CITY OF WAUKEE, IOWA
CITY COUNCIL MEETING COMMUNICATION
MEETING DATE: May 1, 2017
AGENDA ITEM: On proposed plans, specifications, form of contract and estimate of cost
[SE Esker Ridge Drive, Grand Prairie Parkway to SE Glacier Trail, RISE
Project]
FORMAT: Public Hearing
SYNOPSIS INCLUDING PRO & CON: The SE Esker Ridge Drive construction includes
approximately 45,000 cubic yards of excavation, 6,190 square yards of
subgrade preparation, 5,650 square yards of PCC paving, 80 square yards
of PCC sidewalk and shared use path, 1,300 linear feet of water main,
1900 linear feet of sewer, 15 sewer structures 1 flared end section, 1200
linear feet of subdrain, pavement markings, erosion control, surface
restoration, and cleanup.
FISCAL IMPACT INCLUDING COST/BENEFIT ANALYSIS:
COMMISSION/BOARD/COMMITTEE COMMENT:
STAFF REVIEW AND COMMENT:
RECOMMENDATION: Hold Public Hearing.
ATTACHMENTS: I. Notice of Hearing and Letting
PREPARED BY: Beth Richardson
REVIEWED BY: John Gibson
PUBLIC NOTICE INFORMATION –
NAME OF PUBLICATION:
DATE OF PUBLICATION:
NOTICE OF PUBLIC HEARING
NPH - 1
SE ESKER RIDGE DRIVE
GRAND PRAIRIE PARKWAY TO SE GLACIER TRAIL
WAUKEE, IOWA
RISE PROJECT NO. RM-8177(620)--9D-25
The City Council of Waukee, Iowa, will hold a public hearing on the proposed Plans,
Specifications, Form of Contract, and Estimate of Costs for the construction of the above
referenced public improvements at 5:30 p.m. on Monday, May 1, 2017 at the Council Chamber
in City Hall, 230 West Hickman Road, Waukee, Iowa 50263. At said hearing, any interested
person may appear and file objections thereto or to the cost of the improvements.
This project includes the furnishing of all labor, equipment, and materials for the construction of
the SE Esker Ridge Drive improvements from Grand Prairie Parkway to SE Glacier Trail in
Waukee, generally described as follows:
Construct the SE Esker Ridge Drive including all materials, labor and equipment
necessary for installation of approximately: 45,000 CY of excavation, 6,190 SY of
subgrade preparation, 5,650 SY of PCC paving, 80 SY of PCC sidewalk and shared
use path, 1,300 LF of water main, 1900 LF of sewer, 15 EA sewer structures, 1 EA
flared end sections, 1200 LF of subdrain, pavement markings, erosion control,
surface restoration and miscellaneous related work and appurtenances.
William F. Peard, Mayor
ATTEST:
Rebecca D. Schuett, City Clerk
Publish: April 20, 2017