HomeMy WebLinkAbout2018-11-19-J01N Alices Rd Corridor Phase 5_Change Order 2AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: November 19, 2018
AGENDA ITEM:Consideration of approval of Change Order No. 2 to Absolute Concrete,
Inc. for the Alice’s Road PCC Pavement Widening Project, 400-ft North
of SE Olson Drive to NE Horizon Drive, the change order increases the
contract price by $23,661.33.
FORMAT:Consent Agenda
SYNOPSIS INCLUDING PRO & CON:
The change order is for:
New bid item 8003 for modification to Division 3 Temporary Traffic Signalization to add
dedicated left turn onto Hickman Road.
New bid item 8004 for modifying the traffic loops on the north leg of SE Alice’s Road at
SE Olson Drive
New bid item 8005 for adding 1” clean backfill above storm sewer pipes due to saturated
conditions
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: The net result of this
Change Order increases the contract price by a total of $23,661.33.
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the consent agenda.
ATTACHMENTS: I. Change Order No. 2
II. Letter of Recommendation
PREPARED BY:Beth Richardson
REVIEWED BY:Rudy Koester
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
J1N
8191 Birchwood Court, Suite L Johnston, IA 50131 Phone: (515) 254-1393 Fax: (515) 254-1642
November 14, 2018
Rudy Koester
Director of Public Works
805 University Avenue
Waukee, IA 50263
RE: Change Order #2
Alice’s Rd PCC Pavement Widening
400-ft North of SE Olson Drive to NE Horizon Drive
STP-U-8177(621)--70-25, STP-A-8177(623)--86-25, CS-TSF-8177(625)--85-25
Dear Mr. Koester:
Attached please find a detailed Change Order for City Council approval on November 19, 2018.
Change Description
New bid item 8003 for modification to Division 3 Temporary traffic Signalization to add
dedicated left turn onto Hickman Road.
New bid item 8004 for modifying the traffic loops on the north leg of SE Alice’s Road at SE
Olson Drive.
New bid item 8005 for adding 1” clean backfill above storm sewer pipes due to saturated
conditions.
We have reviewed the submitted quotes from Absolute Concrete, Inc. and they appear to be in order with
current industry pricing for DOT work. If City Staff concurs with this pricing, we recommend the City of
Waukee increase the contract price in the amount of $23,661.33 to complete the additional work
associated with Change Order #2.
Please let me know if you have any questions or need additional information.
Sincerely,
Foth Infrastructure and Environment, LLC
Joshua C. DeBower, P.E.
Lead Civil Engineer
Encl: Change Order #2 dated 10/31/18
Page 1 of 3
CHANGE ORDER
For Local Public Agency Projects
Non-Substantial:
Substantial:
No.:2
Kind of Work:PCC Pavement Widening
Accounting ID No. (5-digit number):34975 Project Number:STP-U-8177(621)--70-25
Date Prepared:October 31, 2018Contractor:Absolute Concrete Construction, Inc
Local Public Agency:City of Waukee, Iowa
Administering Office
Concurrence Date
Form 831240 (12-15)
You are hereby authorized to make the following changes to the contract documents.
A - Description of change to be made:
8003 Change- Increase of Division 3 Temporary Traffic Signalization
8004 Change- Add Division 1 Traffic Signalization Modification to SE Olson Drive
8005 Change- Additional Rock Trench Backfill
B - Reason for change:
8003 - Modification to the temporary traffic signal to add a permissive left turns onto Hickman Rd, add pedestrian signal heads, and
add Luminaires to each temporary pole.
8004 - Existing southbound traffic signal loops for the SE Olson Drive Signal were removed and new loops needed to be installed as
well as additional advance detection loops
8005 - Due to continuous rains, material to be used for backfill has a moisture content too high to pass M&D testing so in lieu of
importing drier soils, utilizing 1" clean stone the entire trench width as backfill.
C - Settlement for cost(s) of change as follows with items addressed in Sections F and/or G:
- Modification to temporary traffic signal increases costs by $3,025.00
- Additional Traffic Signal loops increases costs by $10,791.55.
- Additional 1" Clean Backfill increases costs by $9,844.78
D - Justification for cost(s) (See I.M. 3.805, Attachment D, Chapter 2.36, for acceptable justification):
Refer to attached documentation.
E - Contract time adjustment: No Working Days added Working Days added: Unknown at this time
Justification for selection:
Due to circumstances outside the contractor's control, two utility companies were unable to relocate their existing facilities into the
City's Joint Utility Trench for 31 days which delayed the contractor from installing critical storm sewer. 2018 Construction year also
incurred above average rain days. Exact working days to be added will be determined at a later date.
Page 2 of 3
Form 831240 (12-15)
Accounting ID No.(5-digit number):34975
Change Order No.:2
F - Items included in contract:
Participating For deductions enter as
"-x.xx"
Federal-
aid
State-
aid
Line
Number Item Description Unit Price
.xx
Quantity
.xxx
Amount
.xx
Add Row Delete Row TOTAL
G - Items not included in contract:
Page 3 of 3
Participating For deductions enter as
"-x.xx"
Federal-
aid
State-
aid
Change
Number Item Description Unit Price
.xx
Quantity
.xxx
Amount
.xx
8003 (2528-8400256) Temporary Traffic Signals $3,025.00 1.000 $3,025.00
8004 (2525-0000100) Traffic Signalization ( SE Olson Dr $10,791.55 1.000 $10,791.55
8005 (2599-9999020) 1" Clean Backfill $45.98 214.110 $9,844.78
Add Row Delete Row TOTAL $23,661.33
H. Signatures
Agreed:
Contractor Date
Recommended:
Project Engineer Date
Approved:
Person in Responsible Charge Date Other (optional) Title Date
Contracting Authority (optional) Date Other (optional) Title Date
Iowa DOT Administering Office Date
Approval is contingent upon funds being available under the existing project agreement or upon additional Federal-aid funds being made available by a
modified project agreement.
FHWA Concurrence:
Federal Highway Division Administration Date
(if required)
DISTRIBUTION (after fully executed on LPA projects): Original - Finance; Copies - Contractor, Project Engineer, Contracting Authority, Administering Office.
Date distributed: Initials:
Absolute Concrete Construction, Inc.
PO Box 148
505 1st Avenue Phone:(515) 228-3030
Slater, IA 50248 Fax: (515) 228-3031
Project:
To:
Description of Proposed Change:
Item Quantity Units Unit Price Amount
CO2.1 2 EA 487.50$ 975.00$
CO2.2 4 EA 262.50$ 1,050.00$
CO2.3 2 EA 362.50$ 725.00$
Sub-Total:
Mark Up
Total:
Accepted:
By: By:
Date: Date:
Description
Pricing to add flashing yellow arrow for northbound and southbound Alice's Rd traffic.
Change Order Proposal
Date: 8/16/18Alice's Rd Corridor Widening Phase 5
Job Number: ACC18-003
Change Order Proposal Number: 2
City of Waukee
3,025.00$
275.00$
2,750.00$
Flashing Yellow Arrow
Luminaires
Ped. Signals
0
City of Waukee Absolute Concrete Construction, Inc.
Additional Days Requested:
Absolute Concrete Construction, Inc.
PO Box 148
505 1st Avenue Phone:(515) 228-3030
Slater, IA 50248 Fax: (515) 228-3031
Project:
To:
Description of Proposed Change:
Item Quantity Units Unit Price Amount
CO3.1 150 LF 1.00$ 150.00$
CO3.2 1 LS 500.00$ 500.00$
CO3.3 150 LF 1.00$ 150.00$
CO3.4 150 LF 6.00$ 900.00$
CO3.5 3 EA 1,000.00$ 3,000.00$
CO3.6 108 LF 6.00$ 648.00$
CO3.7 1 EA 975.00$ 975.00$
CO3.8 3 EA 1,000.00$ 3,000.00$
CO3.9 390 LF 1.25$ 487.50$
-$
-$
Sub-Total:
Mark Up
Total:
Accepted:
By: By:
Date: Date:
0
City of Waukee Absolute Concrete Construction, Inc.
Additional Days Requested:
10,791.55$
981.05$
9,810.50$
Remove Cable
Reset Handhole
Reinstall Cable
Replace 2" Conduit
Install 2" Conduit
Install New Type 1 HH
Loop Detectors
Loop Lead Cable
Description
Recut Traffic Loop Detectors
Pricing to remove cable, reset handhole, and replace traffic loops on Alice's Rd North of Olson Drive, on the West side.
Change Order Proposal
Date: 9/14/18Alice's Rd Corridor Widening Phase 5
Job Number: ACC18-003
Change Order Proposal Number: 3
City of Waukee
Absolute Concrete Construction, Inc.
PO Box 148
505 1st Avenue Phone:(515) 228-3030
Slater, IA 50248 Fax: (515) 228-3031
Project:
To:
Description of Proposed Change:
Item Units Unit Price Mark-Up
CO5.1 TON 41.80$ 45.98$
Accepted:
By:By:
Date:Date:
City of Waukee
Description
Change Order Proposal
Date: 10/19/18Alice's Rd Corridor Widening Phase 5
Job Number: ACC18-003
Change Order Proposal Number: 5
1" Clean Backfill
Pricing for 1" clean backfill for pipe trench in lieu of dirt backfill.
City of Waukee Absolute Concrete Construction, Inc.