVIEWED BY:
K11
Project # 418297-0
Shive-Hattery, Inc. | 4125 Westown Pkwy | Suite 100 | West Des Moines, IA 50266 | 515.223.8104 | shive-hattery.com
September 24, 2019
TO: Brad Deets, Development Services Director
City of Waukee
230 W. Hickman Road
Waukee, IA 50263
RE: Change Order #3
City of Waukee – City Hall Improvements
SH Project # 418297-0
Dear Mr. Deets,
Attached please find a Change Order for the Waukee City Hall Improvements. The Change
Order includes the following items:
• Landscape and Irrigation Improvements - $120,067
• Credit for Alternate Flag Pole Light – ($2,375)
• Asphalt Patch - $2,200
• Security Cameras - $878
• Monument Sign Power - $1,915
• Schedule Modifications - $0 – Added 48 days to schedule
• Electronic Door Hardware - $2,295
• Mold Time & Material Work - $11,472
• Column Cap - $1,238
• University Sign Plantings - $5,184
We have reviewed each of the Change Order Requests which are attached to this letter and
recommend approval. If City staff concurs with this change order, we recommend the City of Waukee
increase the contract price in the amount of $142,874 and the increase the schedule by 48 days.
Sincerely,
SHIVE-HATTERY, INC.
Emily C. Naylor
Project Manager
Enc. Change Order #3
CITY OF WAUKEE CHANGE ORDER #3
Department of Public Works
805 University Avenue Distribution:
Waukee, IA 50263 Owner __X__
Phone: (515) 978-7920 Engineer__X__
Fax: (515) 987-3979 Contractor__X__
Other _____
Contractor:Ball Team, LLC
10550 New York, Suite 100
Urbandale, Iowa 50322
February 12, 2019
1 COR #11 EA $120,067.00 1.000 $120,067.00
2 COR #12 EA ($2,375.00)1.000 ($2,375.00)
3 COR #13 EA $2,200.00 1.000 $2,200.00
4 COR #14 EA $878.00 1.000 $878.00
5 COR #15 EA $1,915.00 1.000 $1,915.00
6 COR #16 EA $0.00 1.000 $0.00
7 COR #17 EA $2,295.00 1.000 $2,295.00
8 COR #18 EA $11,472.00 1.000 $11,472.00
9 COR #19 EA $1,238.00 1.000 $1,238.00
10 COR #22 EA $5,184.00 1.000 $5,184.00
$142,874.00
$441,000.00
$27,325.00
$468,325.00
$142,874.00
$611,199.00
48 days
Owner:City of Waukee
□ ≤$500 Department Director X_______________________________________Date__________________Date___________________
□ $501 to $2,500 City Administrator X_______________________________________Date__________________Date___________________
□ >$2,501 City Council approved or ratified at Council meeting on Date___________________
Mold Time & Material
Column Cap Covers
The new Contract Sum including this Change Order will be
Date
THE CONTRACT IS CHANGED AS FOLLOWS:
Item No.Value AdjustmentQuantity AdjustmentUnit PriceUnit
Asphalt Patch
Item Code
9/24/2019
Security Cameras
Power to Monument Sign
Schedule Modifications - 48 days added to schedule
Name: Emily Naylor
Title: Project Manager
NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE (if applicable) AND OWNER
Shive-Hattery, Inc.
Checked By:
City of Waukee
Signature:
Name:
Title:
Project Title
Shive-Hattery Project File Number
Change Order Number
The Contract Time will be changed by
CHANGE ORDER SUMMARY
TOTAL
The Original Contract Sum was
Net Change by previously authorized Change Orders
The Contract Sum prior to This Change Order was
The Contract Sum will be increased by this Change Order in the amount of
Waukee Project File Number
Description
Landscaping and Irrigation Improvements
3
Orig. Contract Amount & Date
City of Waukee - City Hall Improvements
418297-0
$441,000.00
Deduct/credit for Flagpoles light revision
Date:
Ball Team, LLC
Contractor:
Name:
Title:
University Sign Plantings
Electronic Door Hardware
Date:
Signature:
Recommended By:
Date:
Signature:
P:\Projects\DM\4182970\Construction\CASupport\CO\ChangeOrder#03\418297-0 Change Order #3.xlsx 1 of 1
10550 New York Avenue, Suite 100
Urbandale, IA 50322
Office: 515.440.4544
Owner:City of Waukee Project:Waukee City Hall Renovation
230 W. Hickman Rd. Project No: 19-003
Waukee, IA 50263 Reference No:CR #11
Date: June 26, 2019
Description:
We thank you for the opportunity to submit a proposal for the Waukee City Hall Front Parking Aesthetic Enhacements.
Our proposal is based off of plans sent by Shive-Hattery dated 06/06/19 as well as scope descriptions provided by Emily Naylor
on 06/06/19. Attached is an estimate summary as well as alternates, as requested, listed below.
ALTERNATE #1a ADD: Irrigation Design/Build at Landscaping Enhacements $12,720.00
ALTERNATE #1b ADD: Add dripline Irrigation to remainder of building landscaping and yards $14,199.00
(See attached irrigation plan)
Exclusions/Clarifications:
- Anything not listed herein
- We exclude any profressional design services and engineering
- Asbestos Abatement or Hazardous Material Handling is excluded
- Excludes any overexcavation or deep foundations.
- We exclude any testing, inspections, or energy audits.
- We exclude all work marked on drawings as "not in contract" areas
- We exclude any signage
- Utility Consumption is to be by owner.
- We exclude Builder's Risk Insurance
- Pricing Excludes Bonds
- We exclude any permits associated with this work
- We Include a $3,500 Survey/Staking Allowance
- We believe project schedule would be +/-4 weeks
TOTAL:$105,868.00
Accepted by:
City of Waukee
Date:
cc: File (1)
Owner Change Request
On behalf of the
9/13/2019
Approved.
$120,067.00
Dated: Prepared by: CR #11Landscape EnhacementsCOST CODE DESCRIPTIONQTY UTLABOR UNIT LABORMATL UNITMATERIAL (w/tax) EQUIP SUB TOTAL01.001Superintendent Part Time4 WK 0.00 $1,400 $0 $0 $0 $0.00$5,60001.002 Pick Up Truck Rental4 WK 0.00 $0 $0 $0 $150 $0$60001.003 Pick Up Truck Fuel4 WK 0.00 $0 $0 $0 $100 $0$40001.011 Project Manager 4 WK 0.00 $750 $0 $0 $0 $0$3,00001.041 Office Expenses4 WK 0.00 $0 $0 $0 $100 $0$40001.071 Weekly Cleanup4 WK 0.00 $225 $0 $0 $0 $0$90001.072 Dumpsters/Concrete Washouts1 LD 0.00 $0 $0 $0 $455 $0$45501.510 Temp. Toilets4 WK 0.00 $0 $0 $0 $88 $0$35001.092 Tool Rental4 WK 0.00 $0 $0 $0 $100 $0$40001.073 Final Clean1 LS 0.00 $0 $0 $0 $0 $500$500$002.111 Survey & Staking Allowance1 LS$3,500$3,500$002.171 Site Demolition / Grading1 LS$8,850$8,850 - Remove Turf/Strip Site$0 - Strip & Salvage Brick Chip & Dispose of Plantings$0 - Remove and Dispose of Flagpoles$0 - Remove uplights$0 - Regrade Slope$0 - 3 Loads of Black Dirt3 LD$800$2,400$002.173 Erosion Control 1 LS$2,750$2,750$002.181 Landscaping 1 LS$37,122$37,122 - Furnish and Install Limestone Edging$0 - Soil Amendments$0 - Includes 1 Added ornamental tree$0 - Double Shredded Mulch$0 - Salvaged Brick Chips / Protect Plantings 1 LS$3,000$3,000 - Restore Disturbed Area $0 - Remove and Replace Brick Chips around Building$0 - Landscape Edger Prep1 LS$2,500$2,500$010.101 Furnish and Install Flag Poles1 LS$18,750$18,750 - Concrete Foundations1 LS$3,500$3,500$016.101 Electrical1 LS$3,599$3,599 - Demo Existing Electrical and Circuits$0 - Run Electrical for new Flagpoles$0 - Uplighting1 LS$1,500$1,500 $2,375 $0 $993 $86,371 $100,076General Liability Insurance0.75%$751Contractor Fee5.00%$5,041 TOTAL$105,868Signature: Date: Waukee City Hall RenovationJune 26, 2019Matt Burch
1
Matt Burch
From:dennis carter <dennisocarter@gmail.com>
Sent:Thursday, May 16, 2019 8:22 AM
To:Matt Burch
Subject:Waukee city hall
$ 8,850 for items on the list with my name on them.I will send a better proposal later today itemizing scope.
Sent from my iPhone
Landscape Proposal
Date
5/16/2019
Estimate #
337379
Name / Address
BallTeam,L.L.C.
2900 Westown Parkway, Suite 240
West Des Moines, Iowa 50266
Alcarey Landscape
PO Box 314
Waukee, IA 50263
Project Waukee parking enhancement
Phone #515-987-7825
Fax #
E-mail
alcareyinc@msn.com
Total
Description Qty
Oso Easy Paprika #2 187
Dwarf Bush Honeysuckle #5 122
'Shenandoah' Switch Grass #5 29
Touchdown Teak #1 75
'Little Lime' Hydrangea #3 18
Chelone lyonii 'Hot Lips' 54
Hardwood Mulch Bulk 197
Iowa Buff Planter Stone 4-5"x6" as edgring 215
TS-32 TreeSpade 5
Typar 3201 4' x 300' 19,687
Compost 32
Spring Snow Crab 1.5" 1
Dump fee trash to remove existing tree and stump 2
Bloomerang Lilac #3 12
Sales Tax
$33,341.49
Landscape Proposal
Date
5/16/2019
Estimate #
337382
Name / Address
BallTeam,L.L.C.
2900 Westown Parkway, Suite 240
West Des Moines, Iowa 50266
Alcarey Landscape
PO Box 314
Waukee, IA 50263
Project Respread Brick chips
Phone #515-987-7825
Fax #
E-mail
alcareyinc@msn.com
Total
Description Qty
Salvage Existing Brick Chip and respread
Brick Chip Course Red tn 23.38
Sales Tax
$3,252.16
Landscape Proposal
Date
5/16/2019
Estimate #
337380
Name / Address
BallTeam,L.L.C.
2900 Westown Parkway, Suite 240
West Des Moines, Iowa 50266
Alcarey Landscape
PO Box 314
Waukee, IA 50263
P.O. No.
Project
Waukee Enhancement sod
Phone #515-987-7825
Fax #
E-mail
alcareyinc@msn.com
Total
Subtotal
Sales Tax (7.0%)
Description Qty Rate Total
Finish grade and sod 12 44.00 528.00T
$564.96
$528.00
$36.96
Sales Quote
Date
6/20/2019
Estimate #
482
Name / Address
Ball Team LLC
10550 New York Ave., Suite 100
Urbandale, IA 50322
Ship To
Ball Team, LLC
10550 New York Ave., Suite 100
Urbandale, IA 50322
135 5th St.
West Des Moines, IA 50265
Terms
Net 15
Availability
Total
Subtotal
Sales Tax (0.0%)
Phone: (800) 992-3524
Email: brettb@martinsflag.com
Terms and Condtions:
Quotations are void unless accepted within 30 days from date of issue. Prepayment in the
form of a credit card or check is due upfront unless other arrangements for payment have been
made. Shipping quotes may vary due to sudden variation of shipping costs.
Martin's Flag Company
Item Description Qty Cost Total
FPS35 35-Ft. Monarch Model Internal System Aluminum
Flagpole, 1 piece, 7" base, .156" wall, Satin Finish
1 2,550.00 2,550.00
FPPARTSMISC Flagpole Uplighting, Pole LED, O2 1 2,895.00 2,895.00
FPS25 25-Ft. Monarch Model Internal System Aluminum
Flagpole, 5" base, .156" wall, FULL LENGTH, Satin
Finish
2 1,590.00 3,180.00
FPPARTSMISC Flagpole Uplighting, Pole LED, Extended 2 2,395.00 4,790.00
FPINSTALL Flagpole Installation 1 4,550.00 4,550.00
Shipping Charges*1 785.00 785.00
This is with a 1-piece 35' flagpole
$18,750.00
$18,750.00
$0.00
Bid Proposal
Date: 5/14/19
Attention:
Matt Burch-Ball Team
,
SUBJECT: Waukee Beautification project.
Thank you for the opportunity to offer our proposal for the subject project. Our pricing encompasses:
I.Scope of Work
A.Our Proposal Includes:
1.Inspections and license fees
2.Trenching power to 3 new Pole Lights
3.Demo lights on wood post
B.Our Proposal Excludes
1.Pole foundations
C.Clarifications: Power will be rerouted from existing circuiting on burm. No new
circuits are included in this proposal.
II.Pricing Summary
A.Base Bid $3,599.00
Thanks for the opportunity if you have questions or would like to discuss in more detail my contact
information is listed below. I look forward to hearing from you.
Sincerely,
Travis Deaver
Commercial Estimator
Office: 515-202-9481
2800 SE Destination Dr. Suite F Grimes, IA 50111 Phone: 515-202-9481
Website: deaverelectricinc.com
1821 SE Miehe Drive Suite A Grimes, IA 50111 Phone (515) 986-1172 Fax: (515) 986-1173
E-mail : tssincdsm@gmail.com
NAME:DATE :
STREET:JOB NAME:
CITY:STREET:
STATE:CITY: STATE:
PH: 515-480-7477 EMAIL: mburch@buildwithball.com
We hereby submit specifications and estimates for:Waukee City Hall- Base Bid
Net Due Upon Completion
This proposal is good for 30 days. Signed:
T & T Sprinkler Service, Inc.
To validate this proposal, initial, sign, date and forward to:
T & T Sprinkler Service 1821 SE Miehe Drive Suite A- Grimes, IA 50111- Phone (515) 986-1172 - Fax (515) 986-1173
Acceptance:Date:
Urbandale
IA
78 Rainbird 1812 Sprays
This bid is for the installation of irrigation per the plan provided and includes the expense to
bore across the west driveway. If any other sleeves are required as part of the installation they
PROPOSAL SUBMITTED TO:
Ball Team, Matt Burch 6/19/19
10550 New York Ave Waukee City Hall
*Bid assumes client is providing backflow connected to water supply for our point of attachment
David Kuncl
Approximately 275' 1" PVC Mainline
All required pipe, fittings, wiring, valve boxes,
and miscellaneous items as needed to complete installation
Total $9,120.00, materials and installation labor
Approximately 1200' 1" Poly Lateral Lines
10 1" Rainbird DV-F Valves
1 Rainbird ESPME3 Controller
1 Rainbird WR2-RFC Rain/Freeze Sensor
Scope as noted in red on attached picture.
would be additional to the price below at $75/foot bored.
1821 SE Miehe Drive Suite A Grimes, IA 50111 Phone (515) 986-1172 Fax: (515) 986-1173
E-mail : tssincdsm@gmail.com
NAME:DATE :
STREET:JOB NAME:
CITY:STREET:
STATE:CITY: STATE:
PH: 515-480-7477 EMAIL: mburch@buildwithball.com
We hereby submit specifications and estimates for:Waukee City Hall- Alternate Bid
Net Due Upon Completion
This proposal is good for 30 days. Signed:
T & T Sprinkler Service, Inc.
To validate this proposal, initial, sign, date and forward to:
T & T Sprinkler Service 1821 SE Miehe Drive Suite A- Grimes, IA 50111- Phone (515) 986-1172 - Fax (515) 986-1173
Acceptance:Date:
David Kuncl
Approximately 225' of Drip Line
All required pipe, fittings, wiring, valve boxes,
and miscellaneous items as needed to complete installation
Total $675.00, materials and installation labor
PROPOSAL SUBMITTED TO:
Ball Team, Matt Burch 6/19/19
10550 New York Ave Waukee City Hall
1 1" Rainbird DV-F Valves
Urbandale
IA
This bid is for scope in addition to the base plan and assumes that the infrastructure from the
base bid is in place. This adds drip line to the area noted in green on the attached picture.
Irrigation Drawings
10550 New York Avenue, Suite 100
Urbandale, IA 50322
Office: 515.440.4544
Owner:City of Waukee Project:Waukee City Hall Renovation
230 W. Hickman Rd.Project No:19-003
Waukee, IA 50263 Reference No:CR #12
Date:July 18, 2019
Description:
Attached is the credit for PR 004. This cost substitutes the originally bid LED uplight for the Stargazer LED Downlight.
TOTAL:($2,375.00)
Accepted by:
City of Waukee
Date:
cc: File (1)
Owner Change Request
Dated: Prepared by: CR-#12PR 004 - Flagpole Light SubstituteCOST CODE DESCRIPTIONQTY UTLABOR UNIT LABORMATL UNITMATERIAL (w/tax) EQUIP SUB TOTAL10.101Eliminate LED Lights and go to 3 Stargazer Down Lights1 LS 0.00$0 $0$0$0($2,375.00)($2,375)$0$0 $0 $0 $0($2,375) ($2,375)General Liability Insurance0.75%$0Contractor Fee5.00%$0 TOTAL($2,375)Signature: Date: Waukee City Hall RenovationJuly 18, 2019Matt Burch
SHIVE-HATTERY, INC.
PROPOSAL REQUEST
PROJECT: City of Waukee – City Hall Renovation
OWNER: City of Waukee
TO: CONTRACTOR: Ball Team, LLC.
CONTRACT FOR: General Construction
PROPOSAL REQUEST NO: 004
DATE OF ISSUANCE: 07/17/2019
ARCHITECT: Shive-Hattery, Inc.
4125 Westown Pkwy, #100
West Des Moines, IA 50266
ARCHITECT’S PROJECT NO: 418297-0
___________________________________________________________________________________________
Please submit an itemized proposal for changes in the Contract Sum and Contract Time for proposed modifications
to the Contract Documents describe herein.
THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE, OR A DIRECTION TO
PROCEED WITH THE WORK DESCRIBED IN THE PROPOSED MODIFICATIONS.
Description:
Substitute (3) POLE LED flagpole-mounted lights with (3) Stargazer LED Downlight/Internal Truck
Combo by Eagle Mountain Flag a& Flagpole.
ISSUED BY: Eric Holt
SHIVE-HATTERY, INC.
Eric B. Holt, PLA
Attached: N/A
Copy: Jace Henderson & Matt Burch – Ball Team
Emily Naylor – Shive-Hattery
Kristen Clark – Shive-hattery
10550 New York Avenue, Suite 100
Urbandale, IA 50322
Office: 515.440.4544
Owner:City of Waukee Project:Waukee City Hall Renovation
230 W. Hickman Rd. Project No: 19-003
Waukee, IA 50263 Reference No:CR #13
Date: July 30, 2019
Description:
Patch Asphalt at 10 Stalls along east entry to Waukee City hall using hot plate process. Stalls will be re-striped upon completion.
If additional stalls along east side need redone add $265.
TOTAL:$2,200.00
Accepted by:
City of Waukee
Date:
cc: File (1)
Owner Change Request
Dated: Prepared by: CR-#13Asphalt RepairCOST CODE DESCRIPTIONQTY UTLABOR UNIT LABORMATL UNITMATERIAL (w/tax) EQUIP SUB TOTAL01.001 Supervision4 HR 0.00 $70 $0 $0 $0 $0$28002.241Asphalt Repair at Wheel Areas along East Side (10 Stalls)1 LS 0.00 $0 $0 $0 $0 $1,600.00$1,60002.241 Re-Stripe Stalls1 LS 0.00 $0 $0 $0 $0 $200$200$0$0 $70 $0 $0 $1,800 $2,080General Liability Insurance0.75%$16Contractor Fee5.00%$105 TOTAL$2,200Signature: Date: Waukee City Hall RenovationJuly 30, 2019Matt Burch
4154 SE Capitol Circle Grimes, IA 50111 Phone: 515-986-4243 Fax: 515-986-4628 www.desmoinessweepingstriping.com
Quotation for Services
Date: 07/30/2019
Customer: Ball Team Project: City of Waukee Offices Asphalt Repair
Address: 10550 New York Avenue, Suite 100 Address: 230 Hickman Rd.
City, State, Zip: Urbandale, IA 50322 City, State, Zip: Waukee, IA
Contact: Matt Burch; 515-480-7477
mburch@buildwithball.com
Bid Date: 07/30/2019
Bid Item Item Description Quantity Unit Price Total
Mobilization Mobilization of crew and equipment for project completion. Lump
Sum
$250.00 $250.00
Asphalt
Repair
Utilization of infrared asphalt repair process to repair wheel
divots on the east side of the building.
10 Heats $185/Heat $1,850.00
Total Cost for Project $2,100.00
Estimated by: Michael Nelson Cell: 515-205-0167 Email: michael@thehenriksengroup.com
Heartland Outdoor Services LLC proposes to supply the labor, materials, and equipment for the project referenced
above based on plans, specifications, and or requests by Ball Team.
Any changes to the bid plans may modify the proposed prices above.
Final quantities based on actual field measurements.
SIGNATURE: _______________________________________________________________________________
10550 New York Avenue, Suite 100
Urbandale, IA 50322
Office: 515.440.4544
Owner:City of Waukee Project:Waukee City Hall Renovation
230 W. Hickman Rd. Project No: 19-003
Waukee, IA 50263 Reference No:CR #14
Date: July 30, 2019
Description:
Add piping and pull strings for two security cameras. Low Voltage Wiring, Furnish and Install of Cameras will be by City of
Waukee
TOTAL:$878.00
Accepted by:
City of Waukee
Date:
cc: File (1)
Owner Change Request
Dated: Prepared by: CR-#14Security Camera PipingCOST CODE DESCRIPTIONQTY UTLABOR UNIT LABORMATL UNITMATERIAL (w/tax) EQUIP SUB TOTAL01.001 Supervision4 HR 0.00 $70 $0 $0 $0 $0$28016.101Security Camera Conduit and Pull String1 LS 0.00 $0 $0 $0 $0 $550.00$550$0$0$0 $70 $0 $0 $550 $830General Liability Insurance0.75%$6Contractor Fee5.00%$42 TOTAL$878Signature: Date: Waukee City Hall RenovationJuly 30, 2019Matt Burch
Change Order
Date
7/22/2019
Change Order #
3753
Contractor
BallTeam LLC
10550 New York Ave Suite 100
Urbandale, IA 50322
Job Location
230 Hickman Rd
Waukee
Deaver Electric Inc.
2800 SE Destination Dr
Suite F
Grimes, IA 50111
Job No.
190147 Waukee City...
Phone #5152029481 E-mail travis@deaverelectricinc.com
TotalSales Tax (6.0%)
DescriptionQty Cost
PR 005 Add additional pull strings from electrical room for 2 security cameras on
the south wall of City hall. This does include mounting the camera's but
connection is by others.
550.00
Change order prepared by: Deaver Electric
This is a quotation on the service and goods named, subject to the conditions noted: The Owner/Contractor shall sign change order before work
can begin.
Please sign and Date Change order to authorize work:___________________________________________________________
Date:_________________
$550.00$0.00
10550 New York Avenue, Suite 100
Urbandale, IA 50322
Office: 515.440.4544
Owner:City of Waukee Project:Waukee City Hall Renovation
230 W. Hickman Rd. Project No: 19-003
Waukee, IA 50263 Reference No:CR #15
Date: July 30, 2019
Description:
Furnish and Install power from existing manhole to monument sign.
Final connections to monument sign is by others.
TOTAL:$1,915.00
Accepted by:
City of Waukee
Date:
cc: File (1)
Owner Change Request
Dated: Prepared by: CR-#15Monument Sign ConduitCOST CODE DESCRIPTIONQTY UTLABOR UNIT LABORMATL UNITMATERIAL (w/tax) EQUIP SUB TOTAL01.001 Supervision8 HR 0.00 $70 $0 $0 $0 $0$56016.101Power to New Monument Sign1 LS 0.00 $0 $0 $0 $0 $1,250.00$1,250$0$0$0 $70 $0 $0 $1,250 $1,810General Liability Insurance0.75%$14Contractor Fee5.00%$91 TOTAL$1,915Signature: Date: Waukee City Hall RenovationJuly 30, 2019Matt Burch
Change Order
Date
7/22/2019
Change Order #
3755
Contractor
BallTeam LLC
10550 New York Ave Suite 100
Urbandale, IA 50322
Job Location
230 Hickman Rd
Waukee
Deaver Electric Inc.
2800 SE Destination Dr
Suite F
Grimes, IA 50111
Job No.
190147 Waukee City...
Phone #5152029481 E-mail travis@deaverelectricinc.com
TotalSales Tax (6.0%)
DescriptionQty Cost
Add new power to the new monument sign. This price includes boring a 1"
conduit from the existing handhole on the North side of the building to the new
sign location.
Total 1,250.00
Change order prepared by: Deaver Electric
This is a quotation on the service and goods named, subject to the conditions noted: The Owner/Contractor shall sign change order before work
can begin.
Please sign and Date Change order to authorize work:___________________________________________________________
Date:_________________
$1,250.00$0.00
10550 New York Avenue, Suite 100
Urbandale, IA 50322
Office: 515.440.4544
Owner:City of Waukee Project:Waukee City Hall Renovation
230 W. Hickman Rd. Project No: 19-003
Waukee, IA 50263 Reference No:CR #16
Date: August 2, 2019
Description:
Additional Days Request due to mold abatement, additional landscape enhancements and weather days.
CR #11 - Landscape Enhancements add 30 days
Mold Abatement - add 10 days.
Weather Days - add 8.5 days
Original Scheduled Completion per schedule issued 03/15/19 = 07/29/19.
TOTAL:$0.00
Accepted by:
City of Waukee
Date:
cc: File (1)
Owner Change Request
Dated: Prepared by: CR-#16Schedule ModificationCOST CODE DESCRIPTIONQTY UTLABOR UNIT LABORMATL UNITMATERIAL (w/tax) EQUIP SUB TOTAL01.000 Schedule Modifications$0$0$0$0$0 $0 $0 $0 $0 $0General Liability Insurance0.75%$0Contractor Fee5.00%$0 TOTAL$0Signature: Date: Waukee City Hall RenovationAugust 2, 2019Matt Burch
10550 New York Avenue, Suite 100
Urbandale, IA 50322
Office: 515.440.4544
Owner:City of Waukee Project:Waukee City Hall Renovation
230 W. Hickman Rd. Project No: 19-003
Waukee, IA 50263 Reference No:CR #17
Date: August 6, 2019
Description:
Revised Electronic Hardware to Work with Existing Door and Automatic Door Opener Refer. RFI 15
*HES 8000 Series did not work with original doors had to change to a HES 5000. City of Waukee wants to keep the 2 HES
8000 series per Son Le.
TOTAL:$2,295.00
Accepted by:
City of Waukee
Date:
cc: File (1)
Owner Change Request
Dated: Prepared by: CR-#17Electronic Door HardwareCOST CODE DESCRIPTIONQTY UTLABOR UNIT LABORMATL UNITMATERIAL (w/tax) EQUIP SUB TOTAL01.001 Supervision2 HR 0.00 $70 $0 $0 $0 $0$140$008.151 HES 8000c Series - kept per city1 LS 0.00 $0 $0 $0 $0 $830$83008.151HES 5000c Series1 LS 0.00 $0 $0 $0 $0 $1,200$1,200$0$0 $70 $0 $0 $2,030 $2,170General Liability Insurance0.75%$16Contractor Fee5.00%$109 TOTAL$2,295Signature: Date: Waukee City Hall RenovationAugust 6, 2019Matt Burch
1
Matt Burch
From:Remedy Glass LLC <remedyglass@gmail.com>
Sent:Monday, August 5, 2019 9:07 AM
To:Matt Burch
Subject:Waukee City Hall Changes
The current strikes will not function properly with the style of latch that is required for the preps on the existing doors.
They need 2 @ 5000c series hes strikes with latch monitoring. We will need to re prep the frames further to accept the
new strike but all the wiring is ran or will be ran by others.
CHANGE ORDER#1
FOR ORGINAL ELECTRIC STRIKES 2 @HES 8000C WITH LATCH MONITORING, 2 @ DEAD LATCHES, PADDLE LEVER, AND
MOUNTING PLATES
WAUKEE CITY HALL WANTS TO KEEP PER SON LE
ADD $829.51
CHANGE#2
FOR NEW ELECTRONIC STRIKES 2 @ 5000c series hes strikes with latch monitoring AND INSTALLED
ADD $1,200.00
--
Remedy Glass, LLC
907 Hwy 30 East
PO Box 514
Carroll, IA 51401
712-792-1979 phone
712-792-1982 fax
remedyglass@gmail.com
10550 New York Avenue, Suite 100
Urbandale, IA 50322
Office: 515.440.4544
Owner:City of Waukee Project:Waukee City Hall Renovation
230 W. Hickman Rd. Project No: 19-003
Waukee, IA 50263 Reference No:CR #18
Date: September 2, 2019
Description:
Mold Remediation Work, on Time and Material. Includes replacing exterior sheathing, bad studs, and new Ty-Vek. Interior work
consists of replacing sheetrock, patching back in ceilings, adding vapor barrier to interior wall cavity, taping, finishing, and paint.
See attached T&M Invoices
TOTAL:$11,472.00
Accepted by:
City of Waukee
Date:
cc: File (1)
Owner Change Request
Dated: Prepared by: CR-#18Mold T&M WorkCOST CODE DESCRIPTIONQTY UTLABOR UNIT LABORMATL UNITMATERIAL (w/tax) EQUIP SUB TOTAL01.001 Supervision8 HR 0.00 $70 $0 $0 $0 $0$56001.100Earth Services Invoice (Direct billed to owner - no work)1 LS 0.00 $0 $0 $0 $0 $0.00$007.161 Additional Nichiha and Brick Flashing at Exterior Windows 1 LS 0.00 $0 $0 $0 $0 $1,736$1,73609.111Replace Sheet Rock, Finish, Tape, includes exterior sheathing and Ty-Vek Work1 LS 0.00 $0 $0 $0 $0 $8,213$8,21309.201Paint Interior Office Walls and Texture1 LS 0.00 $0 $0 $0 $0 $335$335$0 $70 $0 $0 $10,284 $10,844General Liability Insurance0.75%$81Contractor Fee5.00%$546 TOTAL$11,472Signature: Date: Waukee City Hall RenovationSeptember 2, 2019Matt Burch
Invoice
Invoice Date:8/27/2019
Invoice #:3123
Bill To:
Ball Team LLC Construction
2900 Westtown Parkway Suite 240
West Des Moines IA 50266
Whitey Exteriors
Indianola, IA 50125
P.O. Number:
Due Date:8/27/2019
Case:
Total
Balance Due
Payments/Credits
Description Hours/Qty Rate Amount
Waukee City Hall
Nichiha Siding Material and Labor 1 29,500.00 29,500.00
Nichiha Flashing 1 1,280.00 1,280.00
Seamless Gutters and Downspouts 1 4,300.00 4,300.00
Roofing material and labor 1 4,200.00 4,200.00
Extras
Fascia on front Gables material and labor 16 22.00 352.00
Added Framing on bottom of Gables for Gutters 8 55.00 440.00
Additional Nichiha at lower location 1 1,700.00 1,700.00
Brick Flashing 3 12.00 36.00
Soffit Venting and Hardie Material 1 1,860.00 1,860.00
Soffit Venting and Hardie Labor 54 55.00 2,970.00
Column Caps 4 275.00 1,100.00
$47,738.00
$47,738.00
$0.00
JOB NAME:
JOB #:
DATE:
FWO #:
CHARGE TO:
WORK DESCRIPTION:
TRADE HOURS RATE TOTAL
Painter 4.00 64.00 256.00
- -
- -
- -
- -
- -
- -
- -
4.00 256.00$
QUANTITY UNIT $COST SALES TAX TOTAL
1.00 6.00 6.00 6.00%6.00
2.00 20.00 40.00 6.00%42.00
1.00 9.00 9.00 6.00%10.00
1.00 20.00 20.00 6.00%21.00
- -
- -
- -
- -
- -
- -
- -
- -
79.00$
QUANTITY UNIT $COST SALES TAX TOTAL
- -
- -
- -
- -
- -
-$
QUANTITY RATE TOTALS
4.00 256.00
79.00
-
-
-
335.00$ FWO TOTAL
DESCRIPTION
Total Labor Costs
Total Material & Equipment Costs
Material & Equipment Overhead
Truck Charge
Bond
TOTAL EQUIPMENT COSTS
FIELD WORK ORDER SUMMARY
LABOR COST DETAIL
Tim King
DESCRIPTION
EQUIPMENT COST DETAIL
Ball Team
EMPLOYEE NAME
2" Tape
200 Eggshell
1/2" Roller Cover
Lightweight Plastic
7/23/2019
PT-2297
Waukee City Hall
51189
TOTAL MATERIAL COSTS
TOTAL LABOR COSTS
MATERIAL COST DETAIL
Painting textured wall in office
DESCRIPTION
CUSTOMER APPROVAL
Ruben Billalba III
1ST INTERIORS APPROVAL
10550 New York Avenue, Suite 100
Urbandale, IA 50322
Office: 515.440.4544
Owner:City of Waukee Project:Waukee City Hall Renovation
230 W. Hickman Rd. Project No: 19-003
Waukee, IA 50263 Reference No:CR #19
Date: September 2, 2019
Description:
Column Cap Covers per RFI #14 Response
TOTAL:$1,238.00
Accepted by:
City of Waukee
Date:
cc: File (1)
Owner Change Request
Dated: Prepared by: CR-#19Column Caps - RFI 14COST CODE DESCRIPTIONQTY UTLABOR UNIT LABORMATL UNITMATERIAL (w/tax) EQUIP SUB TOTAL01.001 Supervision1 HR 0.00 $70 $0 $0 $0 $0$7007.161 Add Coping Cap to Columns per RFI 14 Response 1LS 0.00 $0 $0 $0 $0 $1,100$1,100$0$0$0 $70 $0 $0 $1,100 $1,170General Liability Insurance0.75%$9Contractor Fee5.00%$59 TOTAL$1,238Signature: Date: Waukee City Hall RenovationSeptember 2, 2019Matt Burch
10550 New York Avenue, Suite 100
Urbandale, IA 50322
Ph: 515.440.4544
To:Emily Naylor, PLA, LEED AP
Shive Hattery
4125 Westown Parkway, Suite 100
West Des Moines, IA 50266
cc:Joe Kurimski, Matt Burch
Subject:Column Enclosure Cap
Drawing:A200, A300, A400 Spec. Section 051200
Cost Impact:TBD Schedule Impact:TBD
Request:Date Reqd:5/22/2019
Requested By:Matt Burch
BallTeam, LLC
Response:
Answered By:
Company:
Date:
RFI # 14
Both steel trusses bear on columns along column line A. Details D3/A400, A3/A400 and Elevation B3/A200, do
not appear to show any kind of cap from the column to the north. It is our understanding from the drawings
the the truss overhang is to be flush with the outside face of columns, but nothing extends from the columns
up to the bottom side of truss. See attached photo for further details.
Install metal flashing to form cap on columns. See sheet RFI14.
Phillip Parrott, Architect
Shive-Hattery
5/21/2019
East Elevation ofColumn Enclosure asdetailed on A3/A400. what are we to do atcap from face of trussout to north, as well asinterior side?
What are we to do to
cap the area shown in
red, no detail shown in
plans? Condition
exists at all 4
locations.
110' - 2"
ROOF
A
METAL FLASHING ON
SELF-ADHERING
WATERPROOFING
5/8" PLYWOOD SHEATHING
WOOD BLOCKING
SEALANT
TRUSS
SIDING ON PLYWODD
SHEATHING SUBSTRATE
METAL STUD FRAMING
110' - 2"
ROOF
2
1
RFI14
METAL FLASHING ON SELF-
ADHERING WATERPROOFING
5/8" PLYWOOD SHEATHING
WOOD BLOCKING
SEALANT
PROJECT NO.
ISSUED FOR SCALEFIELD BOOKAPPROVEDDRAWNDATEREFERENCE DRAWINGIowa | Illinois | Indiana 4125 Westown Pkwy, Suite 100 | West Des Moines, IA 50266515.223.8104 | www.shive-hattery.comXXX XXXAutodesk Revit 20185/21/2019 8:54:07 AMC:\shive\Revit_Local_2019\4182970-A-Cent_pparrott.rvt1 1/2" = 1'-0"4182970 AuthorApproverRFI14WAUKEE CITY HALL RENOVATIONCITY OF WAUKEE230 W. HICKMAN| WAUKEE, IARFI14
01 1/2" = 1'-0"1 COLUMN CAP
1'01 1/2" = 1'-0"2
COLUMN CAP AT
OVERHANG
1'
Invoice
Invoice Date:8/27/2019
Invoice #:3123
Bill To:
Ball Team LLC Construction
2900 Westtown Parkway Suite 240
West Des Moines IA 50266
Whitey Exteriors
Indianola, IA 50125
P.O. Number:
Due Date:8/27/2019
Case:
Total
Balance Due
Payments/Credits
Description Hours/Qty Rate Amount
Waukee City Hall
Nichiha Siding Material and Labor 1 29,500.00 29,500.00
Nichiha Flashing 1 1,280.00 1,280.00
Seamless Gutters and Downspouts 1 4,300.00 4,300.00
Roofing material and labor 1 4,200.00 4,200.00
Extras
Fascia on front Gables material and labor 16 22.00 352.00
Added Framing on bottom of Gables for Gutters 8 55.00 440.00
Additional Nichiha at lower location 1 1,700.00 1,700.00
Brick Flashing 3 12.00 36.00
Soffit Venting and Hardie Material 1 1,860.00 1,860.00
Soffit Venting and Hardie Labor 54 55.00 2,970.00
Column Caps 4 275.00 1,100.00
$47,738.00
$47,738.00
$0.00
Dated: Prepared by: CR-#22PR 007 Response - University Sign LandscapingCOST CODE DESCRIPTIONQTY UTLABOR UNIT LABORMATL UNITMATERIAL (w/tax) EQUIP SUB TOTAL01.001Superintendent Part Time15 HR 0.00 $70 $0 $0 $0 $0$1,05001.002 Pick Up Truck Rental1 WK 0.00 $0 $0 $0 $150 $0$15001.003 Pick Up Truck Fuel1 WK 0.00 $0 $0 $0 $100 $0$10001.011 Project Manager 1 WK 0.00 $750 $0 $0 $0 $0$75001.041 Office Expenses1 WK 0.00 $0 $0 $0 $100 $0$10001.071 Final Clean1 LS 0.00 $500 $0 $0 $0 $0$500$0$002.181 Landscaping1 LS 0.00 $0 $0 $0 $0 $2,250$2,250 - Includes plantings, amended soils, demo, mulch$0and initial watering.$0$0 $1,320 $0 $350 $2,250 $4,900General Liability Insurance0.75%$37Contractor Fee5.00%$247 TOTAL$5,184Signature: Date: Waukee City Hall RenovationSeptember 6, 2019Matt Burch
SHIVE-HATTERY, INC.
PROPOSAL REQUEST
PROJECT: City of Waukee – City Hall Renovation
OWNER: City of Waukee
TO: CONTRACTOR: Ball Team, LLC.
CONTRACT FOR: General Construction
PROPOSAL REQUEST NO: 007
DATE OF ISSUANCE: 08/21/2019
ARCHITECT: Shive-Hattery, Inc.
4125 Westown Pkwy, #100
West Des Moines, IA 50266
ARCHITECT’S PROJECT NO: 418297-0
___________________________________________________________________________________________
Please submit an itemized proposal for changes in the Contract Sum and Contract Time for proposed modifications
to the Contract Documents describe herein.
THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE, OR A DIRECTION TO
PROCEED WITH THE WORK DESCRIBED IN THE PROPOSED MODIFICATIONS.
Description:
Additional scope related to the creation of a planting bed at the new Waukee Community Entrance Sign
installed along University Avenue.
ISSUED BY: Eric Holt
SHIVE-HATTERY, INC.
Eric Holt
Eric B Holt, PLA
Attachments: L000
Copy: Scott Wilmeth, Jace Henderson, Matt Burch – Ball Team
Emily Naylor – Shive-Hattery
Keith Rash & Brad Deets – City of Waukee
8"
8"
SIDEWALK
(5) ARCTIC FIRE REDTWIG DOGWOOD,
# 3 CONTAINER, 4' O.C. SPACING
(39) BLOND AMBITION BLUE GRAMA,
#1 CONTAINER, 1.5' O.C. SPACING
RIGHT OF WAY
PLANTING NOTES:
1.COMPLY WITH APPLICABLE NOTES ON WAUKEE CITY HALL RENOVATION
SHEET C402 ADDITIONAL SITE IMPROVEMENTS LANDSCAPE PLAN.
2.KEEP OPERATIONS WITHIN PUBLIC RIGHT-OF-WAY.
3.COORDINATE CONSTRUCTION ACCESS AND STAGING WITH THE CITY
AND BUSINESS PROPERTY OWNER.
14225 UNIVERSITY
OFFICE BUILDING
PROTECT ALL EXISTING TREES IN
PLACE. MINIMIZE DISTURBANCE
WITHIN CANOPY DRIP LINE.
SIDEWALK
MONUMENT SIGN,
PROTECT N PLACE
8'-0"8'-0"16'-0"INSTALL SPADE-CUT EDGE, TYPICAL
2'-0"(13) MARINA SEDUM,
#1 CONTAINER, 2' O.C. SPACING
LOCATE ELECTRIC CONDUIT AND
IRRIGATION LINES AND PROTECT IN PLACE
UNIVERSITY AVENUE PRIVATE DRIVESCALE
FIELD BOOK
APPROVED
DRAWN
DATE
REVISIONIowa | Illinois | Indiana
4125 Westown Pkwy, Suite 100 | West Des Moines, Iowa 50266
515.223.8104 | www.shive-hattery.com
PROJECT NO.
SHEET NO.File Path:SCALE
FIELD BOOK
APPROVED
DRAWN
DATE
REVISION
PROJECT NO.
SHEET NO.
COMMUNITY ENTRANCE SIGN
PLANTING PLAN
WAUKEE CITY HALL IMPROVEMENTS
14225 UNIVERSITY AVENUE
8/21/2019
EBH
ECN
1"=10'
--
PR-007
4175460, 4182970
L001P:\Projects\DM\4175460\Deliverables\Drawings\1_Civil\C101 SITE PLAN.dwgNORTH
1
Matt Burch
From:Allen Porter <a35po@aol.com>
Sent:Tuesday, September 3, 2019 8:13 AM
To:Matt Burch
Subject:RE: Waukee - Streetscape Sign Plantings
Attachments:image001.jpg
Installation of landscape plantings to include all material, labor, and equipment as needed for 5 Artic fire red twig
dogwoods, 39 Blond ambition blue gramma, 13 marina sedum and hard wood mulch for $1950.00.
Thank you,
Allen Porter
Midwest L&I
Sent from Mail for Windows 10
From: Matt Burch
Sent: Monday, August 26, 2019 12:23 PM
To: Allen Porter
Subject: Waukee - Streetscape Sign Plantings
Allen,
Please see the attached proposal request from the City of Waukee for a different project we are working on for some
landscaping around a new sign.
Can you please provide pricing for the attached?
Thanks,
Matt Burch – mburch@buildwithball.com
P. 515.440.4544 | C. 515.480.7477| F. 515.457.8265
10550 New York Avenue, Suite 100
Urbandale, IA 50322
TEAMWORK Builds Quality
Confidentiality Note: This message is intended only for the named recipient and may contain confidential, proprietary or legally privileged
information. Unauthorized individuals or entities are not permitted access to this information. Any dissemination, distribution, or copying of this
information is strictly prohibited. If you have received this message in error, please advise the sender by reply e-mail, and delete this message and
any attachments.
1
Matt Burch
From:Allen Porter <a35po@aol.com>
Sent:Tuesday, September 3, 2019 6:03 PM
To:Matt Burch
Subject:Re: Waukee - Streetscape Sign Plantings
Add $300 for sod repair and one watering
Sent from my iPhone
On Sep 3, 2019, at 10:03 AM, Matt Burch <MBurch@buildwithball.com> wrote:
Allen – quick do a drive-by and see if there is existing irrigation. Let me know by end of the day today
then I will send in the pricing.
Thanks,
<image001.jpg>
Matt Burch – mburch@buildwithball.com
P. 515.440.4544 | C. 515.480.7477| F. 515.457.8265
10550 New York Avenue, Suite 100
Urbandale, IA 50322
TEAMWORK Builds Quality
Confidentiality Note: This message is intended only for the named recipient and may contain confidential, proprietary or legally
privileged information. Unauthorized individuals or entities are not permitted access to this information. Any dissemination,
distribution, or copying of this information is strictly prohibited. If you have received this message in error, please advise the
sender by reply e-mail, and delete this message and any attachments.
From: Allen Porter <a35po@aol.com>
Sent: Tuesday, September 3, 2019 9:58 AM
To: Matt Burch <MBurch@buildwithball.com>
Subject: RE: Waukee - Streetscape Sign Plantings
We do have removing of turf for the plantings with a natural edge and hard wood mulch soil
amendments as needed.
Sent from Mail for Windows 10
From: Matt Burch
Sent: Tuesday, September 3, 2019 8:58 AM
To: Allen Porter
Subject: RE: Waukee - Streetscape Sign Plantings
Allen,
Do you have included removal of existing sod, amending soils, installing mulch and restoring adjacent
turf?
10550 New York Avenue, Suite 100
Urbandale, IA 50322
Office: 515.440.4544
Owner:City of Waukee Project:Waukee City Hall Renovation
230 W. Hickman Rd. Project No: 19-003
Waukee, IA 50263 Reference No:CR #22
Date: September 6, 2019
Description:
Response to PR 007 - Landscape Plantings at City of Waukee University Sign.
- Includes Plants, Spade edging, removal of sod, amend site soils, and mulch beds, includes initial watering
Pricing Excludes: Import of and soils and irrigation
TOTAL:$5,184.00
Accepted by:
City of Waukee
Date:
cc: File (1)
Owner Change Request