HomeMy WebLinkAbout2018-08-06-H02 Fox Creek Park Phase 2_PHAGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: August 6, 2018
AGENDA ITEM:On proposed plans, specifications, form of contract and estimate of cost
[Fox Creek Park Phase 2 Project]
FORMAT:Public Hearing
SYNOPSIS INCLUDING PRO & CON: The project includes the furnishing of all labor,
equipment, and materials for the construction of an approximately 2,300
SF four season shelter building, sidewalk paving, drive and parking
paving, tennis and pickleball courts, rubber surfacing, playground
equipment, recirculating splash pad equipment with enclosed water
quality management system, parking lot light poles; paved rest areas
incorporating benches, a drinking fountain, and two (2) shade structures;
limited storm sewer, water, gas, and sanitary services; electric
distribution system to supply site lighting and splash pad facility.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Hold Public Hearing.
ATTACHMENTS: I. Notice of Public Hearing
PREPARED BY: Becky Schuett
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION: Dallas County News
DATE OF PUBLICATION: 07/19/2018
H2
NOTICE OF PUBLIC HEARING
FOX CREEK PARK PHASE TWO IMPROVEMENT PROJECT
WAUKEE, IOWA
The City Council of Waukee, Iowa, will hold a public hearing on the proposed Plans,
Specifications, Form of Contract, and Estimate of Costs for the construction of the above
referenced public improvements at 5:30 p.m. on Monday, August 6, 2018 at the Council
Chamber in City Hall, 230 West Hickman Road, Waukee, Iowa 50263. At said hearing, any
interested person may appear and file objections thereto or to the cost of the improvements.
This project includes the furnishing of all labor, equipment, and materials for the construction of
the Fox Creek Park Phase Two Improvements at 522 NE Westgate Drive, Waukee, Iowa,
generally described as follows:
The Fox Creek Park Phase Two improvements include an approximately 2,300 SF four
season shelter building including, but not limited to: modern restrooms, kitchen, storage
and mechanical rooms, assembly space, electric, gas, water, and sanitary service
connections, and drinking fountains.
Site work includes PCC sidewalk paving, PCC drive and parking, PCC tennis and
pickleball courts with painted surfacing and fencing, along with associated earthwork;
transformer and dumpster enclosure wall and gates; poured in place rubber surfacing,
engineered wood fiber playground mulch and playground equipment; integrally colored
PCC spray zone and associated recirculating splash pad equipment with enclosed water
quality management system, underground water tank and debris trap; parking lot light
poles and luminaires; paved rest areas incorporating benches, a drinking fountain, and
two (2) shade structures; landscaping that includes evergreen trees, deciduous overstory
and understory trees, shrubs, sod, seeded lawn, native seed areas, boulders, outcropping,
erosion control rock, and trap rock; bioretention basins with filtration soil and aggregate;
limited storm sewer, water, gas, and sanitary services; electric distribution system to
supply site lighting and splash pad facility.
______________________________
William Peard, Mayor
ATTEST:
________________________________
Rebecca D. Schuett, City Clerk
01495485-1\21938-171