CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: November 5, 2018
AGENDA ITEM:Consideration of approval of Change Order No. 2 to Concrete Connections,
for the Waukee Trailhead and Dog Park project increasing the contract in the
amount of $1,800.00.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Change Order No. 2 to Concrete Connection is for the
installation of a PCC Flume in the front detention basin at the entrance into
the dog park. The area has minimal slope and standing water has been present
in this area the entire summer. The installation of the a PCC flume will allow
the water to flow at minimal slop and will allow for the native seeding and
erosion matting to be installed. This option will additionally provide the city
with a long-term solution to standing water at entrance to the park. The flume
is approximately 90’ long and 3’ wide.
Change order No. 2 also adjusts the Substantial Completion Date from
October 15, 2018 to December 15th, 2018. This is to account for the wet fall
that we have encountered. Attempts at seeding and planting have been
delayed multiple times.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Change Order No. 2
PREPARED BY: Matt Jermier
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
October 16, 2018
Mr. Matt Jermier, Director
Waukee Parks and Recreation Department
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: Change Order #2
Waukee Trailhead and Dog Park
Dear Mr. Jermier:
Attached please find Change Order #2 in the amount of $1,800.00, for approval and signature by
Waukee City Council. Quantities have been reviewed and agreed upon by the contractor, City staff, and
Confluence.
Confluence recommends approval and payment as indicated.
If there are any questions, please let me know.
Respectfully,
Confluence
Matthew O. Carlile, PLA, ASLA. LEED AP
Principal
Waukee Trail Head and Dog Park / 16140-01
Page 1 of 1
CHANGE ORDER
ISSUED TO: Concrete Connection
PROJECT NAME: Waukee Trail Head and Dog Park PROJECT NO.: 16140-01
CHANGE ORDER NO.: 2
CONTRACT FOR: Concrete Connection
CONTRACT DATE: April 2, 2018
INITIATION DATE: July 27, 2018
DESCRIPTION:
During construction, we identified some grading connections that would make the project and surrounding properties drain better. Secondly the
concrete walkway on the West end was significantly higher than design grades exhibited. To adjust sidewalk elevations and connections to the
dog park this area needed to be re-worked.
Original Contract: $ 639,327.50
Change Order #1: $ 8,520.00
Change Order #2: $ 1,800.00
Total Contract: $ 649,647.50
Change Order Summary:
Qty. Description Total
ADD
1. Installation of a PCC Flume in the front detention basin at the entrance to the dog park. The area has minimal slope and standing
water has been present in this area the entire summer. The installation of a PCC flume would allow the water to flow at minimal
slope and would allow us the opportunity to eliminate the mud and complete the native seeding and erosion matting. This option will
additionally provide the city with a long-term solution to standing water at entrance to the park. The proposed flume would be
approximately 90' long and 3' wide.
2. Adjust the Substantial Completion Date from October 15th , 2018 to December 15th, 2018. This is to account for the wet fall that we
have encountered. Attempts at seeding and planting have been delayed several times.
Subtotal $1,800.00
Change Order Issued by:
Matthew O. Carlile, Principal
Printed Name Signature Date
Approved by:
Tim Moerman, City Administrator
Printed Name Signature Date