HomeMy WebLinkAbout2018-11-19-J01L Waukee Trailhead and Dog Park_Pmt Est 6AGENDA ITEM: J1L
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: November 19, 2018
AGENDA ITEM:Consideration of approval of Payment Estimate No. 6 to Concrete
Connections for the Waukee Dog Park and Trailhead Project in the amount of
$24,451.98
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON: Payment Estimate No. 6 to Concrete Connections is for
construction of the restroom facility, sod, benches, dog waste stations, litter
receptacles, and drinking fountains. The quantities completed to date have
been reviewed and agreed upon by the contractor, City of Waukee Staff, and
Confluence.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT: Approve Payment
RECOMMENDATION: Approve the resolution.
ATTACHMENTS: I. Letter of Recommendation
II. Payment Estimate No. 6
PREPARED BY: Matt Jermier
REVIEWED BY:
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
November 14, 2018
Mr. Matt Jermier, Parks and Recreation Director
Parks and Recreation Department
City of Waukee
805 University Avenue
Waukee, IA 50263
RE: Contractor Application for Payment #6
Waukee Community and Dog Park
Dear Mr. Jermier:
Attached please find contractor Application for Payment #6 in the amount of $24,451.98 for approval
and signature by Waukee City Council. Quantities have been reviewed and agreed upon by the
contractor, City staff, and Confluence.
Confluence recommends approval and payment as indicated.
If there are any questions, please let me know.
Respectfully,
Confluence
Matthew O. Carlile, ASLA
Principal
Cc: Project File