HomeMy WebLinkAbout2017-03-06-J01P Fox Creek Trunk Sewer Phase 3 - Approve Contract, Bond AGENDA ITEM:
CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: March 6, 2017
AGENDA ITEM: Consideration of approval of a resolution approving contract, bond [Fox
Creek Trunk Sewer Phase 3 Project]
FORMAT: Resolution
SYNOPSIS INCLUDING PRO & CON:
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS: $583,778.00
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Approve the resolution approving contract and bond with Graff
Excavating of Toledo, IA, in the amount of $583,778.00.
ATTACHMENTS: I. Proposed resolution
II. Contract, Bond
PREPARED BY: Becky Schuett
REVIEWED BY:
RESOLUTION 17-
RESOLUTION APPROVING CONSTRUCTION CONTRACT
AND BOND FOR THE FOX CREEK TRUNK SEWER - PHASE
3
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WAUKEE, STATE
OF IOWA:
That the construction contract and bond executed and insurance coverage for the
construction of certain public improvements described in general as the Fox Creek Trunk Sewer
- Phase 3, and as described in detail in the plans and specifications heretofore approved, and
which have been signed by the Mayor and Clerk on behalf of the City be and the same are
hereby approved as follows:
Contractor:
Graff Excavating
of
Toledo, IA
Amount of bid:
$583,778.00
Bond surety:
Granite Re, Inc.
Date of bond:
March 1, 2017
Portion of project:
All construction work
PASSED AND APPROVED this 6th day of March, 2017.
Mayor
ATTEST:
City Clerk