AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: January 3, 2017
AGENDA ITEM: Consideration of approval of a Contract Modification No. 26 to the Iowa
Department of Transportation for the 105"' Street/Alice's Road I-80 Interchange
Project with a increase in the contract of $69,867.36.
FORMAT: Resolution
SYNOPSIS INCLUDING PRO & CON:
Reason:
Additional revetment was required to stabilize the roadway ditch along Ramp C in the NW corner of the
interchange. The drainage from Grand Prairie Parkway storm sewer was causing erosion in the ditch.
Class B revetment was the only material available within a reasonable haul distance.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
Increase the contract by $69,867.36 —The City of Waukee's portion of the change order is $34,933.68
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve Contract Modification No. 26 to the Iowa Department of
Transportation for the I05"' Street/Alice's Road I-80 Interchange Project with a
net increase in the contract of $69,867.36.
ATTACHMENTS: I. Contract Modification 26
PREPARED BY: Beth Richardson
REVIEWED BY: John Gibson
X/I
PUBLIC NOTICE INFORMATION —
NAME OF PUBLICATION:
DATE OF PUBLICATION:
GJContract Modification
Iowa Department of Transportation
Contract: 25.0803.175, PCC PAVEMENT - GRADE AND NEW
12/20/2016 11:16 AM
Field Manager 5.3a
Cont. Mod.
Number
26
Revision
Number
Cont. Mod.
Date
12/20/2016
Net Change
$69,867.36
Awarded ContractAmount
$13,423,922.46
Route
Entered By
HWY 1-80 (C31912)
Jennifer Strunk
Contract Location
DALLAS IMN-080-3(175)119-0E-25
Short Description
Add Item
Description of Changes
SUBSTANTIAL CONCURRENCE DATE: 8/25/16
Add Item: Revetment, Class B
New Items
Project: 25-0803-175, 140819 009 NTF
Category: 0001, N: ROADWAY ITEMS
Item Description Item Code Prop.Ln. ItemType Unit Proposed Qty. Unit Rice Dollar Value
REVETMENT, CL B 2507-6800021 1896 SUPPLEMENT TON 1,455.570 48.00000 $69,867.36
Reason: Additional revetment was required to stabilize the roadway ditch along Ramp C in the NW corner of the interchange. The
drainage from Grand Prairie Parkway storm sewer was causing erosion in the ditch. Class B revetment was the only material
available within a reasonable haul distance.
Justification of Costs: These prices are comparable to the Summary of Awarded Prices.
Subtotal for Category 0001: $69,867.36
Subtotal for Project 25-0803-175: $69,867.36
When authorized, the contractor agrees to perform the work outlined above in accordance with provisions of the contract
documents.
Contract: 25-0803-175 Cont. Mod.: 26 Page 1 of 1