HomeMy WebLinkAbout2017-05-15-J01S NW Area Trunk Sewer Extension Phase 1_Change Order 5►f►4 Waukee •���� THE KEY TO GOOD LIVING AGENDA ITEM: CITY OF WAUKEE, IOWA CITY COUNCIL MEETING COMMUNICATION MEETING DATE: May 15, 2017 AGENDA ITEM: Consideration of approval of Change Order No. 5 to Rognes Corp. for the Northwest Area Trunk Sewer Extension — Phase I Improvements Project decreasing the contract in the amount by $30,461.49 FORMAT: Consent Agenda SYNOPSIS INCLUDING PRO & CON: The change order is to delete the original payment item for irrigation repairs across Sugar Creek Golf Course and to add a deduct for irrigation repairs completed by others. Change Order No. 5 is also to adjust the plan quantities to the as -constructed quantities. FISCAL IMPACT INCLUDING COSTBENEFIT ANALYSIS: The net result of this Change Order decreases the contract price by $30,461.49. COMMISSIONBOARD/COMMITTEE COMMENT: STAFF REVIEW AND COMMENT: RECOMMENDATION: Approve the consent agenda. ATTACHMENTS: 1. Change Order No. 5 11. Veenstra & Kimm Letter of Recommendation PREPARED BY: Beth Richardson v_ REVIEWED BY: John Gibson // PUBLIC NOTICE INFORMATION NAME OF PUBLICATION: DATE OF PUBLICATION: VEENSTRA & KIMM, INC. 3000 Westown Parkway • West Des Moines, Iowa 50266-1320 515-225-8000 •515-225-7848(FAX9 •800-241-8000 (WATS) i. May 10, 2017 John R. Gibson Public Works Director City of Waukee 805 University Avenue Waukee, Iowa 50263 WAUKEE, IOWA NORTHWEST AREA TRUNK SEWER EXTENSION — PHASE 1 CHANGE ORDER NOS. 5 AND 6 PARTIAL PAYMENT ESTIMATE NO. 5 (FINAL) Enclosed are three copies each of Change Order Nos. 5 and 6 for the Northwest Area Trunk Sewer Extension — Phase 1 project under the contract between the City of Waukee and Rognes Corp. Change Order No. 5 is to delete the original payment item for irrigation repairs across Sugar Creek Golf Course and to add a deduct for irrigation repairs completed by others. Change Order No. 5 is also to adjust the plan quantities to the as -constructed quantities. Change Order No. 5 decreases the contract price by a total of $30,461.49. Change Order No. 6 is to compensate the Rognes Corp. for downtime during the installation of the bore under the creek at the east end of the golf course. Change Order No. 6 increases the contract price by a total of $9,101.40. Veenstra & Kimm, Inc. recommends approval of Change Order Nos. 5 and 6. Also enclosed are three copies of Partial Payment Estimate No. 5 (Final) for the period between March 11, 2017 and April 28, 2017 for the above mentioned project. Partial Payment Estimate No. 5 (Final) is for seeding and erosion control. We have checked the estimate and recommend payment by the City Council of the City of Waukee to Rognes Corp. in the amount of $5,890.00. Partial Pay Estimate No. 5 (Final) also provides that 30 days after the acceptance of the project, the retainage in the amount of $49,314.20 will be paid to Rognes Corp. provided it has submitted the necessary documentation. Please sign all copies of Change Order Nos. 5 and 6 and Partial Payment Estimate No. (Final) in the spaces provided. Return one signed copy of each to our office and one signed copy of each to Rognes Corp. The remaining copy of each is for the City of Waukee's records. West Des Moines, IA • Coralville, IA • Mason City, IA •Sioux City, IA • Moline, IL •Springfield, IL • Liberty, MO John R. Gibson May 10, 2017 Page 2 If you have any questions or comments, please contact us at 225-8000. VEENSTRA & KIMM, INC. Jordan Kappos JDK 275205-1 cc: Rudy Koester, City of Waukee (via e-mail) Becky Schuett, City of Waukee (via e-mail) Beth Richardson, City of Waukee (via e-mail) VEENSTRA & KIMM, INC. 3000 Westown Parkway • West Des Moines, Iowa 50266-1320 515-225-8000 • 515-225-7848(PAX) • 800-241-8000(WATS) May 1, 2017 CHANGE ORDER NO. 5 WAUKEE, IOWA NORTHWEST AREA TRUNK SEWER EXTENSION - PHASE 1 Change Order No. 5 is to delete the original payment item for irrigation repairs across Sugar Creek Golf Course and add a deduct for irrigation repairs completed by others. Change Order No. 5 is also to adjust the plan quantities to the as -constructed quantities. It includes the following items: Item Estimated Completed Price No. Description Unit Quantity Quantity Unit Price Adjustment 1.3 Granular Surfacing 1 310 305.27 $24.00 ($113.52) 1.5 Irrigation System Repair 1 1 0 $5,000.00 ($5,000.00) 1.6 6" PCCTrai1 1 510 413 $60.00 ($5,820.00) 1.7 12" PVC Sanitary Sewer 1 1420 1422 $55.00 $110.00 Pipe in Place 1.9 24" Sanitary Sewer Pipe 1 1380 1378 $72.00 ($144.00) in Place 1.10 36" Sanitary Sewer 1 145 120 $595.00 ($14,875.00) Augered in Place in Steel Casing 1.11 36" Sanitary Sewer Pipe 1 1223.5 1237 $170.00 $2,295.00 in Place 1.15 48" Manhole Extra 1 9 6 $315.00 ($945.00) Depth 1.16 60" Manhole Extra 1 29 30.75 $635.00 $1,111.25 Depth 1.17 Rip -Rap 1 34 96.74 $72.00 $4,517.28 1.25 15" Dual Wall Pipe in 1 400 390 $34.00 ($340.00) Place 1.30 36" Sanitary Sewer 1 282.5 286 $25.00 $87.50 Removal 275205-1 Page 1 of 2 1.31 Remove and Replace 24" RCP Storm Sewer 1 295 240 $90.00 ($4,950.00) 1.35 Temporary Stabilization - Hydromulch LS 3.43 2.5 $1,500.00 ($1,395.00) 1.36 Irrigation Deduct LS 0 1 ($5,000.00) ($5,000.00) Total ($30,461.49) Change Order No. 5 decreases the contract price by a total of $30 461 49 ROGNES CORP. CITY OF WAUKEE, IOWA By N/�..tc _ / zr� By. Title Tit Date Date VEENSTRA & KIMM, INC. ATTEST: By Title Project Engineer Date �J 1102ol, 0 Date 275205-1 Page 2 of 2