HomeMy WebLinkAbout2018-11-19-J01N Alices Rd Corridor Phase 5_Change Order 2AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: November 19, 2018 AGENDA ITEM:Consideration of approval of Change Order No. 2 to Absolute Concrete, Inc. for the Alice’s Road PCC Pavement Widening Project, 400-ft North of SE Olson Drive to NE Horizon Drive, the change order increases the contract price by $23,661.33. FORMAT:Consent Agenda SYNOPSIS INCLUDING PRO & CON: The change order is for: New bid item 8003 for modification to Division 3 Temporary Traffic Signalization to add dedicated left turn onto Hickman Road. New bid item 8004 for modifying the traffic loops on the north leg of SE Alice’s Road at SE Olson Drive New bid item 8005 for adding 1” clean backfill above storm sewer pipes due to saturated conditions FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this Change Order increases the contract price by a total of $23,661.33. COMMISSION/BOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve the consent agenda. ATTACHMENTS: I. Change Order No. 2 II. Letter of Recommendation PREPARED BY:Beth Richardson REVIEWED BY:Rudy Koester PUBLIC NOTICE INFORMATION – NAME OF PUBLICATION: DATE OF PUBLICATION: J1N 8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393 Fax: (515) 254-1642 November 14, 2018 Rudy Koester Director of Public Works 805 University Avenue Waukee, IA 50263 RE: Change Order #2 Alice’s Rd PCC Pavement Widening 400-ft North of SE Olson Drive to NE Horizon Drive STP-U-8177(621)--70-25, STP-A-8177(623)--86-25, CS-TSF-8177(625)--85-25 Dear Mr. Koester: Attached please find a detailed Change Order for City Council approval on November 19, 2018. Change Description  New bid item 8003 for modification to Division 3 Temporary traffic Signalization to add dedicated left turn onto Hickman Road.  New bid item 8004 for modifying the traffic loops on the north leg of SE Alice’s Road at SE Olson Drive.  New bid item 8005 for adding 1” clean backfill above storm sewer pipes due to saturated conditions. We have reviewed the submitted quotes from Absolute Concrete, Inc. and they appear to be in order with current industry pricing for DOT work. If City Staff concurs with this pricing, we recommend the City of Waukee increase the contract price in the amount of $23,661.33 to complete the additional work associated with Change Order #2. Please let me know if you have any questions or need additional information. Sincerely, Foth Infrastructure and Environment, LLC Joshua C. DeBower, P.E. Lead Civil Engineer Encl: Change Order #2 dated 10/31/18 Page 1 of 3 CHANGE ORDER For Local Public Agency Projects Non-Substantial: Substantial: No.:2 Kind of Work:PCC Pavement Widening Accounting ID No. (5-digit number):34975 Project Number:STP-U-8177(621)--70-25 Date Prepared:October 31, 2018Contractor:Absolute Concrete Construction, Inc Local Public Agency:City of Waukee, Iowa Administering Office Concurrence Date Form 831240 (12-15) You are hereby authorized to make the following changes to the contract documents. A - Description of change to be made: 8003 Change- Increase of Division 3 Temporary Traffic Signalization 8004 Change- Add Division 1 Traffic Signalization Modification to SE Olson Drive 8005 Change- Additional Rock Trench Backfill B - Reason for change: 8003 - Modification to the temporary traffic signal to add a permissive left turns onto Hickman Rd, add pedestrian signal heads, and add Luminaires to each temporary pole. 8004 - Existing southbound traffic signal loops for the SE Olson Drive Signal were removed and new loops needed to be installed as well as additional advance detection loops 8005 - Due to continuous rains, material to be used for backfill has a moisture content too high to pass M&D testing so in lieu of importing drier soils, utilizing 1" clean stone the entire trench width as backfill. C - Settlement for cost(s) of change as follows with items addressed in Sections F and/or G: - Modification to temporary traffic signal increases costs by $3,025.00 - Additional Traffic Signal loops increases costs by $10,791.55. - Additional 1" Clean Backfill increases costs by $9,844.78 D - Justification for cost(s) (See I.M. 3.805, Attachment D, Chapter 2.36, for acceptable justification): Refer to attached documentation. E - Contract time adjustment: No Working Days added Working Days added: Unknown at this time Justification for selection: Due to circumstances outside the contractor's control, two utility companies were unable to relocate their existing facilities into the City's Joint Utility Trench for 31 days which delayed the contractor from installing critical storm sewer. 2018 Construction year also incurred above average rain days. Exact working days to be added will be determined at a later date. Page 2 of 3 Form 831240 (12-15) Accounting ID No.(5-digit number):34975 Change Order No.:2 F - Items included in contract: Participating For deductions enter as "-x.xx" Federal- aid State- aid Line Number Item Description Unit Price .xx Quantity .xxx Amount .xx Add Row Delete Row TOTAL G - Items not included in contract: Page 3 of 3 Participating For deductions enter as "-x.xx" Federal- aid State- aid Change Number Item Description Unit Price .xx Quantity .xxx Amount .xx 8003 (2528-8400256) Temporary Traffic Signals $3,025.00 1.000 $3,025.00 8004 (2525-0000100) Traffic Signalization ( SE Olson Dr $10,791.55 1.000 $10,791.55 8005 (2599-9999020) 1" Clean Backfill $45.98 214.110 $9,844.78 Add Row Delete Row TOTAL $23,661.33 H. Signatures Agreed: Contractor Date Recommended: Project Engineer Date Approved: Person in Responsible Charge Date Other (optional) Title Date Contracting Authority (optional) Date Other (optional) Title Date Iowa DOT Administering Office Date Approval is contingent upon funds being available under the existing project agreement or upon additional Federal-aid funds being made available by a modified project agreement. FHWA Concurrence: Federal Highway Division Administration Date (if required) DISTRIBUTION (after fully executed on LPA projects): Original - Finance; Copies - Contractor, Project Engineer, Contracting Authority, Administering Office. Date distributed: Initials: Absolute Concrete Construction, Inc. PO Box 148 505 1st Avenue Phone:(515) 228-3030 Slater, IA 50248 Fax: (515) 228-3031 Project: To: Description of Proposed Change: Item Quantity Units Unit Price Amount CO2.1 2 EA 487.50$ 975.00$ CO2.2 4 EA 262.50$ 1,050.00$ CO2.3 2 EA 362.50$ 725.00$ Sub-Total: Mark Up Total: Accepted: By: By: Date: Date: Description Pricing to add flashing yellow arrow for northbound and southbound Alice's Rd traffic. Change Order Proposal Date: 8/16/18Alice's Rd Corridor Widening Phase 5 Job Number: ACC18-003 Change Order Proposal Number: 2 City of Waukee 3,025.00$ 275.00$ 2,750.00$ Flashing Yellow Arrow Luminaires Ped. Signals 0 City of Waukee Absolute Concrete Construction, Inc. Additional Days Requested: Absolute Concrete Construction, Inc. PO Box 148 505 1st Avenue Phone:(515) 228-3030 Slater, IA 50248 Fax: (515) 228-3031 Project: To: Description of Proposed Change: Item Quantity Units Unit Price Amount CO3.1 150 LF 1.00$ 150.00$ CO3.2 1 LS 500.00$ 500.00$ CO3.3 150 LF 1.00$ 150.00$ CO3.4 150 LF 6.00$ 900.00$ CO3.5 3 EA 1,000.00$ 3,000.00$ CO3.6 108 LF 6.00$ 648.00$ CO3.7 1 EA 975.00$ 975.00$ CO3.8 3 EA 1,000.00$ 3,000.00$ CO3.9 390 LF 1.25$ 487.50$ -$ -$ Sub-Total: Mark Up Total: Accepted: By: By: Date: Date: 0 City of Waukee Absolute Concrete Construction, Inc. Additional Days Requested: 10,791.55$ 981.05$ 9,810.50$ Remove Cable Reset Handhole Reinstall Cable Replace 2" Conduit Install 2" Conduit Install New Type 1 HH Loop Detectors Loop Lead Cable Description Recut Traffic Loop Detectors Pricing to remove cable, reset handhole, and replace traffic loops on Alice's Rd North of Olson Drive, on the West side. Change Order Proposal Date: 9/14/18Alice's Rd Corridor Widening Phase 5 Job Number: ACC18-003 Change Order Proposal Number: 3 City of Waukee Absolute Concrete Construction, Inc. PO Box 148 505 1st Avenue Phone:(515) 228-3030 Slater, IA 50248 Fax: (515) 228-3031 Project: To: Description of Proposed Change: Item Units Unit Price Mark-Up CO5.1 TON 41.80$ 45.98$ Accepted: By:By: Date:Date: City of Waukee Description Change Order Proposal Date: 10/19/18Alice's Rd Corridor Widening Phase 5 Job Number: ACC18-003 Change Order Proposal Number: 5 1" Clean Backfill Pricing for 1" clean backfill for pipe trench in lieu of dirt backfill. City of Waukee Absolute Concrete Construction, Inc.