Loading...
HomeMy WebLinkAbout2018-09-04-I03B Lift Station 3 Rehab Phase 1, Control Building_Award ContractAGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: September 4, 2018 AGENDA ITEM:Consideration of approval of a resolution awarding contract [Lift Station No. 3 Rehabilitation Phase 1 Project, Control Building] FORMAT:Resolution SYNOPSIS INCLUDING PRO & CON: The project bid letting was held at Waukee City Hall on August 29, 2018, at 2:00 p.m. Two (2) apparent bids were received, with the low bid submitted by Synergy Contracting of Bondurant, IA, in the amount of $406,000.00. The Engineer’s Estimate of cost for the construction of the project was $320,000.00. The reasons for the difference between the estimate and low bid are due to the contractor including a contingency backup plan to prevent sewer backups into adjacent residences during construction, a wide swing of electrical subcontractor quotes and an increase to the control building price due to additional electrical equipment being added during final design of the project. FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:$406,000.00 COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: City staff recommends awarding contract to Synergy Contracting of Bondurant, IA, in the amount of $406,000.00. RECOMMENDATION: Approve the resolution awarding contract to Synergy Contracting of Bondurant, IA, in the amount of $406,000.00. ATTACHMENTS: I. Proposed resolution II. Veenstra & Kimm, Inc., letter of recommendation III. Bid tabulation PREPARED BY: Becky Schuett REVIEWED BY: I3B RESOLUTION 18- RESOLUTION MAKING AWARD OF CONSTRUCTION CONTRACT FOR THE LIFT STATION NO. 3 REHABILITATION PHASE 1 - CONTROL BUILDING BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WAUKEE, STATE OF IOWA: Section 1. That the following bid for the construction of certain public improvements described in general as the Lift Station No. 3 Rehabilitation Phase 1 - Control Building, described in the plans and specifications heretofore adopted by this Council on September 4, 2018, be and is hereby accepted, the same being the lowest responsive, responsible bid received for such work, as follows: Contractor: Synergy Contracting, LLC, of Bondurant, IA Amount of bid: $406,000.00 Portion of project: All construction work Section 2. That the Mayor and Clerk are hereby directed to execute the contract with the contractor for the construction of the public improvements, such contract not to be binding on the City until approved by this Council. PASSED AND APPROVED this 4th day of September, 2018. Mayor ATTEST: City Clerk